From Casetext: Smarter Legal Research

MSI Construction Managers, Inc. v. Corvo Iron Works, Inc.

Michigan Court of Appeals
Jan 17, 1995
208 Mich. App. 340 (Mich. Ct. App. 1995)

Summary

holding that the words "to the extent" meant that the indemnitor was only responsible for reimbursing the indemnittee for that portion of the indemnitee's liability which represented the indemnitor's negligence

Summary of this case from Nusbaum v. City of Kansas City

Opinion

Docket No. 144824.

Submitted May 10, 1994, at Detroit.

Decided January 17, 1995, at 9:30 A.M.

Coticchio, Zotter, Sullivan, Molter, Skupin Turner, P.C. (by Walter J. Zotter), for MSI Construction Managers, Inc.

Harvey, Kruse, Westen Milan, P.C. (by Francis H. Poretta and Andrew C. Vredenburg), for Corvo Iron Works, Inc.

Before: MARILYN KELLY, P.J., and SHEPHERD and L.P. BORRELLO, JJ.

Circuit judge, sitting on the Court of Appeals by assignment.


Third-party defendant, Corvo Iron Works, Inc., appeals as of right from an order of judgment in favor of third-party plaintiff, MSI Construction Managers, Inc., in this negligence action.

Corvo claims that the trial court erred in failing to properly apportion fault and in assessing damages. It also alleges that certain evidence was erroneously admitted. We vacate a portion of the judgment.

I

In 1987, plaintiff Dale Frank was seriously injured in a construction site accident. MSI was the construction manager of the project. Corvo, a subcontractor, supplied the steel beams involved in the accident. Frank filed a claim against MSI. MSI, as third-party plaintiff, sued Corvo seeking indemnification.

At trial, MSI and Corvo disputed the effect to be given to an indemnification clause in the subcontract. Corvo claimed that, if it was found to be negligent, it would be liable only to the extent of its own negligence. MSI argued that the clause required Corvo to fully indemnify MSI if Corvo were found at all negligent. The judge permitted the jury to assess the relative degrees of fault between Corvo and MSI. He concluded that, if Corvo were found to be negligent, Corvo would be required to indemnify MSI to the full extent of the judgment.

The jury returned a verdict in favor of the Franks against MSI and Corvo. The jury found MSI to be sixty-five percent negligent and Corvo to be thirty-five percent negligent. The jury also found in favor of MSI against Corvo in the third-party suit. The order of judgment instructed Corvo to fully indemnify MSI for the entire amount awarded to the Franks.

II

On appeal, Corvo contends that the trial judge erred in requiring it to fully indemnify MSI for its negligence. Corvo contends that it should have been required to indemnify MSI only to the extent it was actually found to be negligent.

The disputed clause provides:

To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Owner, the Architect and the Contractor and all of their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorneys' fees arising out of or resulting from the performance of the Subcontractor's work under this Subcontract, provided that any such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease, or death or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom, to the extent caused in whole or in part by any negligent act or omission of the Subcontractor or anyone directly or indirectly employed by him or anyone for whose acts he may be liable, regardless of whether it is caused in part by a party indemnified hereunder. Such obligations should not be construed to negate, or abridge, or otherwise reduce any other right or obligation of indemnity which otherwise exists as to any party or person described in this Paragraph 11.11.

Indemnity contracts should be construed to ascertain and give effect to the intentions of the parties. Fischbach-Natkin Co v Power Process Piping, Inc, 157 Mich. App. 448, 452; 403 N.W.2d 569 (1987). In ascertaining their intentions, one must consider the language used in the contract as well as the situation of the parties and circumstances surrounding the contract. Meadows v Depco Equipment Co, 4 Mich. App. 370, 375; 144 N.W.2d 844 (1966). A provision which seeks to indemnify a promisee against liability for its own negligence is valid in the case of concurrent negligence by multiple tortfeasors. Fishbach-Natkin, p 461; Harbenski v Upper Peninsula Power Co, 118 Mich. App. 440, 453; 325 N.W.2d 785 (1982). An indemnity clause should be interpreted to give a reasonable meaning to all its provisions. Pritts v J I Case Co, 108 Mich. App. 22, 30; 310 N.W.2d 261 (1981).

