Westmoreland H. Assn. v. West. Const. Co.

Supreme Court of Pennsylvania
Nov 15, 1966
423 Pa. 255 (Pa. 1966)

Summary

In Westmoreland, supra, a party sought to invoke the contract arbitration clause following receipt of final payment for its performance.

Summary of this case from Gavlik Const. Co. v. H. F. Campbell Co.

Opinion

September 27, 1966.

November 15, 1966.

Arbitration — Contract — Terms — Construction — Final payment — Effect.

1. In this appeal from a decree enjoining a building contractor from seeking arbitration, in which it appeared that during the performance of the construction work the contractor complained of delays in completing the work because of lack of co-operation on the part of the owner, resulting in an alleged loss of $37,203; that the construction work was completed in May, 1965, and on December 28, 1965 the contractor filed a notice of demand for arbitration of the claim for $37,203 and thereafter on January 17, 1966 the contractor accepted a check in the amount of $67,421.26 in final payment for the job; and that the contract provided ". . . in any event, no demand for arbitration shall be made after the date of final payment . . .", it was Held that this provision barred the contractor from arbitrating the dispute and that the injunction decree should be affirmed.

2. A provision in the contract that "It is mutually agreed that all disputes arising in connection with this contract shall be submitted to arbitration" is sufficiently broad to embrace differences between the parties over expenditures and losses caused by delays in the execution of the contract. [257-8]

3. Arbitration agreements are strictly construed and are not to be extended by implication. [255]

Mr. Justice ROBERTS concurred in the result.

Before BELL, C. J., MUSMANNO, JONES, COHEN, EAGEN, O'BRIEN and ROBERTS, JJ.

Appeal, No. 219, March T., 1966, from decree of Court of Common Pleas of Westmoreland County, No. 3423 in Equity, in case of Westmoreland Hospital Association v. Westmoreland Construction Company. Decree affirmed.

Equity.

Decree entered enjoining defendant from submitting to arbitration its claim against plaintiff, opinion by WEISS, P. J. Defendant appealed.

Edward B. Doran, for appellant. B. Patrick Costello, with him Smith, Best, Williams, Costello Snyder, for appellee.


On March 16, 1964, the Westmoreland Construction Company, hereinafter called the contractor, entered into a contract with the Westmoreland Hospital Association to erect an additional wing to the Westmoreland Hospital. During the performance of the construction work, the contractor complained that it was encountering delays in its operation because effective liaison between the hospital staff, the architectural firm and the contractor, was lacking. The contractor endeavored to correct the averred fault but was unsuccessful in its efforts. Because of the trouble here referred to, the contractor incurred an alleged loss of $37,203.

On May 19, 1965, the construction job was completed and on January 17, 1966, the contractor accepted a check in the amount of $67,421.26 in final payment for the job.

On December 28, 1965, the contractor filed a notice of demand for arbitration with the American Arbitration Association of Pittsburgh, charging that, because of failure of cooperation on the part of the Westmoreland Hospital Association, it had incurred losses in the amount of $37,203. The Hospital Association then filed a complaint in equity in the Westmoreland County Court asking that the contractor be enjoined from seeking arbitration of the indicated dispute on the ground that arbitration was not an available form of relief. The court of common pleas did so enjoin the contractor, and the contractor has appealed.

This Court has no difficulty in finding that the dispute here involved between the parties could be the proper subject for arbitration, the agreement between them specifically declaring that "7. Arbitration. — (a) It is mutually agreed that all disputes arising in connection with this contract shall be submitted to arbitration." (Emphasis supplied) Certainly, a dispute over expenditures and losses caused by delays in the execution of the contract would be a dispute "arising in connection with" the contract.

However, the arbitration clause is not applicable in this case for the reason that, by its very terms, it obviously was not meant to apply where the contract was completed and there could be no need for a speedy resolution of a dispute. A reading of the terms of arbitration make it clear that the purpose of providing for arbitration was to settle those differences, that, arising during the course of construction, might have unduly interrupted completion of the work. The agreement provided: "(b) The work under this contract shall not be stopped or delayed in any way during the arbitration proceedings except by written mutual consent of both parties to the contract, and such mutual consent shall stipulate whether extension of the time for completion of the contract will be authorized by such stoppage or delay. (c) Demand for arbitration in connection with any dispute shall be filed in writing with the Architect and with the other party to the contract. Any demand for arbitration shall be made within thirty days after the dispute has arisen if practicable, but, in any event, no demand for arbitration shall be made after the date of final payment except in the case of a dispute arising in connection with any guarantee provisions of the Contract Documents."

As the case comes to us, the contract had already been completed by the contractor when it applied for arbitration. Thus, there was no need for arbitration; the regular channels of legal procedure were sufficient and proper for resolvement of any post-completion disputes. This is made even more evident by the fact that after making application for arbitration the contractor accepted "final payment" for the work performed.

To enlarge the arbitration provisions of this contract to include a dispute remaining after completion of the work involved would be violative of the rule that agreements to arbitrate must be strictly construed and cannot be enlarged by implication: McDevitt v. McDevitt, 365 Pa. 18.

Decree affirmed; each party to bear own costs.

Mr. Justice ROBERTS concurs in the result.


Summaries of

Westmoreland H. Assn. v. West. Const. Co.

Supreme Court of Pennsylvania
Nov 15, 1966
423 Pa. 255 (Pa. 1966)

In Westmoreland, supra, a party sought to invoke the contract arbitration clause following receipt of final payment for its performance.

Summary of this case from Gavlik Const. Co. v. H. F. Campbell Co.

In Westmoreland Hospital Association v. Westmoreland Construction Co., 423 Pa. 255, 223 A.2d 681 (1966) upon which the Hussey court relied, the Supreme Court of Pennsylvania, on facts remarkably similar to case sub judice, held that the contractor's delay claim was not subject to arbitration because the contract had been completed and the contractor had accepted final payment.

Summary of this case from Aberthaw Construction Co. v. Centre County Hospital
Case details for

Westmoreland H. Assn. v. West. Const. Co.

Case Details

Full title:Westmoreland Hospital Association v. Westmoreland Construction Company…

Court:Supreme Court of Pennsylvania

Date published: Nov 15, 1966

Citations

423 Pa. 255 (Pa. 1966)
223 A.2d 681

Citing Cases

Shamokin Area Sch. Auth. v. Farfield Co.

Even if the court below was not in error as to the completion of the work, the obligation to arbitrate…

Tekmen Co. v. Southern Builders

Since, pursuant to the contract, this condition ends upon the date of final payment, at that point there is…