From Casetext: Smarter Legal Research

Stieglitz v. Belding

Supreme Court, Appellate Term
May 1, 1897
20 Misc. 297 (N.Y. App. Term 1897)

Opinion

May, 1897.

George M. MacKellar, for appellant.

Michael H. Cardozo and Edgar J. Nathan, for respondent.


The action was upon a "Lloyd's" fire insurance policy, to which the defendant was one of several underwriters, and upon this appeal the sufficiency of a separate defense, set forth below, is the matter in question. This defense was:

"First. That the firm of D.R. Satterlee Co., composed of Douglass R. Satterlee and Elizabeth K. Satterlee, which said firm are the attorneys in fact, under said policy of insurance described in the complaint, for this defendant and all of the underwriters upon the said policy, are as such firm and as individuals, underwriters with this defendant upon said policy of insurance.

"Second. That in and by the policy of insurance described in the complaint it is provided that no action shall be brought by the assured to enforce the provisions of the said policy, except against the said firm of D.R. Satterlee Co., as representing all of the underwriters, and that each of the underwriters, upon said policy, including this defendant, therein and thereby agreed to abide the result of any suit so brought against the said firm of D.R. Satterlee Co., as fixing the individual responsibility of each underwriter, including this defendant, under said policy."

Following this appear allegations of the failure to comply with the provisions thus set forth as contained in the contract, but the instrument itself is not made a part of the pleadings.

The respondent's contention upon this appeal is that the defense, as pleaded, fell within the decision of Knorr v. Bates, 14 Misc. 501; 12 id. 395, wherein a demurrer by the defendant to an action upon a contract, which contained a provision somewhat similar in purport to that now alleged, and which provision appeared by the complaint to have been uncomplied with, was overruled upon the ground that a condition precluding an action against any of the persons who had assumed the contract obligations was void because contrary to public policy, in that it sought to deprive the insured of the right of redress and the courts of the right to afford relief.

In the case cited, the condition operated to permit the maintenance of any action against the underwriters and left the insured to an action against the "attorneys in fact" who appeared to have no connection, contractually, with the underwriters' obligations and against whom an action could not, apparently, be maintained.

The question now before us, however, is by no means the same, since here the condition called for the prior determination of an action not against "attorneys in fact" unconnected with the contract, but against a firm made up of two of the actual underwriters, parties jointly and severally to the plaintiff's contract, as against whom a judgment could properly be obtained.

The decision in Knorr v. Bates, supra, applies to the present case to no greater degree than it applied to the facts before the court in New Jersey Penn. Concentrating Works v. Ackermann, 6 A.D. 540, and is distinguishable for the reasons there adopted. In the Ackermann case the policy prohibited the assured from maintaining an action against more than one of the underwriters at a time, and provided that a final decision in any suit thus brought should be conclusive as to the amount of the claim of the assured against each of the others.

The court held that Knorr v. Bates had no application ( 6 A.D. 540), since in the case considered the assured was protected by the maintenance of an action against one of the contracting parties (the others being bound by the result), while in Knorr v. Bates the basis of the decision was that no action could be maintained, according to the condition, except against persons not parties and so in no way bound.

The defense pleaded in this action was not founded upon a condition which precluded the assured's right of redress, since his claim could well be established in the suit against the particular underwriters named, and we can find no reason for holding that the provision was obnoxious in that the preliminary action was to be against underwriters named by the contract rather than against one selected by the assured.

It was competent to the parties to stipulate that but one action might be maintained upon the contract itself (if the action provided for was one available in contemplation of law), the effect being the avoidance of a multiplicity of actions and the remedy of the assured being complete because of the agreement by the several underwriters to abide the event of the original action, their agreement thus to respond being enforcible, subsequently, at the instance of the assured. Concentrating Works v. Ackermann, supra.

We have, therefore, under the allegations considered, no case of a condition repugnant to public policy and the defense alleged was sufficient in law.

It may be said that these parties have differed, not as to the rules applicable to the case, but as to the facts alleged in this particular defense, the plaintiff's construction of the allegations being that the preliminary suit was to be brought against the firm of D.R. Satterlee Co., as attorneys in fact, only, while the defendant takes the words used as intending an action against the members of this firm, individually, as underwriters.

The pleading is, in a sense, duplicitous, since either of these views was permissible, and the plaintiff may have been in a position to move the court below for a direction that the two possible defenses alleged should be separately stated (Code Civ. Pro., § 507) or that the answer be made more definite and certain, so far (Code Civ. Pro., § 546), but the matter alleged was not open to attack by demurrer, a defense being disclosed by averments which, although indefinite, were sufficient under the construction which must be adopted in determining an issue such as that raised here. Marie v. Garrison, 83 N.Y. 14; Milliken v. W.U.T. Co., 110 id. 403.

We have to do only with the allegations, not with the proof which the defendant may be prepared to produce, and the question whether this case falls within the decision of Knorr v. Bates, on the one hand, or of Concentrating Works v. Ackermann, on the other, is one which can be determined only upon the trial.

Judgment reversed and judgment directed for defendant upon the demurrer, with costs.

DALY, P.J., and McADAM, J., concur.

Judgment reversed and judgment directed for defendant on the demurrer, with costs.


Summaries of

Stieglitz v. Belding

Supreme Court, Appellate Term
May 1, 1897
20 Misc. 297 (N.Y. App. Term 1897)
Case details for

Stieglitz v. Belding

Case Details

Full title:LOUIS STIEGLITZ, Respondent, v . MILO M. BELDING, Jr., Appellant

Court:Supreme Court, Appellate Term

Date published: May 1, 1897

Citations

20 Misc. 297 (N.Y. App. Term 1897)
45 N.Y.S. 670

Citing Cases

Ralli v. White

This provision has been before the courts in actions on similar policies, and it has been decided that where…