From Casetext: Smarter Legal Research

S.J. Fuel Co. v. NYC Hous. Auth.

SUPREME COURT OF THE STATE OF NEW YORK — NEW YORK COUNTY PART 60
Mar 20, 2009
2009 N.Y. Slip Op. 33400 (N.Y. Sup. Ct. 2009)

Opinion

INDEX NO. #601609-2008

03-20-2009

S.J. FUEL CO., INC., Plaintiff, v. NEW YORK CITY HOUSING AUTHORITY (CONTRACT NO. ME0100029) Defendant.


PRESENT: BERNARD J. FRIED Justice MOTION DATE #001

MOTION SEQ. NO. ___

MOTION CAL. NO. ___

Defendant New York City Housing Authority moves to dismiss this action.

Plaintiff S.J. Fuel Co., Inc.'s complaint asserts a single cause of action for breach of contract, based upon defendant's alleged failure to pay additional compensation in the amount of $2,076,843.90. According to the complaint, plaintiff is due these monies because of "undisclosed and unforseen site conditions" encountered at the site which were "vastly different than as represented" on plans & etc. provided by defendant, The complaint alleges that "[o]n or about April 2, 2008, the plaintiff duly presented its claims to [defendant] for adjustment by the filing of plaintiff's Notice of Claim".

In seeking dismissal of this action, the defendant contends that (1) the plaintiff failed to comply with the Notice of Claim provision of the Contract, a condition precedent to commencing this action; (2) this action is barred by the statute of limitations; and 3) plaintiff cannot recover damages for a pass-through claim which belongs to its subcontractor.

As noted at oral argument, this ground has been abandoned by the defendant. (Tr. p. 5).

Because I am persuaded that the plaintiff has failed to comply with the written notice requirement this motion is granted.

Section 23 of the Contract's General Conditions requires the filing of a notice of Claim within 20 days, after the claim arises. Here Plaintiff's failed to file a timely notice of claim. Its claim for damages arose on June 17, 2005, when the defendant wrote a letter rejecting plaintiff's claim for additional work. (Mialkowski Aff., Ex. H). Plaintiff's subsequent letter, dated July 6, 2005, although sent within 20 days, does not constitute a notice of claim for "Extra Work entailing extra cost, or claims [for] compensation for any damages", i.e., it did not meet the requirements stated in ''Section 23- CLAIMS". Clearly, there was a failure of the plaintiff to give the defendant timely written notice of the claim. This untimeliness, alone, requires dismissal of the action. (E.g., Kovachevich v. New York City Housing Authority, 290 AD 2d 325 [1st Dept., 2002] and Master Painting and Roofing Corp., v. New York City Housing Authority, 258 Ad2d 275 [1st Dept., 1999][cited in Kovachevich]). Furthermore, the plaintiff's letter, as a matter of law is defective (Bat-Jac Contracting, Inc. v. New York City Housing Authority, 1 AD3d 128 [1st Dept., 2003]).

There was no statement "of intention to make a claim for such extra", no statement of "the nature and amount of the extra cost or damages sustained"; and no statement of the basis of the Claim against the [defendant]".

Further discussion is unwarranted, and this action is dismissed. Dated: 3/20/09

/s/ _________

J.S.C.


Summaries of

S.J. Fuel Co. v. NYC Hous. Auth.

SUPREME COURT OF THE STATE OF NEW YORK — NEW YORK COUNTY PART 60
Mar 20, 2009
2009 N.Y. Slip Op. 33400 (N.Y. Sup. Ct. 2009)
Case details for

S.J. Fuel Co. v. NYC Hous. Auth.

Case Details

Full title:S.J. FUEL CO., INC., Plaintiff, v. NEW YORK CITY HOUSING AUTHORITY…

Court:SUPREME COURT OF THE STATE OF NEW YORK — NEW YORK COUNTY PART 60

Date published: Mar 20, 2009

Citations

2009 N.Y. Slip Op. 33400 (N.Y. Sup. Ct. 2009)