Opinion
515406.
10-29-2015
Harriton & Furrer, LLP, Armonk (Urs Broderick Furrer of counsel), for appellants-respondents. Tabner, Ryan & Keniry, LLP, Albany (Thomas R. Fallati of counsel), for respondent-appellant.
Harriton & Furrer, LLP, Armonk (Urs Broderick Furrer of counsel), for appellants-respondents.
Tabner, Ryan & Keniry, LLP, Albany (Thomas R. Fallati of counsel), for respondent-appellant.
Before: PETERS, P.J., McCARTHY, GARRY and ROSE, JJ.
Opinion
ROSE, J.Cross appeals (1) from an order of the Supreme Court (Teresi, J.), entered October 5, 2012 in Albany County, which, in action No. 1, among other things, denied plaintiff's cross motion seeking to amend its pleading to add certain affirmative defenses, (2) from an order of said court, entered October 15, 2012 in Albany County, which, in action No. 1, denied certain defendants' motion to reargue, (3) from an order of said court (McDonough, J.), entered January 24, 2014 in Albany County, upon a decision of the court in favor of Science Applications International Corporation, and (4) upon the judgment entered thereon.
ExxonMobil Corporation sold and/or assigned lease rights to 47 gas station sites in upstate New York to various entities affiliated with Lehigh Gas Corporation (hereinafter collectively referred to as Lehigh). Both ExxonMobil and Lehigh were aware that the sites were affected by varying degrees of petroleum contamination, and the purchase and sale agreements required Lehigh to assume, in perpetuity, all liability resulting from any such contamination. They also executed three Remediation Escrow Agreements whereby ExxonMobil agreed to, among other things, establish and fund escrow accounts for the purpose of covering the estimated costs for Lehigh to achieve regulatory closure of the spill numbers established by the Department of Environmental Conservation (hereinafter DEC) for each of the 47 sites.Thereafter, Lehigh hired defendant Environmental Risk Solutions, LLC (hereinafter ERS) as its environmental remediation contractor. ERS, in turn, retained Science Applications International Corporation (hereinafter SAIC), with whom it had a preexisting Professional Services Master Agreement (hereinafter PSMA), as its subcontractor to perform the actual onsite remediation work. To that end, ERS and SAIC entered into three separate subcontracts designated as Project Specific Scopes of Work (hereinafter PSSW) that were, as relevant here, identical in language. The PSSWs required SAIC to perform remediation at each site for a fixed price, regardless of the actual site-specific cleanup costs incurred in achieving the appropriate remediation standard, with the fixed price for each site to be paid from the escrowed funds.
After SAIC obtained closure of DEC spill numbers at 18 of the 47 sites, ERS—at Lehigh's request—notified SAIC that it was being “terminated for convenience” pursuant to section 14.2 of the PSMA. SAIC then wound down its operations and submitted final invoices to ERS for payment. When no further payments were forthcoming, SAIC filed notices of mechanic's liens on seven of the sites based upon remediation work that it had allegedly performed and for which it was not fully compensated. Thereafter, SAIC commenced action No. 1 alleging, among other things, breach of contract against ERS and seeking the foreclosure of the mechanic's liens against Lehigh. Lehigh responded with action No. 2, which alleged, among other things, breach of contract against ERS and SAIC. Action Nos. 1 and 2 were joined and, following discovery and extended motion practice, Supreme Court (Teresi, J.), issued an order entered October 5, 2012, which, among other things, denied SAIC's request to amend its pleadings. SAIC and Lehigh cross-appeal from this order.
These cross appeals must be dismissed, inasmuch as SAIC concedes in its brief that its cross appeal is moot, and Lehigh has effectively abandoned its cross appeal by failing to raise in its brief any argument regarding this order's propriety (see Mayr v. Alvarez, 130 A.D.3d 1199, 1200 n. 1, 14 N.Y.S.3d 530 [2015] ; Miller v. Genoa AG Ctr., Inc., 124 A.D.3d 1113, 1114 n., 2 N.Y.S.3d 650 [2015] ). To the extent that Lehigh also appeals from the court's October 15, 2012 order denying its subsequent motion to reargue, no appeal lies therefrom (see Schillaci v. Sarris, 122 A.D.3d 1085, 1087, 997 N.Y.S.2d 504 [2014] ; Matter of Yager v. Massena Cent. Sch. Dist., 119 A.D.3d 1066, 1068–1069, 989 N.Y.S.2d 177 [2014] ).
