From Casetext: Smarter Legal Research

Schnell Contracting Sys. v. Empire Outlet Builders LLC

Supreme Court of New York
Oct 21, 2021
2021 N.Y. Slip Op. 5796 (N.Y. Sup. Ct. 2021)

Opinion

2021-01563 Index 150619/20

10-21-2021

Schnell Contracting Systems L.L.C., Formerly Known as Schnell Contracting Services L.L.C., Plaintiff-Respondent, v. Empire Outlet Builders LLC, Care of BFC Partners Development LLC, et al., Defendants-Appellants, Fidelity and Deposit Company of Maryland et al., Defendants. Appeal No. 14435

Silverman Shin & Byrne PLLC, New York (Andrew V. Achiron of counsel), for appellants. Virginia & Ambinder, LLP, New York (John M. Harras of counsel), for respondent.


Silverman Shin & Byrne PLLC, New York (Andrew V. Achiron of counsel), for appellants.

Virginia & Ambinder, LLP, New York (John M. Harras of counsel), for respondent.

Before: Acosta, P.J., Manzanet-Daniels, Kern, Oing, Kennedy, JJ.

Order, Supreme Court, New York County (Melissa Anne Crane, J.), entered on or about April 14, 2021, which, to the extent appealed from as limited by the briefs, denied defendants' motion to dismiss the veil-piercing claims, unanimously affirmed, with costs.

The amended complaint asserts that the individual defendants controlled and owned defendants Empire Outlet Builders LLC c/o BFC Partners Development LLC and St. George Outlet Development LLC c/o BFC Partners, L.P. To support this allegation, plaintiff asserts that although Empire Builders and St. George had different organization formation documents, they effectively operated as a single integrated company, under the umbrella of BFC Partners, with both companies controlled and dominated by the same owners, officers, and managers, including defendants Brandon Baron, Joseph Ferrara, Donald Capoccia, and CFO Harry Zapiti. Moreover, the companies had the same location and email domain address, and the same business purpose of constructing the Empire Outlet Mall on Staten Island. These allegations, which must be accepted as true at this stage of the litigation (see Allianz Underwriters Ins. Co. v Landmark Ins. Co., 13 A.D.3d 172, 174 [1st Dept 2004]), militate in favor of finding complete control and domination over the entities (see Martinez v Plaza Prospect Apt., Inc., 25 A.D.3d 437, 438 [1st Dept 2006]).

The amended complaint further alleges that St. George received $284,375,000 from its lenders and that by and through Baron, Ferrara, and Capoccia, failed to disperse those funds to Empire Builders, purposefully undercapitalizing the latter entity. These allegations sufficiently assert that corporate funds were purposefully diverted to make Empire Builders judgment-proof (see Baby Phat Holding Co., LLC v Kellwood Co., 123 A.D.3d 405, 407 [1st Dept 2014]).


Summaries of

Schnell Contracting Sys. v. Empire Outlet Builders LLC

Supreme Court of New York
Oct 21, 2021
2021 N.Y. Slip Op. 5796 (N.Y. Sup. Ct. 2021)
Case details for

Schnell Contracting Sys. v. Empire Outlet Builders LLC

Case Details

Full title:Schnell Contracting Systems L.L.C., Formerly Known as Schnell Contracting…

Court:Supreme Court of New York

Date published: Oct 21, 2021

Citations

2021 N.Y. Slip Op. 5796 (N.Y. Sup. Ct. 2021)