From Casetext: Smarter Legal Research

County School Bd. v. Beiro

Supreme Court of Virginia
Jan 22, 1982
223 Va. 161 (Va. 1982)

Summary

In Beiro, the owner of a public school building brought an action against the contractor claiming damages due to a defective roof.

Summary of this case from Suffolk City School Board v. Conrad Brothers, Inc.

Opinion

44267 Record No. 791613.

January 22, 1982

Present: Carrico, C.J., Cochran, Poff, Compton, Thompson, and Stephenson, JJ., and Harrison, Retired Justice.

The five-year limitation on contracts not under seal contained in former Code 8-13 [now consolidated in Code Sec. 8.01-246(2)] runs from the date of completion of an indivisible building contract and not from the completion of one phase of the construction, the earliest date of comply lion here being when the architect issued the certificate of final payment, the action thus not being barred.

Limitations of Actions — Contract Not Under Seal [Code Sec. 8-13, Now Consolidated in Code Sec. 8.01-246(2)] — Five-Year Limit Runs From Date of Completion of Indivisible Building Contract — Here Completion Not Earlier Than Date Architect Issues Certificate of Final Payment and Action Not Barred.

Alterations and an addition to a school building were to be done under a contract between the Fairfax County School Board and Beiro in four phases. Phase 1 involved installation of a roof which allegedly was defective. The contractor retained the right to correct defects until the building was completed. The roof was substantially completed in May 1971 and fully completed by February 1972. However the architect did not approve final payment until August 1973, suit being filed by the Board in January 1978. Beiro contended the Board's action was barred by the five-year statute of limitations on contracts not under seal then in Code Sec. 8-13 and now consolidated in Code 18.01-246(2). The Trial Court held the cause of action occurred when the roof was completed in February 1972 at the latest and was barred, applying Virginia Military Institute v. King. 217 Va. 751, 232 S.E.2d 895 (1977). The School Board appeals.

The contract was not divisible and the action sounds in contract and not in tort. Consequently the Board's cause of action accrued at the earliest in August 1973, when the architect issued the certificate of final payment. The action having been brought within 5 years from the time the certificate of final payment was issued, the action was timely brought. Virginia Military Institute v. King, 217 Va. 751, 232 S.E.2d 895 (1977); Housing Authority v. Laburnum Corp., 195 Va. 827, 80 S.E.2d 574 (1954), distinguished.

Appeal from a judgment of the Circuit Court of Fairfax County. Hon. Thomas J. Middleton, judge presiding.

Reversed and remanded.

Thomas J. Cawley (Robert H. J. Loftus; Grady K. Carlson; McCandlish, Lillard, Church Best, on briefs), for appellant.

John N. Fenrich, Jr., for appellees.


The School Board of Fairfax County (the Board) brought suit against A. A. Beiro Construction Company (Beiro) and its surety, Travelers Indemnity Company (Travelers), alleging the roof of a school building built by Beiro was defective. The trial court ruled that the School Board's action was barred by the statute of limitation. On appeal, the Board argues the suit was brought within five years of the time the cause of action arose.

Under the statute in force at the time this suit arose, the time limitation for bringing actions was ten years on contracts under seal and five years on contracts not under seal. Former Code Sec. 8-13 (repealed, Acts 1977, c. 617). The Board argues that, as an agency of the State, no limitation applies to it and, alternatively, that the contract was under seal. See County School Bd. v. Whitlow, et al., 223 Va. 157, 286 S.E.2d 230 (1982). Our decision that the suit was brought within five years makes it unnecessary to reach these issues.

On October 30, 1970, the Board and Beiro entered into a contract for construction at the Belleview Elementary School. The plans called for both an addition to and the alteration of the existing school building. The construction was to be done in four phases, with only Phase One involving roof installation.

The parties agree that the roof was substantially completed in May, 1971, and fully completed by February, 1972. All areas of the building were occupied by the Board by the end of 1971. While the architect did not approve final payment until August, 1973, and this payment was not made until July, 1974, Beiro argues the building was completed in August, 1972. Suit was not filed by the Board until January, 1978.

The trial court, relying on Virginia Military Institute v. King, 217 Va. 751,232 S.E.2d 895 (1977), held the cause accrued when the roof was completed, February, 1972 at the latest. We cannot agree. In King, an architect contracted both to design a building and to supervise its construction. The contract, by its terms was divisible, and we held a cause of action for negligent design accrued when that portion of the contract was completed.

The contract in the present case was not divisible. The contractor retained the right to correct defects until the time the building was completed. Indeed, the architect and Board frequently inspected the site and corresponded with the contractor so that corrections could be made.

Nor do we feel that Housing Authority v. Laburnum Corp., 195 Va. 827, 80 S.E.2d 574 (1954), and its progeny are apposite. Laburnum involved a suit sounding in tort for property damage caused by a breach of implied warranty. The contractor had improperly connected a gas pipe while constructing a building, leading to an explosion after it was completed. We held that the action arose at the time the connection was made and not when the building was completed. The present case, however, sounds in contract, not tort.

The Board's cause of action accrued, at the earliest, in August, 1973, when the architect issued the certificate of final payment. The suit, therefore, was timely filed. The judgment of the trial court will be reversed and the case remanded for further proceedings consistent with this opinion.

Reversed and remanded.


Summaries of

County School Bd. v. Beiro

Supreme Court of Virginia
Jan 22, 1982
223 Va. 161 (Va. 1982)

In Beiro, the owner of a public school building brought an action against the contractor claiming damages due to a defective roof.

Summary of this case from Suffolk City School Board v. Conrad Brothers, Inc.
Case details for

County School Bd. v. Beiro

Case Details

Full title:COUNTY SCHOOL BOARD OF FAIRFAX COUNTY v. A. A. BEIRO CONSTRUCTION COMPANY…

Court:Supreme Court of Virginia

Date published: Jan 22, 1982

Citations

223 Va. 161 (Va. 1982)
286 S.E.2d 232

Citing Cases

Suffolk City School Board v. Conrad Brothers, Inc.

In the case of an indivisible or entire contract, a party seeking to recover for a breach committed while the…

Nelson v. Commonwealth

While we made a merits adjudication of the issues relating to the owner's claims for the architects' failure…