On the eve of trial, Lehigh settled all of its outstanding claims against ERS. SAIC then agreed to sever all of its claims and cross claims against ERS, thereby removing ERS as a party to these actions. Following a five-week nonjury trial, Supreme Court (McDonough, J.) issued a decision and order entered January 24, 2014 that, among other things, permitted foreclosure of six of SAIC's mechanic's liens and dismissed Lehigh's counterclaims in action No. 1. As for action No. 2, Supreme Court determined that Lehigh had failed to prove its causes of action for breach of contract and fraud, denied its remaining claims and dismissed SAIC's counterclaims. Supreme Court also denied each party's request for counsel fees. The court then entered judgment in accord with its order, and SAIC and Lehigh now cross-appeal from both the order and the judgment.
Upon our review of a nonjury trial, we will independently review the record and grant any judgment that we find to be warranted (see Mazza v. Fleet Bank, 16 A.D.3d 761, 762, 790 N.Y.S.2d 730 [2005] ; Amodeo v. Town of Marlborough, 307 A.D.2d 507, 508, 763 N.Y.S.2d 132 [2003] ). While our overall review of Supreme Court's order and judgment is rooted in New York law, we will accept the parties' agreement that Lehigh's claim in action No. 2—that SAIC breached the PSSWs by failing to fully perform its remediation obligations—is governed by Pennsylvania law. Under Pennsylvania law, “[t]he necessary material facts that must be alleged for such an action are simple: there was a contract, the defendant breached it, and plaintiffs suffered damages from the breach” (McShea v. City of Philadelphia, 606 Pa. 88, 97, 995 A.2d 334, 340 [2010] ; see Stein v. Magarity, 102 A.3d 1010, 1013–1014 [PA.Super.2014] ). Here, neither Lehigh nor SAIC questions the validity of the PSSWs. Rather, the central issue in this dispute is one of contract interpretation, as the parties present starkly contrasting views of how the PSSWs define the scope of SAIC's remediation obligations.
When a court must resolve questions of contract interpretation, “[t]he fundamental rule ... is to ascertain and give effect to the intent of the contracting parties” (Murphy v. Duquesne Univ. of The Holy Ghost, 565 Pa. 571, 590–591, 777 A.2d 418, 429 [2001] ; see Robert F. Felte, Inc. v. White, 451 Pa. 137, 143, 302 A.2d 347, 351 [1973] ). If the terms of the contract are unambiguous, “the intent of the parties is to be ascertained from the document itself” (Insurance Adjustment Bureau, Inc. v. Allstate Ins. Co., 588 Pa. 470, 481, 905 A.2d 462, 468 [2006] ; see Lesko v. Frankford Hospital–Bucks County, 609 Pa. 115, 123, 15 A3d 337, 342 [2011] ). However, when a contract is “reasonably susceptible of different constructions and capable of being understood in more than one sense” (Trizechahn Gateway LLC v. Titus, 601 Pa. 637, 653, 976 A.2d 474, 483 [2009] [internal quotation marks and citation omitted]; accord Ferrer v. Trustees of Univ. of Pa., 573 Pa. 310, 339, 825 A.2d 591, 608 [2002] ), “parol evidence is admissible to explain or clarify or resolve the ambiguity, irrespective of whether the ambiguity is patent, created by the language of the instrument, or latent, created by extrinsic or collateral circumstances” (Insurance Adjustment Bureau, Inc. v. Allstate Ins. Co., 588 Pa. at 481, 905 A.2d 462 ).
Here, we agree with Supreme Court that most of the disputed terms regarding SAIC's remediation obligations under the PSSWs are “a compromised hodgepodge of conflicting proposals” susceptible to several reasonable interpretations. As an example, Lehigh's argument that section 5(a)(1) of the PSSWs unambiguously required SAIC to, among other things, meet a stringent, contractually defined “Cleanup Standard” is belied by section 5(a)(3) of the PSSWs, which—also unambiguously—permits SAIC to remediate the sites by, among other things, achieving regulatory closure of the spill numbers from DEC, as indicated by receipt of “no further action” (hereinafter NFA) letters from DEC.
As an additional example, SAIC argues that Lehigh's consent to seek spill number closures pursuant to section 5(a)(3) of the PSSWs could be obtained passively via the review and comment procedure set forth in section 5(p) of the PSSWs. Nowhere in the PSSWs, however, does it indicate that SAIC could rely on this subsection to obtain Lehigh's consent—passively or otherwise—to proceed with regulatory closure pursuant to section 5(a)(3). Likewise, the PSSWs fail to provide any alternative mechanism or procedure for Lehigh to review and comment on SAIC's submissions to DEC. This failure on the part of Lehigh and SAIC to articulate an adequately defined procedure for how SAIC was to obtain Lehigh's consent to proceed with an alternate cleanup standard left the ultimate formation of such a procedure susceptible to the varied and subjective constructions of the parties, thus creating additional ambiguity.
