810 CMR, § 4.06

Current through Register 1530, September 13, 2024
Section 4.06 - Selection of Projects for Evaluation
(1) DCAM shall consider evaluations of public and/or private Building Projects completed by the Contractor within five years prior to the date DCAM receives the Contractor's application for certification.
(2) DCAM shall not be required to obtain evaluations of all Building Projects completed by the Contractor. DCAM may consider a representative sample of completed projects and may require that each evaluated project be of a minimum dollar value.
(3) DCAM shall consider project evaluations of Awarding Authorities, owner's project managers, or owners of private Building Projects on properly completed Standard Contractor Evaluation Forms issued by DCAM pursuant to M.G.L. c. 149, § 44D and submitted to DCAM as prescribed in the Guidelines. DCAM shall consider only reliable evaluations that are indicative of Contractor's ability to perform Building Projects of the type and size for which certification is requested.
(4) DCAM may also obtain evaluations of completed Building Projects through telephone interviews. DCAM personnel shall use the Standard Contractor Evaluation Form as a questionnaire when obtaining evaluations through telephone interviews.

810 CMR, § 4.06