From Casetext: Smarter Legal Research

Glacius et al. v. Black

Court of Appeals of the State of New York
Dec 22, 1876
67 N.Y. 563 (N.Y. 1876)

Summary

In Glacius v. Black (67 N.Y. 563) the contract itself provided that the entire sheathing of the attic should be of felt. It was unambiguous and presented no question of fact.

Summary of this case from Langley v. Rouss

Opinion

Argued December 6, 1876

Decided December 22, 1876

George A. Black for the appellant. Ernest Hall for the respondents.


The constitutionality of the legislation known as mechanics' lien laws, was affirmed in Blauvelt v. Woodworth ( 31 N.Y., 285), and the court held that there was no constitutional objection to the creation, by the legislature, of statutory liens, in favor of mechanics and others, for the purposes and under the circumstances and limitations specified in these statutes. Laws of similar character have been in force in this State for more than forty years (Laws of 1844, chap. 220); and similar legislation is found on the statute books of many of the States. These statutes have been frequently under consideration by the courts, and, so far as we know, their constitutional validity has never been judicially questioned.

We do not doubt the soundness of the decision in Blauvelt v. Woodworth; and if the question admitted of doubt we should not feel at liberty, under the circumstances, to reconsider the decision in that case. We dismiss, therefore, the further consideration of the argument pressed upon us as to the unconstitutionality of the statute in question.

This action has been twice tried, and the plaintiff recovered on both trials. The first judgment was reversed by this court. ( 50 N.Y., 145.) The appellant then insisted that if the judgment should be reversed the reversal should be absolute, and without awarding a new trial on the ground that the lien had then expired by limitation, and that the action could not be further prosecuted. The court, in answer to this argument, and in overruling it, said: "This position is not tenable; if the lien has expired, the action can still be prosecuted as a personal action;" and a new trial was awarded on the reversal of the judgment. The plaintiffs, on the new trial, admitted that the lien had expired; and the defendant then moved to dismiss the proceeding, on the ground that the court had no jurisdiction to render judgment therein for the claimants, after the expiration of the lien. The motion was denied, and the trial proceeded, and resulted in a verdict and judgment for the plaintiffs, as in an ordinary action upon contract.

The defendant now, again, insists that the plaintiffs could not proceed, after the expiration of the lien, to obtain judgment for their debt. This precise question was decided adversely to the defendant, on the former appeal, and is therefore res adjudicata in this case.

The plaintiffs entered into a written contract to put an attic story, with mansard roof, on the house of the defendant, and to complete it according to certain plans, drawings and specifications forming part of the contract, and the final payment, which they claimed to recover in this proceeding, was, by the terms of the contract, to be made when the "work is done and completely accepted." The plaintiffs, in order to recover, were bound to show that the contract had been substantially performed. It was not necessary that they should be able to show literal performance of the work in every detail, according to the specifications, as a condition precedent to a recovery, provided it appeared that the departures and variations were not willful, and were technical and unsubstantial, and in unimportant and immaterial particulars. In such cases the law allows a recovery under the contract, with compensation to the other party by way of allowance, and deduction from the contract-price for such damages as he has sustained by reason of the omission of the plaintiff to comply with the exact terms of the contract. The contrary rule would deprive a contractor, in a building contract, of all compensation, although he has in good faith endeavored to perform his contract, and has substantially performed it, but has failed in some minor and subordinate particulars, as to which an allowance out of the contract-price would afford to the other party a complete indemnity. The rule that substantial performance is sufficient for the purpose of maintaining the action, was declared on the former appeal; and on the last trial the judge, in conformity with it, charged the jury that to entitle the claimants to recover any thing, it must appear that there had been no willful departure from the terms of the contract, or omissions in essential points, and that if there were substantial defects in the work, the plaintiffs could not recover. The jury found for the plaintiffs on this issue, and while the weight of evidence, as presented in the case, seems to be adverse to this conclusion, we are of opinion that the question was one of fact for the jury, and by their finding this court is concluded. There is, however, a point upon which the judgment must be reversed. The specifications contained this provision: "The sides of the attic story to be covered with one-inch pine plank, grooved and tongued — white pine plank, laid in the best manner * * * the frame is to be sheathed with pine boards; sheathing to be covered with felt, put on in the best manner." The evidence on the part of the defendant tended to show that the walls of the old building were filled in with brick, to the point where the attic story commenced, and that the plaintiff, in constructing the new story, did not remove the old sheathing above this point, on one side of the building, except immediately below the old roof, and that a space two or three feet wide extending across the house in the new attic story was left without any felt covering the sheathing.

The defendant requested the court to charge the jury that the contract required the plaintiffs to put on the felt as low as the attic story. The judge, in reply to this request, said: "This is left for the jury to say," and the defendant excepted. There was no ambiguity in the contract in respect to the points referred to in the request. It plainly required the plaintiffs to cover the entire sheathing of the attic story with felt. This was a question of law for the court to decide, and the judge erred in remitting it to the jury for decision. (2 Parsons on Contracts, 492, and cases cited.)

For this error of the judge, and without examining the exceptions to evidence, which have been argued, the judgment must be reversed and a new trial ordered.

All concur.

Judgment reversed.


Summaries of

Glacius et al. v. Black

Court of Appeals of the State of New York
Dec 22, 1876
67 N.Y. 563 (N.Y. 1876)

In Glacius v. Black (67 N.Y. 563) the contract itself provided that the entire sheathing of the attic should be of felt. It was unambiguous and presented no question of fact.

Summary of this case from Langley v. Rouss

In Glacius v. Black (67 N.Y. 563) we are referred to the same case (50 N.Y. 145). There the court say: "The point is made by the appellant that the judgment should be reversed without a new trial, claiming that the lien has expired, and no personal judgment can be rendered against the defendant.

Summary of this case from Mowbray v. Levy
Case details for

Glacius et al. v. Black

Case Details

Full title:GEORGE C. GLACIUS et al., Respondents, v . BESSIE BLACK, Appellant

Court:Court of Appeals of the State of New York

Date published: Dec 22, 1876

Citations

67 N.Y. 563 (N.Y. 1876)

Citing Cases

Spence v. Ham

The contractor has no excuse for making them single when the specifications required them to be double, and…

Mowbray v. Levy

The very cases cited by the learned counsel for the respondent indicate, almost without exception, the…