Further ambiguity arose with regard to section 5(g) of the PSSWs, an inherently contradictory provision governing when SAIC's remediation work at a given site could be considered complete. In its first clause, section 5(g) references SAIC's obligations pursuant to section 5(a)(1) of the PSSWs, stating that “SAIC's remediation and monitoring obligations under this [PSSW] shall cease upon attainment of the Cleanup Standard and receipt of [NFA] Status from DEC for each [s]ite as defined in [section 5(a) ]” (emphasis added). However, the very next clause contradicts the prior one, stating that, “[u]pon receipt of [NFA] Status confirmation from DEC, SAIC's remediation and monitoring obligations shall cease, except for re-openers to the extent found to be due to SAIC's negligence[.]” In light of these ambiguities, we find that Supreme Court appropriately considered parol evidence to determine both the intent of the parties and whether SAIC breached the PSSWs (see Insurance Adjustment Bureau, Inc. v. Allstate Ins. Co., 588 Pa. at 481, 905 A.2d 462 ; Murphy v. Duquesne Univ. of The Holy Ghost, 565 Pa. at 591, 777 A.2d 418 ).
Generally speaking, under Pennsylvania law, when considering parol evidence to resolve contractual ambiguities, the course of performance between the contracting parties is “perhaps the strongest indication of what the writing means” (Atlantic Richfield Co. v. Razumic, 480 Pa. 366, 376, 390 A.2d 736, 741 [1978] ; accord Matt Lamb & Sons, Inc. v. Christian Schmidt Brewing Co., 336 Pa.Super. 341, 351, 485 A.2d 836, 841 [1984] ). Indeed, “[w]herever reasonable, the manifestations of intention of the parties to a promise or agreement are interpreted as consistent with each other and with any relevant course of performance” (Sunbeam Corp. v. Liberty Mut. Ins. Co., 566 Pa. 494, 501, 781 A.2d 1189, 1193 [2001] [internal quotation marks and citation omitted]; accord Solomon v. U.S. Healthcare Systems of Pa., Inc., 797 A.2d 346, 350 [PA.Super.2002], lv. denied 570 Pa. 688, 808 A.2d 573 [2002] ).
Here, SAIC concedes that, during the performance of its remediation obligations, it never met the more stringent cleanup standards required by section 5(a)(1) of the PSSWs. Nonetheless, SAIC maintains that it fully complied with its remedial obligations by obtaining Lehigh's passive consent to utilize the alternative cleanup standards required to obtain spill number closures in accordance with section 5(a)(3) of the PSSWs. We agree. The evidence reveals that, prior to requesting closure of an open spill number from DEC, it was SAIC's regular practice to post relevant documentation, including, among other things, remedial action plans, to a File Transfer Protocol (hereinafter FTP) site to allow for review and comment by ERS and Lehigh pursuant to the terms of section 5(p) of the PSSWs. Each time it posted such information to the FTP site, if SAIC did not receive any objections within the 10–day review period provided by section 5(p), SAIC assumed—as section 5(p) entitled it to do—that ERS and Lehigh had approved its proposed submissions and, by extension, consented to its remedial action plan as required by section 5(a)(3). This, in turn, prompted SAIC to contact DEC and seek closure of the spill number pursuant to DEC's Spill Guidance Manual.
Remedial action plans provided detailed designs of the intended cleanup strategy for a given site and, as such, were an instrumental component of each application to DEC seeking spill number closure.
--------
Between late 2006, when remediation work began, and late 2008, SAIC relied solely upon the above-described procedure to seek and obtain consent from Lehigh to pursue spill number closures according to its remedial action plans. These extensive, highly detailed plans were proposals to utilize the cleanup standards authorized by section 5(a)(3) of the PSSWs, and should have been considered as such by Lehigh, a sophisticated party undoubtedly familiar with the subject matter. At no point during this two-year period did ERS or Lehigh ever object to the remedial action plans or other documentation that SAIC posted on the FTP site, and there is no evidence tending to show that Lehigh was unable to do so. In our view, given that SAIC obtained spill number closure in accordance with the Spill Guidance Manual at 18 sites, and inasmuch as the parties' course of performance leading up to the closures is consistent with SAIC's interpretation of subsections (a)(3) and (p) of section 5, we find that the parties intended to permit SAIC to obtain Lehigh's passive consent to seek spill number closure pursuant to section 5(a)(3), and that Lehigh manifested its consent by not objecting to SAIC's remedial action plans, or any other relevant documentation, within the section 5(p) review period (see Sunbeam Corp. v. Liberty Mut. Ins. Co., 566 Pa. at 501, 781 A.2d 1189 ; Solomon v. U.S. Healthcare Systems of Pa., Inc., 797 A.2d at 350 ).
