In Matter of Electronic Missile Facilities, Inc., 20 A.D.2d 891, 248 N.Y.S.2d 944 (1964); Unipak Aviation Corp. v. Mantell, 20 Misc.2d 1078, 196 N.Y.S.2d 126 (Sup.Ct.N.Y.Co. 1959). It sets forth among other things the failure to sign Addendum No. 27, the claimed adjustment of the premium rate, and the period for which the adjustment is claimed.

Summary of this case from American Home Assurance Co. v. American Fidelity & Casualty Co.

Opinion

April 30, 1964


Order, entered on August 13, 1963, granting petitioner-respondent's motion to compel arbitration and appointing an arbitrator, unanimously reversed, on the law, without costs to any party, and the petition dismissed, with leave to petitioner to amend the petition to set forth a proper dispute and demand under the agreement in question. The executed written agreement providing for arbitration of "Any controversy or claim arising out of or relating to this agreement or the breach thereof" is sufficient to include questions of continued existence of the agreement itself (see 6 Weinstein-Korn-Miller, N Y Civ. Prac., pars. 7501.23, 7503.02). However, the petition does not state the nature of any arbitrable dispute, as distinguished from asserting merely that there is a dispute. This is insufficient (see Matter of Unipak Aviation Corp. [ Mantell], 20 Misc.2d 1078).

Concur — Botein, P.J., Breitel, Valente, Stevens and Eager, JJ.


Summaries of

Matter of Elec. Missile Facilities, Inc.

Appellate Division of the Supreme Court of New York, First Department
Apr 30, 1964
20 A.D.2d 891 (N.Y. App. Div. 1964)

In Matter of Electronic Missile Facilities, Inc., 20 A.D.2d 891, 248 N.Y.S.2d 944 (1964); Unipak Aviation Corp. v. Mantell, 20 Misc.2d 1078, 196 N.Y.S.2d 126 (Sup.Ct.N.Y.Co. 1959). It sets forth among other things the failure to sign Addendum No. 27, the claimed adjustment of the premium rate, and the period for which the adjustment is claimed.

Summary of this case from American Home Assurance Co. v. American Fidelity & Casualty Co.
Case details for

Matter of Elec. Missile Facilities, Inc.

Case Details

Full title:In the Matter of the Arbitration between ELECTRONIC MISSILE FACILITIES…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Apr 30, 1964

Citations

20 A.D.2d 891 (N.Y. App. Div. 1964)

Citing Cases

State Farm Mutual Automobile Ins. Co. v. Szwec

Moreover, the letter is totally devoid of any information as to why arbitration is required, other than that…

Matter of Steinberg

Rather than attempting to reframe the demand by drastic modification thereof, it is preferable that…