Macalloy Corporation v. Metallurg, Inc.

Appellate Division of the Supreme Court of New York, First Department
Jun 21, 2001
284 A.D.2d 227 (N.Y. App. Div. 2001)

Summary

In Macalloy, the plaintiff sought declaratory relief under a contract which included a "plant shutdown" as a force majeure event.

Summary of this case from Drummond Coal Sales Inc. v. Kinder Morgan Operating LP

Opinion

June 21, 2001.

Order, Supreme Court, New York County (Martin Schoenfeld, J.), entered August 30, 2000, which granted defendant's motion for summary judgment, dismissing plaintiff's complaint for injunctive and declaratory relief, unanimously modified, on the law, only to the extent of declaring that plaintiff is not relieved from performing under the parties' contract pursuant to the contract's force majeure provision, and otherwise affirmed, with costs to defendant payable by plaintiff.

Richard H. Waxman, for plaintiff-appellant.

Eric Ordway, for defendant-respondent.

Before: Nardelli, J.P., Mazzarelli, Rubin, Saxe, Buckley, JJ.


Plaintiff was not relieved of its obligations to perform under the contract with defendant based on the "plant shutdown" language contained in the force majeure provision of the contract. Such force majeure clauses excuse non-performance only where the reasonable expectations of the parties have been frustrated due to circumstances beyond the control of the parties (see, Kel Kim Corp. v. Cent. Mkts., Inc., 70 N.Y.2d 900, 902; United Equities v. First Natl. City Bank, 52 A.D.2d 154, 157, affd 41 N.Y.2d 1032). Plaintiff shut down its plant voluntarily due to financial considerations brought about by environmental regulations. Those are not circumstances constituting a force majeure event, and financial hardship is not grounds for avoiding performance under a contract (see, 407 E. 61st Garage v. Savoy Fifth Ave. Corp., 23 N.Y.2d 275, 282; Matter of Coastal Power Production Co. v. New York State Pub. Serv. Commn., 153 A.D.2d 235, 240). Furthermore, plaintiff was fully aware of the environmental regulations, and the Environmental Protection Agency's intention to enforce them fully, prior to entering into the contract with defendant.

We modify only to declare in defendant's favor (see, Lanza v. Wagner, 11 N.Y.2d 317, 334).

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

Macalloy Corporation v. Metallurg, Inc.

Appellate Division of the Supreme Court of New York, First Department
Jun 21, 2001
284 A.D.2d 227 (N.Y. App. Div. 2001)

In Macalloy, the plaintiff sought declaratory relief under a contract which included a "plant shutdown" as a force majeure event.

Summary of this case from Drummond Coal Sales Inc. v. Kinder Morgan Operating LP

In Macalloy, the plaintiff sought declaratory relief under a contract which included a "plant shutdown" as a force majeure event.

Summary of this case from Drummond Coal Sales, Inc. v. Kinder Morgan Operating LP
Case details for

Macalloy Corporation v. Metallurg, Inc.

Case Details

Full title:MACALLOY CORPORATION, Plaintiff-Appellant, v. METALLURG, INC.…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jun 21, 2001

Citations

284 A.D.2d 227 (N.Y. App. Div. 2001)
728 N.Y.S.2d 14

Citing Cases

Team Marketing USA Corp. v. Power Pact, LLC

That clause specifies: "Force Majeure: Notwithstanding anything to the contrary contained herein, [defendant]…

Route 6 Outparcels Llc v. Ruby Tuesday Inc.

Defendant made a calculated choice to allocate funds to the payment of its debts rather than to perform under…