We likewise reject Lehigh's contention that the PSSWs required DEC to make express findings of infeasibility in order for SAIC to utilize section 5(a)(3) of the PSSWs, as the claim is contradicted by the plain language of that subsection. Lehigh also claims that SAIC should not have attempted to obtain its consent through the PSSWs and, instead, should have sought it in accordance with the PSMA. Lehigh, however, was neither a party nor a third-party beneficiary to the PSMA and, thus, Lehigh cannot argue that the consent procedures between it and SAIC are governed by anything other than the PSSWs, to which Lehigh was expressly made a third-party beneficiary.
The parties' course of performance between late 2008 and mid 2009 leads us to the further conclusion that, despite the conflicting language in section 5(g) of the PSSWs, the parties intended to relieve SAIC of any further remediation obligations at a given site upon achieving NFA status, regardless of whether the more stringent cleanup standard set forth in section 5(a)(1) of the PSSWs had been met. Despite Lehigh's desire, after two years of acquiescence, to alter the consent procedure for future spill number requests, and despite the fact that residual petroleum contamination might remain at the 18 sites at which SAIC had already attained NFA status, Lehigh failed to charge SAIC with any breach of contract and did not specifically reserve any rights with respect thereto. Nor did Lehigh mandate that SAIC return to any of those sites to perform additional remediation in order to satisfy the more stringent standards set forth in section 5(a)(1). Instead, Lehigh agreed to move forward with remediation at the remaining 29 sites and approved payment of approximately $800,000 in SAIC invoices that were then in arrears. Accordingly, we concur with Supreme Court's determination to dismiss Lehigh's breach of contract claim in action No. 2, inasmuch as the parol evidence makes clear that SAIC performed its remedial obligations in accordance with the PSSWs. We likewise concur that, in action No. 2, Supreme Court appropriately dismissed Lehigh's fraud cause of action. In order to prevail upon its cause of action for fraud, Lehigh was required to establish that SAIC, “with the intent to deceive, misrepresented or omitted a material fact that [it] knew to be false and [Lehigh], in turn, justifiably relied upon such misrepresentation or omission, thereby incurring damages” (Revell v. Guido, 124 A.D.3d 1006, 1010, 2 N.Y.S.3d 252 [2015] ; see Mandarin Trading Ltd. v. Wildenstein, 16 N.Y.3d 173, 178, 919 N.Y.S.2d 465, 944 N.E.2d 1104 [2011] ; McColgan v. Brewer, 112 A.D.3d 1191, 1193, 977 N.Y.S.2d 790 [2013], lv. denied 24 N.Y.3d 911, 2014 WL 7152321 [2014] ). Here, Lehigh offered no evidence indicating that SAIC had any intention to not perform its contractual obligations pursuant to the PSSWs. We agree with Supreme Court's view that certain email messages between SAIC's managers could be characterized—at worst—as flippant, but they did not support a fraud cause of action. Nor could Lehigh have justifiably relied on any misrepresentations purportedly set forth by SAIC, as Lehigh had a full and fair opportunity to review and comment on SAIC's remedial action plans as well as the reprogramming of certain site-specific funds from one task to another pursuant to the procedure set forth in section 5(p) of the PSSWs. To the extent that Lehigh avers that SAIC misrepresented the degree of the contamination at various gas station sites, Supreme Court appropriately determined that its claims are premised on its dissatisfaction with SAIC's performance of its contractual obligations and duplicative of its breach of contract cause of action (see New York Univ. v. Continental Ins. Co., 87 N.Y.2d 308, 318–320, 639 N.Y.S.2d 283, 662 N.E.2d 763 [1995] ; Carpenter v. Plattsburgh Wholesale Homes, Inc., 83 A.D.3d 1175, 1176, 921 N.Y.S.2d 654 [2011] ; see also Demetre v. HMS Holdings Corp., 127 A.D.3d 493, 494, 7 N.Y.S.3d 110 [2015] ).
