From Casetext: Smarter Legal Research

Suffolk County Water Auth. v. J.D. Posillico

Appellate Division of the Supreme Court of New York, Second Department
Dec 30, 1988
145 A.D.2d 623 (N.Y. App. Div. 1988)

Opinion

December 30, 1988

Appeal from the Supreme Court, Suffolk County (Saladino, J.).


Ordered that the order is affirmed insofar as appealed from, with costs.

The defendant is a contractor which allegedly installed sewers beneath the plaintiff's in-ground water mains pursuant to contracts with Suffolk County which is not a party to this action. During and subsequent to the defendant's work, hundreds of water main breaks occurred in areas excavated and backfilled by the defendant. On November 21, 1985, the plaintiff began this action to recover damages in connection with the water main breaks, based, inter alia, on the defendant's alleged failure to protect and provide adequate support for the water mains. The plaintiff claims that it is a third-party beneficiary of the contract and its complaint seeks recovery on theories of breach of contract, negligence, trespass and violation of General Business Law article 36. The defendant moved to dismiss the plaintiff's claims on the ground that they were barred by the Statute of Limitations (CPLR 214; 213 [2]).

The plaintiff's status as a third-party beneficiary of the contract has not yet been determined and is not properly before us on this appeal. Therefore, it cannot be said whether the plaintiff's causes of action have their genesis in contract. Accordingly, we cannot determine on this record whether the period of limitations with respect to the plaintiff's claims is the six-year period applicable to claims having their genesis in the contract or some shorter limitation period (see, Sears, Roebuck Co. v Enco Assocs., 43 N.Y.2d 389, 394; Lewis v Axinn, 100 A.D.2d 617; Baratta v Kozlowski, 94 A.D.2d 454). Furthermore, the period of limitation with respect to a cause of action for breach of a construction contract begins to run upon completion of construction (see, Phillips Constr. Co. v City of New York, 61 N.Y.2d 949; State of New York v Lundin, 60 N.Y.2d 987). However, the defendant has not submitted the construction contract or any other evidence to show when it completed the "actual physical work" on the contract (see, Cabrini Med. Center v Desina, 64 N.Y.2d 1059; Phillips Constr. Co. v City of New York, 61 N.Y.2d 949, supra; State of New York v Lundin, 60 N.Y.2d 987, supra). Accordingly, we conclude that the defendant has not shown that it is entitled to judgment as a matter of law and, therefore, its motion for summary judgment was properly denied (see, Winegrad v New York Univ. Med. Center, 64 N.Y.2d 851, 853). We note, however, that the trial court was incorrect insofar as it indicated that any of the plaintiff's claims accrued when the injury was discovered. Kunzeman, J.P., Weinstein, Rubin and Kooper, JJ., concur.


Summaries of

Suffolk County Water Auth. v. J.D. Posillico

Appellate Division of the Supreme Court of New York, Second Department
Dec 30, 1988
145 A.D.2d 623 (N.Y. App. Div. 1988)
Case details for

Suffolk County Water Auth. v. J.D. Posillico

Case Details

Full title:SUFFOLK COUNTY WATER AUTHORITY, Respondent, v. J.D. POSILLICO, INC.…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Dec 30, 1988

Citations

145 A.D.2d 623 (N.Y. App. Div. 1988)

Citing Cases

Hunter's Run Stables v. Triple H

N.Y.C.P.L.R, § 213(2). Generally, in actions involving construction or building contracts, the statute of…