Here, in contrast to Fishbach-Natkin and Pritts, the trial court erred in concluding that the clause required Corvo to fully indemnify MSI for the entire judgment awarded to the Franks. The indemnity clause envisions that Corvo will indemnify MSI. However, MSI's interpretation of the indemnity clause emphasizes only language which supports its position. It minimizes the importance of the phrase, "to the extent caused in whole or in part by any negligent act or omission of the Subcontractor." This language limits the extent of Corvo's liability.

We construe the contract most strictly against the party who is the indemnitee. Gartside v YMCA, 87 Mich. App. 335, 339; 274 N.W.2d 58 (1978). Here, when the various disputed phrases of the indemnity clause are emphasized equally, and none is ignored, the indemnity clause essentially provides:

To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Contractor from and against all claims arising out of the Subcontractor's work to the extent caused in whole or in part by any negligent act or omission of the Subcontractor.

MSI's claims to the contrary, the language here differs significantly from cases which have permitted indemnification. See Paquin v Harnischfeger Corp, 113 Mich. App. 43; 317 N.W.2d 279 (1982), Gartside, supra, Fishbach-Natkin, supra, and Pritts supra. Corvo is liable to MSI to the extent of its own negligence but is not required to indemnify MSI for MSI's negligence.

III

The trial court did not abuse its discretion when it allowed into evidence information concerning a citation issued to Corvo under the Michigan Occupational Safety and Health Act, MCL 408.1001 et seq.; MSA 17.50(1) et seq. De Voe v CA Hull, Inc, 169 Mich. App. 569, 577; 426 N.W.2d 709 (1988). The citation, although not dispositive on the issue of Corvo's negligence, was relevant as it intended to show that Corvo had not provided a safe work environment for its employees. It was not more prejudicial than probative. We find that it was properly admitted. MRE 402; MRE 403.

We vacate that portion of the trial court's order which required Corvo to fully indemnify MSI. We instruct the trial court to enter an order requiring MSI to pay sixty-five percent and Corvo to pay the remaining thirty-five percent of the judgment to the Franks.

SHEPHERD, J., did not participate.


Summaries of

MSI Construction Managers, Inc. v. Corvo Iron Works, Inc.

Michigan Court of Appeals
Jan 17, 1995
208 Mich. App. 340 (Mich. Ct. App. 1995)

holding that the words "to the extent" meant that the indemnitor was only responsible for reimbursing the indemnittee for that portion of the indemnitee's liability which represented the indemnitor's negligence

Summary of this case from Nusbaum v. City of Kansas City

holding that the words "to the extent" meant that the indemnitor was only responsible for reimbursing the indemnitee for that portion of the indemnitee's liability which represented the indemnitor's negligence

Summary of this case from East-Harding, Inc. v. Piazza Associates

holding that the words "to the extent" meant that the indemnitor was only responsible for reimbursing the indemnittee for that portion of the indemnitee's liability which represented the indemnitor's negligence

Summary of this case from Nusbaum v. City of Kansas City, Missouri

interpreting a similar provision — one that required the subcontractor to indemnify the contractor "to the extent caused in whole or in part by any negligent act or omission of the [s]ubcontractor," — and finding that the language limited the extent of the subcontractor's liability to its own negligence

Summary of this case from Honeywell Intern. v. Lutz Roofing Co.
Case details for

MSI Construction Managers, Inc. v. Corvo Iron Works, Inc.

Case Details

Full title:MSI CONSTRUCTION MANAGERS, INC v CORVO IRON WORKS, INC

Court:Michigan Court of Appeals

Date published: Jan 17, 1995

Citations

208 Mich. App. 340 (Mich. Ct. App. 1995)
527 N.W.2d 79

Citing Cases

General Motors Corp. v. American Ecology Environ. Serv.

See Taggart v. United States, 880 F.2d 867, 870 (6th Cir. 1989). While Michigan courts construe indemnity…

Zurich Insurance v. CCR & Co.

Emphasis supplied.] On the basis of this passage it is contended that, with respect to indemnity contracts,…