Lewin v. Levine

Supreme Court, Appellate Division, Second Department, New York.
Jan 11, 2017
146 A.D.3d 768 (N.Y. App. Div. 2017)

Summary

In Lewin v. Leuine, (146 A.D.3d 768 [2d Dept 2017]) the Court determined that the proper measure of the plaintiffs' damages was the cost of completion of the construction work.

Summary of this case from Lew v. Connors

Opinion

01-11-2017

Harley LEWIN, et al., respondents, v. Harmon LEVINE, et al., appellants.

Sahn Ward Coschignano, PLLC, Uniondale, N.Y. (Christian Browne, Ralph Branciforte, and Joshua Brookstein of counsel), for appellants. John R. Sachs, Jr., New York, N.Y., for respondents.


Sahn Ward Coschignano, PLLC, Uniondale, N.Y. (Christian Browne, Ralph Branciforte, and Joshua Brookstein of counsel), for appellants.

John R. Sachs, Jr., New York, N.Y., for respondents.

JOHN M. LEVENTHAL, J.P., JEFFREY A. COHEN, ROBERT J. MILLER, and HECTOR D. LaSALLE, JJ.

In an action, inter alia, to recover damages for breach of contract, the defendants appeal from an order of the Supreme Court, Westchester County (Adler, J.), dated February 5, 2015, which, after a nonjury trial on the issue of damages, in effect, directed the entry of a judgment in favor of the plaintiffs and against them in the principal sum of $300,500.

ORDERED that on the Court's own motion, the notice of appeal from the order is deemed to be an application for leave to appeal, and leave to appeal is granted (see CPLR 5701[c] ); and it is further,

ORDERED that the order is reversed, on the law and the facts, and the matter is remitted to the Supreme Court, Westchester County, for entry of a judgment dismissing the complaint; and it is further,

ORDERED that one bill of costs is awarded to the defendants.

The plaintiffs entered into a contract with the defendant Harmon Development Corp. (hereinafter Harmon Development) to renovate their home located in Chappaqua. The defendant Harmon Levine, as president of Harmon Development, executed the contract. The defendant Randy Levine is Harmon Levine's wife.

The plaintiffs alleged that after they made payments of hundreds of thousands of dollars to the defendants under the contract, they became dissatisfied with the work, terminated Harmon Development's employment, and hired others to complete the project and remediate what they alleged to be improper and poor work. The plaintiffs commenced this action alleging causes of action sounding in breach of contract, conversion, and negligence.

In March 2014, the plaintiffs moved for summary judgment on the complaint. In an order dated September 3, 2014, the Supreme Court (Giacomo, J.) granted the motion to the extent of awarding the plaintiffs summary judgment on the issue of liability on their causes of action. The court noted that the plaintiffs sought the sum of $216,399.05 in damages in their complaint, yet in their motion sought the sum of $468,768.78. Thus, the court directed that a trial be conducted on the issue of damages.

A nonjury trial on the issue of damages was held in December 2014. In an order dated February 5, 2015, the Supreme Court (Adler, J.) determined that the plaintiffs were entitled to damages in the principal sum of $300,500, which represented the amount of money paid by the plaintiffs to the defendants pursuant to the contract. The court found that the plaintiffs failed to establish that they made payments to other contractors to remediate the work or to complete the project.

"In reviewing a determination made after a nonjury trial, the power of the Appellate Division is as broad as that of the trial court and it may render the judgment it finds warranted by the facts, taking into account that in a close case the trial judge had the advantage of seeing and hearing the witnesses" (Yonkers Contr. Co., Inc. v. Romano Enters. of N.Y., Inc., 40 A.D.3d 629, 629, 835 N.Y.S.2d 363 ; see Northern Westchester Professional Park Assoc. v. Town of Bedford, 60 N.Y.2d 492, 499, 470 N.Y.S.2d 350, 458 N.E.2d 809 ; Novair Mech. Corp. v. Universal Mgt. & Contr. Corp., 81 A.D.3d 909, 909–910, 917 N.Y.S.2d 876 ; Candela v. Byron Chem. Co., Inc., 54 A.D.3d 306, 863 N.Y.S.2d 230 ).

