From Casetext: Smarter Legal Research

LoDuca Associates, Inc. v. PMS Construction Management Corp.

Supreme Court, Appellate Division, First Department, New York.
Jan 12, 2012
91 A.D.3d 485 (N.Y. App. Div. 2012)

Summary

finding that if, by reason of information it had prior to the contract, a defendant knew or should have known of alleged defects resulting in a delay in construction, such facts constitute merely "inept administration or poor planning" and do not negate the exculpatory clause

Summary of this case from N.J.D. Wiring & Elec., Inc. v. M.A. Angeliades, Inc.

Opinion

2012-01-12

LoDUCA ASSOCIATES, INC., Plaintiff–Appellant, v. PMS CONSTRUCTION MANAGEMENT CORP., Defendant–Respondent,City of New York, et al., Defendants.

Tunstead & Schechter, Jericho (Michael D. Ganz of counsel), for appellant. Hollander & Strauss, LLP, Great Neck (Michael R. Strauss of counsel), for respondent.


Tunstead & Schechter, Jericho (Michael D. Ganz of counsel), for appellant. Hollander & Strauss, LLP, Great Neck (Michael R. Strauss of counsel), for respondent.

MAZZARELLI, J.P., ANDRIAS, SAXE, FREEDMAN, JJ.

Order, Supreme Court, New York County (Bernard J. Fried, J.), entered September 15, 2010, which granted defendant PMS Construction Management Corp.'s motion to dismiss the second, third, and fourth causes of action, and order, same court and Justice, entered December 10, 2010, which, to the extent appealable, denied plaintiff's motion for leave to renew, unanimously affirmed, without costs.

Plaintiffs seeking to invoke one of the exceptions to the enforceability of a “no damages for delay” clause face a “heavy burden” ( see Dart Mech. Corp. v. City of New York, 68 A.D.3d 664, 891 N.Y.S.2d 76 [2009] ). Possible causes for delay specifically mentioned in the contract are, by definition, “contemplated” ( see Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297, 309–10, 502 N.Y.S.2d 681, 493 N.E.2d 905 [1986] ); Universal/MMEC, Ltd. v. Dormitory Auth. of State of N.Y., 50 A.D.3d 352, 353, 856 N.Y.S.2d 560 [2008] ).

The causes of action were properly dismissed, as the alleged cause of the delays—primarily design defects based on faulty architectural drawings—was “precisely within the contemplation of the exculpatory clauses” ( Gottlieb Contr. v. City of New York, 86 A.D.2d 588, 589, 446 N.Y.S.2d 311 [1982], affd. 58 N.Y.2d 1051, 462 N.Y.S.2d 642, 449 N.E.2d 422 [1983] ). Moreover, even if defendant knew or should have known of the alleged defects by reason of information it had prior to the contract, such facts constitute merely “inept administration or poor planning,” which does not negate application of the “no damages for delay” provisions ( see Commercial Elec. Contrs., Inc. v. Pavarini Constr. Co., Inc., 50 A.D.3d 316, 317–18, 856 N.Y.S.2d 46 [2008]; T.J.D. Constr. Co. v. City of New York, 295 A.D.2d 180, 743 N.Y.S.2d 111 [2002] ).

It is true that, as argued by plaintiff, the length of the delay is relevant to the issue of whether an exception to the general rule enforcing “no damages for delay” clauses applies ( see Bovis Lend Lease LMB v. GCT Venture, 6 A.D.3d 228, 229, 775 N.Y.S.2d 259 [2004] ). However, the length of the delay does not transform a delay caused by an event specifically contemplated by the “no damages for delay” clause into something uncontemplated ( see Dart Mech. Corp., 68 A.D.3d at 664, 891 N.Y.S.2d 76 [32–month delay not actionable where several contract provisions indicated that delay was contemplated] ).

The motion for leave to renew was properly denied since the new evidence offered by plaintiff demonstrated merely the alleged severity and scope of the alleged design defects and ensuing delays, but not that they were uncontemplated.

We have reviewed plaintiff's remaining contentions and find them unavailing.


Summaries of

LoDuca Associates, Inc. v. PMS Construction Management Corp.

Supreme Court, Appellate Division, First Department, New York.
Jan 12, 2012
91 A.D.3d 485 (N.Y. App. Div. 2012)

finding that if, by reason of information it had prior to the contract, a defendant knew or should have known of alleged defects resulting in a delay in construction, such facts constitute merely "inept administration or poor planning" and do not negate the exculpatory clause

Summary of this case from N.J.D. Wiring & Elec., Inc. v. M.A. Angeliades, Inc.

In LoDuca Assoc., Inc. v PMS Constr. Mgt. Corp. (91 AD3d 485, supra), the same exact language of a "no damages for delay" clause was held to bar a claim for delay damages by a trade contractor whose work was delayed by 27 months due to "faulty architectural drawings."

Summary of this case from Omni Contracting Co. v. City of New York
Case details for

LoDuca Associates, Inc. v. PMS Construction Management Corp.

Case Details

Full title:LoDUCA ASSOCIATES, INC., Plaintiff–Appellant, v. PMS CONSTRUCTION…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Jan 12, 2012

Citations

91 A.D.3d 485 (N.Y. App. Div. 2012)
936 N.Y.S.2d 192
2012 N.Y. Slip Op. 121

Citing Cases

Weydman Elec., Inc. v. Joint Sch. Constr. Bd.

Contrary to plaintiff's further contention, we conclude that defendants met their prima facie burden on their…

Primiano Elec. Co. v. HTS-NY, LLC

"[A] party seeking to invoke any of the exceptions to the general rule that no damages for delay clauses are…