Tooher v. Willets Point Contracting Corp.

Appellate Division of the Supreme Court of New York, Third Department
Mar 16, 1995
213 A.D.2d 856 (N.Y. App. Div. 1995)

Opinion

March 16, 1995

Appeal from the Supreme Court, Schenectady County (Lynch, J.).


On September 5, 1989, plaintiff Robert Tooher (hereinafter plaintiff) sustained the injuries forming the basis for this action when he fell into a trench (40 feet long, 15 feet wide and 10 to 15 feet deep) constructed as part of a project to clean and repair underground water mains in New York City. In order to maintain the integrity of the excavation, the sides of the trench were shored with three-inch oak planks. Two sets of horizontal 20-foot timbers were positioned end-to-end on each side of the excavation, at levels approximately two feet and seven feet below ground level. The horizontal timbers (and the oak planking behind them) were in turn braced by crossbeams spanning the width of the trench. Prior to September 5, 1989, some of the interior crossbeams had been removed to permit the retrieval of a large piece of equipment from the water pipe at the bottom of the trench. As a temporary measure, vertical 20-foot timbers were positioned in the trench, extending along the sides at the point of intersection of the horizontal timbers. The accident took place after the equipment had been retrieved, during the dismantling of the temporary supports. After the removal of the crossbeams that had braced the vertical timbers, plaintiff was walking on one of the horizontal timbers situated two feet below ground level and took hold of an unsecured vertical timber, which gave way, causing plaintiff to "ride" it into the excavation.

Defendant appeals from Supreme Court's order granting plaintiffs' motion and denying defendant's cross motion for partial summary judgment on the issue of liability under Labor Law § 240 (1), primarily contending that plaintiff's injuries were caused by the collapse of a shoring timber, a hazard outside the ambit of Labor Law § 240 (1). We disagree and accordingly affirm. There is no question that, although occurring below ground level, plaintiff was injured in a gravity-related accident where a protective device was called for because of the elevation differential between plaintiff's work site and a lower level (see, Ross v. Curtis-Palmer Hydro-Elec. Co., 81 N.Y.2d 494, 500-501; Rocovich v. Consolidated Edison Co., 78 N.Y.2d 509, 514; DeLong v. State St. Assocs., 211 A.D.2d 891; Nichols v. Deer Run Investors, 204 A.D.2d 929). As such, plaintiff's accident falls squarely within the intended scope of Labor Law § 240 (1) (see, supra; cf., Kelleher v. Power Auth., 211 A.D.2d 918). Defendant's reliance upon Third Department cases predating the Court of Appeals decisions in Ross v. Curtis-Palmer Hydro-Elec. Co. (supra) and Rocovich v. Consolidated Edison Co. (supra) is clearly misplaced (see, e.g., Kimball v. Fort Ticonderoga Assn., 167 A.D.2d 581, lv dismissed 77 N.Y.2d 989).

Nor are we persuaded that plaintiff's injuries were caused by an excavation cave-in and that, as a result, his sole remedy is under Labor Law § 241 (6) (cf., Kelleher v. First Presbyt. Church, 158 A.D.2d 946, lv dismissed 75 N.Y.2d 947; Staples v Town of Amherst, 146 A.D.2d 292). As a final matter, the argument that Labor Law § 240 (1) does not apply because plaintiff's work did not involve a building or structure was not raised before Supreme Court and, thus, has not been preserved for our review (see, Rohdie v. Michael Guidice Inc., 132 A.D.2d 541, 542) and is found to lack merit in any event (see, Lewis-Moors v. Contel of N Y, 78 N.Y.2d 942, 943).

Cardona, P.J., White, Casey and Peters, JJ., concur. Ordered that the order is affirmed, with costs.


Summaries of

Tooher v. Willets Point Contracting Corp.

Appellate Division of the Supreme Court of New York, Third Department
Mar 16, 1995
213 A.D.2d 856 (N.Y. App. Div. 1995)
Case details for

Tooher v. Willets Point Contracting Corp.

Case Details

Full title:ROBERT TOOHER et al., Respondents, v. WILLETS POINT CONTRACTING…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Mar 16, 1995

Citations

213 A.D.2d 856 (N.Y. App. Div. 1995)
623 N.Y.S.2d 431

Citing Cases

Wells v. British American Development Corp.

He did not require the use of one of the devices contemplated by Labor Law § 240 (1) in order to safely…

Trillo v. City of New York

Whether plaintiff's fall was caused by the collapse of the wooden sheeting structure over the trench, or by…