It is fundamental to the law of damages that one complaining of injury has the burden of proving the extent of the harm suffered, must demonstrate actual damages, and must lay a basis for a reasonable estimate of the extent of the harm (see Berley Indus. v. City of New York, 45 N.Y.2d 683, 686, 412 N.Y.S.2d 589, 385 N.E.2d 281 ; RMP Capital Corp. v. Victory Jet, LLC, 139 A.D.3d 836, 838, 32 N.Y.S.3d 231 ; G & A Moving & Stor. Co. v. Computer Assoc. Intl., 233 A.D.2d 479, 479, 650 N.Y.S.2d 982 ).

Here, the Supreme Court erred in awarding damages equal to the monies paid by the plaintiffs to the defendants on the contract. The proper measure of the plaintiffs' damages was the cost of completion of the construction work and the correction of defects in the defendants' work (see Metropolitan Switch Bd. Mfg. Co., Inc. v. B & G Elec. Contrs., Div. of B & G Indus., Inc., 96 A.D.3d 725, 726, 946 N.Y.S.2d 178 ; Marino v. Lewis, 17 A.D.3d 325, 325–326, 792 N.Y.S.2d 572 ; Ferreira v. Saccento, 286 A.D.2d 366, 729 N.Y.S.2d 178 ; Kaufman v. Le Curt Construction Corp., 196 A.D.2d 577, 578, 601 N.Y.S.2d 186 ; Lukoff v. Suzzex Downs, 131 A.D.2d 442, 443, 516 N.Y.S.2d 471 ). Indeed, in their complaint, the plaintiffs stated that their damages on the breach of contract, negligence, and conversion causes of action were the "total sum" of $201,399.05, which was the cost "to repair the premises to the condition that was agreed upon" in the contract, and to "replace the damaged property and stolen property."

At trial, the plaintiffs failed to demonstrate what portion of the $300,500 they paid to the defendants was attributed to (1) work that was never done, and/or (2) defective work. The only testimony regarding these payments was simply the amount of the payments made under the contract. Such proof of payment to the defendants was inadequate to establish the plaintiffs' damages (see Hodges v. Cusanno, 94 A.D.3d 1168, 1170, 941 N.Y.S.2d 772 ; O'Malley v. Campione, 70 A.D.3d 595, 896 N.Y.S.2d 49 ; Marino v. Lewis, 17 A.D.3d at 325–326, 792 N.Y.S.2d 572 ; Ferreira v. Saccento, 286 A.D.2d 366, 729 N.Y.S.2d 178 ; Alpha Auto Brokers v. Continental Ins. Co., 286 A.D.2d 309, 310, 728 N.Y.S.2d 769 ; Wenger v. Alidad, 265 A.D.2d 322, 696 N.Y.S.2d 227 ; Kaufman v. Le Curt Construction Corp., 196 A.D.2d at 578, 601 N.Y.S.2d 186 ). Accordingly, the trial court's damages award was not warranted by the facts. Since the plaintiffs failed to demonstrate that they sustained actual damages, the complaint must be dismissed.

To the extent that the plaintiffs contend on appeal that the damages award was inadequate, such contention is not properly before this Court, as the plaintiffs did not appeal from the order (see Matter of Visiting Nurse Serv. of N.Y. Home Care v. New York State Dept. of Health, 5 N.Y.3d 499, 806 N.Y.S.2d 465, 840 N.E.2d 577 ; Metropolis A.C. Corp. v. National Envtl. Safety Co., Inc., 37 A.D.3d 431, 432, 829 N.Y.S.2d 614 ; 310 S. Broadway Corp. v. Barrier Gas Serv., 224 A.D.2d 409, 411, 637 N.Y.S.2d 765 ).


Summaries of

Lewin v. Levine

Supreme Court, Appellate Division, Second Department, New York.
Jan 11, 2017
146 A.D.3d 768 (N.Y. App. Div. 2017)

In Lewin v. Leuine, (146 A.D.3d 768 [2d Dept 2017]) the Court determined that the proper measure of the plaintiffs' damages was the cost of completion of the construction work.

Summary of this case from Lew v. Connors
Case details for

Lewin v. Levine

Case Details

Full title:Harley LEWIN, et al., respondents, v. Harmon LEVINE, et al., appellants.

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Jan 11, 2017

Citations

146 A.D.3d 768 (N.Y. App. Div. 2017)
44 N.Y.S.3d 540
2017 N.Y. Slip Op. 159

Citing Cases

Yorizzo v. Maple Corp, LLC

Defendants allege that "the proper measure of Plaintiffs' damages is the cost of completion of the…

Wei Su v. Sotheby's Inc.

In short, Yeh has failed to establish that he suffered “actual damages” from this lost investment opportunity…