From Casetext: Smarter Legal Research

Massachusetts Elec. Sys. v. Granger Sons

Appeals Court of Massachusetts
Jun 22, 1992
594 N.E.2d 545 (Mass. App. Ct. 1992)

Summary

concluding that surety can be forced into arbitration through incorporation by reference clause in bond

Summary of this case from C & I Steel, LLC v. Travelers Casualty & Surety Co. of America

Opinion

No. 91-P-625.

June 22, 1992.

Arbitration, Stay of judicial proceedings. Contract, Arbitration, Construction contract, Subcontract.

Charles A. Plunkett for the defendant.

Martin Fisch for the plaintiff.


The plaintiff, a subcontractor subject to G.L.c. 149, § 44F, brought an action against the defendant general contractor (Granger) and its surety alleging breach of contract with respect to the construction of a school for the town of Harwich. Granger filed an answer and a motion to stay the action and compel arbitration. This appeal is from the denial of Granger's motion. See G.L.c. 251, § 18. We reverse.

United States Fidelity and Guaranty Company. The surety is not a party to this appeal.

The construction contract between Granger and the town included an arbitration provision, and by virtue of the statutory form of subcontract required by G.L.c. 149, § 44F(4)( c) (1988 ed.), set forth in the margin, the provisions of the contract between Granger and the town were incorporated into the subcontract. See Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274, 275 (6th Cir. 1984), and Maxum Foundations, Inc. v. Salus Corp., 779 F.2d 974, 979, 980 (4th Cir. 1985), where, on almost identical language, the court held the subcontractor bound by the arbitration clause in the prime contract.

The "General Conditions of the Contract for Construction" of the American Institute of Architects (AIA), AIA document A201 (1976) was part of the contract. The arbitration provision is § 7.9.1, which in relevant part provides as follows:
"All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof, except as provided in Subparagraph 2.2.11 with respect to the Architect's decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraphs 9.9.4 and 9.9.5, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. . . . The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof."

"(a) The Subcontractor agrees to be bound to the Contractor by the terms of the hereinbefore described plans; specifications (including all general conditions stated therein) and addenda No. ___, and ___, and ___, and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the ___ (Awarding Authority) hereinafter called the "Awarding Authority," except to the extent that provisions contained therein are by their terms or by law applicable only to the Contractor.
"(b) The Contractor agrees to be bound to the Subcontractor by the terms of the hereinbefore described documents and to assume to the Subcontractor all the obligations and responsibilities that the Awarding Authority by the terms of the hereinbefore described documents assumes to the Contractor, except to the extent that provisions contained therein are by their terms or by law applicable only to the Awarding Authority."

Buttressed by the "strong public policy favoring arbitration as an expeditious alternative to litigation for settling commercial disputes," Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. 160, 161, 163 (1981), courts generally hold that where a subcontract (or a performance bond) incorporates the prime contract, the subcontractor (or the surety) is bound by an arbitration clause contained in the prime contract. See, e.g., Kearsarge Metallurgical Corp. v. Peerless Ins. Co., 383 Mass. 162, 166-167, 170 and 167 n. 8 (1981) (construing New Hampshire law but where there was no specific New Hampshire case on point); Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d at 276; Maxum Foundations, Inc. v. Salus Corp., 779 F.2d at 980; United States Fid. Guar. Co. v. W. Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir. 1988); Thomas O'Connor Co. v. Insurance Co. of N. Am., 697 F. Supp. 563 (D. Mass. 1988); Hoffman v. Fidelity Deposit Co., 734 F. Supp. 192, 194-195 (D.N.J. 1990). See also Uniroyal, Inc. v. A. Epstein Sons, 428 F.2d 523, 526-527 (7th Cir. 1970); Compania Espanola de Petroleos v. Nereus Shipping, 527 F.2d 966, 973-74 (2d Cir. 1975), cert. denied, 426 U.S. 936 (1976); Acret, Construction Arbitration Handbook § 5.05 (1985 1991 Supp.), and cases cited. The plaintiff has presented no meritorious reason to apply a different rule here.

Accordingly, the parties should have been directed to proceed to arbitration, and the action should have been stayed. See G.L.c. 251, §§ 2( a) and 2( d); Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. at 161-162. The order denying a stay of the action is reversed, and the matter is remanded to the Superior Court for the entry of an order directing the parties to proceed to arbitration.

So ordered.


Summaries of

Massachusetts Elec. Sys. v. Granger Sons

Appeals Court of Massachusetts
Jun 22, 1992
594 N.E.2d 545 (Mass. App. Ct. 1992)

concluding that surety can be forced into arbitration through incorporation by reference clause in bond

Summary of this case from C & I Steel, LLC v. Travelers Casualty & Surety Co. of America
Case details for

Massachusetts Elec. Sys. v. Granger Sons

Case Details

Full title:MASSACHUSETTS ELECTRICAL SYSTEMS, INC. vs. R.W. GRANGER SONS, INC

Court:Appeals Court of Massachusetts

Date published: Jun 22, 1992

Citations

594 N.E.2d 545 (Mass. App. Ct. 1992)
594 N.E.2d 545

Citing Cases

Wellesley v. D C Constr. Comp., No

Indeed, If, as alleged in this case, the owners specifications are incorporated into the contract between D C…

Travelers Surety v. Long Bay

Id. at 914. See Massachusetts Elec. Sys., Inc. v. R.W. Granger Sons, 32 Mass. App. Ct. 982, 983 (1992)…