People ex Rel. Jermain v. Thayer

Court of Appeals of the State of New York
Dec 7, 1875
63 N.Y. 348 (N.Y. 1875)

Opinion

Argued November 24, 1875

Decided December 7, 1875

Charles S. Fairchild for the appellant.

George W. Miller for the respondent.


The first objection made on behalf of the auditor to the payment of the award is, that the canal appraisers had no jurisdiction to hear the claim, as it was filed more than twelve years after the injuries were done.

The claimant, before the canal appraisers, claimed that in the location and construction of the enlarged Oswego canal, in the city of Oswego, the channel of the Oswego river was encroached upon and narrowed, and the prism of the channel reduced so as to cause a serious obstruction to the flow of water, in consequence of which the water was caused to set back upon his property adjacent to the Varick canal, injuring the same, and reducing the available head of water from said canal, and the damages awarded were for injuries thus caused to his property.

Prior to 1866, so far as I can discover, there was no general law authorizing the canal appraisers to appraise such damages. At first they were authorized only to appraise damages where any lands, waters or streams were permanently appropriated by the canal commissioners to the use of the public. (1 R.S., 225, § 46.) In 1836 (Laws of that year, chap. 287, § 10), jurisdiction was conferred upon them to appraise the damages where the canal commissioners had for temporary purposes occupied any lands, waters or streams. And these two laws specified all the cases in which they had authority to appraise damages, except when lands were overflowed by the erection of a dam on any river or stream connected with the public works (Laws of 1830, chap. 293, § 1), and except when damages were claimed for being deprived of a bridge over the canal. (Laws of 1839, chap. 207, as amended by chap. 372, Laws of 1840.) In 1866 (chap. 836) it was provided that every person interested in premises appropriated for the use of the canals, and "every person who shall claim to have sustained damages by reason of the temporary appropriation of his lands or waters, or any injury caused by the canals of this State, or the works connected therewith, if he intend to claim such damages, shall, within one year after such premises, lands or waters have been taken, permanently appropriated or temporarily occupied, and within one year after jurisdiction shall be conferred upon the canal appraisers by the legislature, to hear such other injury, file in the office of the canal appraisers a detailed statement of his claim," etc. It will be seen that this statute conferred no new jurisdiction upon the appraisers. It gave no authority to hear claims for injuries to lands not taken or appropriated. Such claims were not to be heard until jurisdiction to hear them was conferred upon the appraisers by some other act of the legislature.

Such were the laws and such the jurisdiction of the appraisers prior to 1870. And it appears that they had no authority to hear and award upon such claims as were presented by the relator in this case. But whether they had or not it is not necessary to determine in this case. For in that year (Laws of 1870, chap. 321), jurisdiction was granted to the appraisers "to hear and determine all claims against the State of any and all persons and corporations for damages alleged to have been sustained by them from the canals of the State or from their use and management, or resulting or arising from the negligence or conduct of any officer of the State having charge thereof, or resulting or arising from any accident or other matter or thing connected with the canals." It was, however, provided that no award should be made unless the facts proved should make out a case "which would create a legal liability against the State were the same established in evidence in a court of justice against an individual or corporation;" and that in such cases the appraisers should award to the claimant such sum as should be just and equitable; subject, however, to the right of appeal in all cases to the canal board in the manner provided by law. There was a further provision that claims under the act should be filed within two years from the time the damages occurred unless they had occurred more than one year prior to the passage of the act in which case they were to be filed within one year after its passage.

The claim in this case was filed under this act within the time specified therein. I can perceive no reasonable ground for arguing that it was not one of the claims which the appraisers were authorized under the act to hear. It was a claim for damages occasioned by the location and construction of the enlarged Oswego canal, and jurisdiction to hear such a claim was, first conferred by this act. It matters not how old the claim was; provided it was presented and filed within the year, the appraisers had jurisdiction to hear it. It is not necessary for us to decide whether, under the act, the appraisers were bound to disregard the statute of limitations and allow all claims, without reference to their age, for which if presented against an individual there would have been a legal liability; for the reason, having jurisdiction, if they erred in exercising it, and allowed a claim to which a good defence on the part of the State existed, their decision might have been erroneous, but their award would not have been void. The canal commissioners could have appealed to the canal board and had the error corrected, but the auditor could not refuse payment, so long as the award remained unreversed. Like the judgment of a court, its validity could not be attacked collaterally.

Another objection is made, that on two days when evidence upon the claim was taken but one of the canal appraisers was present, and that the award was finally made by the other two appraisers, he dissenting. This objection does not go to the jurisdiction of the appraisers or validity of the award. There is no allegation that all the appraisers did not consider all the evidence taken; and they certify that they made a personal examination of the premises alleged to be damaged as they were bound to under the law. (Laws of 1829, chap. 368.) There is no allegation that there was not sufficient evidence considered by all the appraisers to authorize the award. And the evidence thus taken may have been read before all the appraisers by counsel, and the irregularity, if one, may have been waived in some other way. But a complete answer to this objection is that there is no law requiring the evidence to be taken before all the appraisers or a majority of them. Section 3, of the act of 1870, provides that the board of canal appraisers "shall provide a general rule for the taking of evidence when the witness shall not be examined orally before said board and for reducing to writing and preserving said evidence when taken." Under this provision a rule could be made, and we must presume was made, authorizing evidence to be taken by one of the appraisers in the absence of the others.

The order must be affirmed, with costs.

All concur; except ALLEN, J., not voting.

Order affirmed.


Summaries of

People ex Rel. Jermain v. Thayer

Court of Appeals of the State of New York
Dec 7, 1875
63 N.Y. 348 (N.Y. 1875)
Case details for

People ex Rel. Jermain v. Thayer

Case Details

Full title:THE PEOPLE ex rel. JAMES B. JERMAIN, Respondent, v . FRANCIS S. THAYER…

Court:Court of Appeals of the State of New York

Date published: Dec 7, 1875

Citations

63 N.Y. 348 (N.Y. 1875)

Citing Cases

Rockaway Pacific Corp. v. State of New York

We think there can be no doubt about its sufficiency. We base this opinion upon what was held by the Court of…

Mark et al. v. the State

The rights of the claimants thus became barred, and they have not been restored by the provisions of the act…