(a) After conducting a regulatory analysis under section 22.7 of this chapter, if an agency elects to adopt a rule subject to section 23 of this chapter or IC 13-14-9, the agency shall submit a request to the budget agency and the office of management and budget to authorize commencement of the public comment periods under this chapter or IC 13-14-9 (as applicable). The request must include the following:
(1) A general description of the subject matter of the proposed rule.
(2) The full text of the proposed rule (including a copy of any matter incorporated by reference under section 21 of this chapter) in the form required by the publisher, including citations to any related authorizing and affected Indiana statutes.
(3) The regulatory analysis, including supporting data, prepared under section 22.7 of this chapter.
(4) Any other information required by the office of management and budget.
(b) The budget agency and the office of management and budget shall expedite the review of the request to adopt a rule. The budget agency and the office of management and budget may do the following:
(1) Return the request to the agency with a statement describing any additional information needed to authorize or disapprove further rulemaking actions on one (1) or more of the rules in the request.
(2) Authorize the commencement of the public comment periods on one (1) or more of the rules in the request with or without changes.
(3) Disapprove commencement of the public comment periods on one (1) or more of the rules with a statement of reasons for the disapproval.
(c) If an agency has requested authorization for more than one (1) rule in the same request, the budget agency and the office of management and budget may make separate determinations with respect to some or all of the rules in the request. Approval of a request shall be treated as a determination that the review conducted and findings made by the agency comply with the requirements of section 22.7 of this chapter and this section. The budget agency and the office of management and budget may not approve any part of a proposed rule that adds or amends language to increase or expand application of a fee, fine, or civil penalty or a schedule of fees, fines, or civil penalties before submitting the proposed rule to the budget committee for review.
(d) If the implementation and compliance costs of a proposed rule are expected to exceed the threshold set forth in section 22.7(c)(6) of this chapter, the office of management and budget shall submit the rule to the legislative council, in an electronic format under IC 5-14-6, within thirty (30) days of completing the review of the regulatory analysis. The chairperson of legislative council shall inform members of the budget committee of a rule submitted under this subsection. The budget agency and the office of management and budget may not approve any part of a proposed rule covered by this subsection prior to review of the proposed rule by the budget committee.
(e) Notice of the determination shall be provided to the agency in an electronic format required by the publisher. The budget agency and the office of management and budget may return to the agency any copy of a matter incorporated by reference under section 21 of this chapter that was submitted with the request.
(f) If an agency revises a proposed rule after the budget agency and the office of management and budget authorize commencement of the public comment periods, the agency must obtain a new notice of determination under subsection (e). The agency shall resubmit to the budget agency and the office of management and budget the revised proposed rule and a revised regulatory analysis with sufficient information for the budget agency and the office of management and budget to determine the impact the revisions have on the regulatory analysis previously reviewed by the budget agency and the office of management and budget. After obtaining a new notice of determination, the agency shall submit to the publisher the new notice of determination, the revised proposed rule, and the revised regulatory analysis.