Next, we address a number of the arguments raised by the parties with regard to Supreme Court's award of damages. First, Lehigh argues that Supreme Court erred by granting SAIC's requests in action No. 1 to foreclose on six of SAIC's mechanic's liens. We disagree. To the extent that Lehigh argues, for the first time on appeal, that SAIC had no right to file the liens because the PSMA was not a “construction contract” and, thus, SAIC was not a “contractor” or “subcontractor” under General Business Law § 756, the argument is unpreserved for our review (see Anthony DeMarco & Sons Nursery, LLC v. Maxim Constr. Serv. Corp., 130 A.D.3d 1409, 1411 [2015] ). In any event, it is patently without merit, as the aforementioned definitions are particular to the General Business Law and are contradicted by separate definitions of the same terms in the Lien Law, which clearly allow SAIC to maintain the liens (see Lien Law § 2[9], [10] ).
Nor did Lehigh sufficiently prove that SAIC failed to perform the work for which it filed the subject liens or that it willfully exaggerated the amount of its lien claims. For the liens upon which it was allowed to foreclose, SAIC established the basis of each lien and the underlying unpaid work alleged to have been performed through the introduction of itemized statements of the lien claims, which were provided to Lehigh upon its demand (see Lien Law § 38 ; Associated Bldg. Servs., Inc. v. Pentecostal Faith Church, 112 A.D.3d 1130, 1131–1132, 976 N.Y.S.2d 699 [2013] ). Lehigh's largely conclusory and unsupported allegations to the contrary are, in any event, refuted by extensive course of performance evidence indicating that Lehigh was fully aware of SAIC's invoicing practices and had consented to them for years, both through section 5(p) of the PSSWs and by actually paying SAIC's invoices (compare Creech v. Rufa, 101 A.D.3d 1224, 1225–1226, 956 N.Y.S.2d 218 [2012] ; Tri–North Bldrs. v. Di Donna, 217 A.D.2d 886, 887, 629 N.Y.S.2d 850 [1995] ). Furthermore, we find no credible evidence in the record tending to indicate that SAIC willfully exaggerated the amounts of its lien claims (see Lien Law §§ 39, 39–a ; Saratoga Assoc. Landscape Architects, Architects, Engrs. & Planners, P.C. v. Lauter Dev. Group, 77 A.D.3d 1219, 1223, 910 N.Y.S.2d 571 [2010] ; Pyramid Champlain Co. v. Brosseau & Co., 267 A.D.2d 539, 542–543, 699 N.Y.S.2d 516 [1999], lv. denied 94 N.Y.2d 760, 706 N.Y.S.2d 80, 727 N.E.2d 577 [2000] ).
Finally, both Lehigh and SAIC argue that, pursuant to section 20.8 of the PSMA, they are entitled to recover costs and counsel fees from the other party. However, inasmuch as Lehigh is not a party to the PSMA, the only way that either Lehigh or SAIC would be entitled to enforce this provision against the other party is if Lehigh can be considered a third-party beneficiary to the PSMA (see Scarpitti v. Weborg, 530 Pa. 366, 372–373, 609 A.2d 147, 150 [1992] ). Here, ERS and SAIC unambiguously limited Lehigh's third-party beneficiary rights to the provisions of the PSSWs only. Thus, we find that neither SAIC nor Lehigh has the right to enforce any provision of the PSMA against the other, including section 20.8, which is the only provision in any of the contracts relevant to this appeal that allows for the recovery of costs and counsel fees (cf. Ribarchak v. Municipal Auth. of City of Monongahela, 44 A.3d 706, 709–710 [Pa.Cmwlth.2012], lv. denied 618 Pa. 692, 57 A.3d 73 [2012] ; Victoria Gardens Condominium Assn. v. Kennett Twp. of Chester County, 23 A.3d 1098, 1104–1106 [Pa.Cmwlth.2011], lv. denied 611 Pa. 644, 24 A.3d 365 [2011] ).
To the extent that Lehigh's remaining arguments have not been rendered academic by our decision, they have been considered and found to be without merit. We have also considered SAIC's arguments regarding its purported entitlement to additional damages beyond what was awarded by Supreme Court's judgment, and find that SAIC has failed to make a sufficient showing as to any of those claims.
ORDERED that the appeals from the orders entered October 5, 2012 and October 15, 2012 are dismissed, without costs.
ORDERED that order entered January 24, 2014 and the judgment are affirmed, without costs.
PETERS, P.J., McCARTHY and GARRY, JJ., concur.