CONTRACTS (58, 67) — CONSTRUCTION — PRELIMINARY NEGOTIATIONS — ORAL AGREEMENTS COLLATERAL TO WRITING. Where there was a written contract to dig a well, prior oral negotiations to the effect that the well was to produce water are merged in the writing, and cannot be pleaded in defense.

APPEAL (418) — REVIEW — VERDICTS. The jury's finding under proper instructions, on disputed evidence, as to which one of the parties breached the contract, is conclusive on appeal.

Appeal from a judgment of the superior court for Snohomish county, Alston, J., entered January 15, 1927, upon the verdict of a jury rendered in favor of the plaintiff, in an action on contract. Affirmed.

Louis A. Merrick, for appellant.

S.A. Bostwick, for respondent.


The respondent, a well-digger, contracted with the appellant, a farm-owner, to dig a well, which he never completed, and this suit was commenced to recover the unpaid balance of the contract price for the work performed. The jury returned a verdict for the amount sued for, and after judgment this appeal was taken.

[1] The appellant first urges that error was committed in striking from his answer certain affirmative allegations under which he would seek to prove that the intention of the parties, manifested by conversations and negotiations prior to the making of the written contract, was that a well was to be dug which would produce water. The court was correct in striking these allegations, for the reason that the prior negotiations were all merged in the written contract, and that contract not being ambiguous, it was improper to explain it in this way. Moreover, the court at the time of the trial, interpreted the contract in the manner contended for by the appellant and no prejudice therefore resulted from the striking of those portions of the affirmative answer.

Objection is also made to certain questions and the admission of certain testimony, but as we read the record the court was correct in its rulings in these regards.

[2] The issues in the case were reduced by the trial court to one, and the jury was instructed that there was but a single question of fact for it to decide. The court's instructions are unexcepted to, and the jury answered the question in favor of the respondent. The jury was told by the court that the respondent was required by his contract to continue the digging of the well until stopped by the appellant or until water was reached, and (it being an admitted fact that water was not reached) that the only question then "for you to determine is which one of the litigants breached the contract." Upon disputed testimony, the jury found that the appellant had caused the digging to be suspended and the well to be abandoned. There being substantial testimony to sustain this finding by the jury, it does not lie within the province of this court to interfere with the verdict or the judgment based on it.

Affirmed.

TOLMAN, PARKER, MITCHELL, and FRENCH, JJ., concur.


Summaries of

Peterson v. Hansen

The Supreme Court of Washington
Nov 23, 1927
260 P. 1074 (Wash. 1927)
Case details for

Peterson v. Hansen

Case Details

Full title:WILLIAM E. PETERSON, Respondent, v. JOHN B. HANSEN, Appellant

Court:The Supreme Court of Washington

Date published: Nov 23, 1927

Citations

260 P. 1074 (Wash. 1927)
260 P. 1074
145 Wash. 582

Citing Cases

Champlin v. Transport Motor Co.

There was here undoubted business compulsion exerted upon respondent, compelling him to enter into both…