From Casetext: Smarter Legal Research

Meinhardt v. Investment Builders

Colorado Court of Appeals. Division I
Jan 8, 1974
518 P.2d 1376 (Colo. App. 1974)

Opinion

Nos. 73-076, 73-270.

Rehearing Denied January 8, 1974. December 18, 1973. Not Selected for Official Publication.

1. Contracts 322(4)

Evidence sustained finding that changes and additions requested by builder substantially increased the scope of labor and materials required beyond that contemplated by original oral contract and that electrical contractor continued work under the original oral contract until builder's security guards prevented access to the project.

2. Contracts 236

A meeting of minds of contracting parties is required not only to make a contract, but also to modify it.

3. Contracts 312(1)

Where original contract between builder and electrical contractor was negotiated on a unit-price basis covering the work set forth in original proposal and where changes required by builder substantially extended the scope of the electrical work beyond that contemplated in the oral agreement, electrical contractor was justified in seeking to negotiate new terms for the modified contract and such action did not constitute a breach by the electrical contractor.

4. Contracts 313(2)

A repudiation of a contract must consist of a present, positive, unequivocal refusal to perform the contract and a mere threat to abandon is not a "repudiation.

"See publication Words and Phrases for other judicial constructions and definitions.
5. Contracts 313

Mere declaration of a contingent intention not to be bound will not of itself amount to a breach, so as to constitute a renunciation of a contract.

6. Contracts 313

Where builder requested changes which substantially extended the scope of electrical work contemplated by oral contract, where electrical contractor and builder discussed entering into a written contract revising the oral contract on several occasions, and where electrical contractor left a proposed written contract with builder, letter from electrical contractor to builder giving builder the alternative of accepting the contract, paying for labor and materials expended to date, in which case electrical contractor would complete the contract on a cost-plus basis, or having contractor terminate the work was not a repudiation of the oral contract.

7. Contracts 312, 314

Where electrical contractor, who continued work under oral contract, was justified in seeking modification to the contract, and where letter sent to builder stating alternative proposals for written contract did not constitute a repudiation of the oral contract, electrical contractor did not breach the contract and builder, by refusing to allow electrical contractor to continue to perform, did breach the contract and such breach excused further performance by electrical contractor.

8. Work and Labor 14(3), 29(2)

When a construction contractor is confronted by a breach on the part of the other party, he may relinquish his rights under the contract and sue on a theory of quantum meruit, and, under such circumstances, his recovery is not limited by the contract rate.

9. Work and Labor 28(4)

Records which showed total value of labor and materials furnished by electrical contractor to builder and testimony by two independent electrical contractors as to the reasonableness of contractor's charges supported findings as to reasonable value of materials and services furnished to the builder.

10. Discovery 31

Where each party signified that it was ready for trial and where no objection was made to proceeding to trial, it was not an abuse of discretion to deny builder's request to take deposition of electrical contractor during appeal for purposes of impeaching testimony given by contractor at trial. Rules of Civil Procedure, rule 27(b).

Electrical contractor brought action to foreclose mechanic's lien on building project. The District Court, County of El Paso, Robert W. Johnson, J., entered judgment in favor of electrical contractor and builder appealed. The Court of Appeals, Coyte, J., held that electrical contractor was entitled to renegotiate contract in light of changes requested by builder; that letter giving builder the alternative of agreeing to a new contract or continuing on a cost-plus basis did not constitute a repudiation of the contract; that builder breached the contract by refusing to allow contractor to continue to perform; that upon breach, contractor could relinquish his rights under the contract and sue on theory of quantum meruit; that the evidence sustained findings as to the value of labor and materials furnished; and that it was not an abuse of discretion to deny builder's request to take deposition of contractor during appeal.

Affirmed.

Spurgeon, Aman Hanes, Richard W. Hanes, Gregory R. Piche, Colorado Springs, for plaintiff-appellee.

Frank W. Davis, Colorado Springs, Theodore M. Smith, Denver, for defendants-appellants.


Plaintiff purchased the electrical contracting business of Archie's Electric on March 15, 1972, from R. M. Archibald. As part of the transaction, plaintiff assumed an oral contract with Investment Builders Properties Company, a partnership composed of John W. Dawson and Joseph M. Birdsell, hereinafter referred to as defendants, for electrical work on an apartment complex under construction by them. Plaintiff worked on the apartment complex through June 15, 1972. On June 16th, defendants barred plaintiff's workmen from the project, and shortly thereafter they hired a different electrical contractor on a cost-plus basis to finish the project.

Plaintiff then filed a mechanic's lien statement and filed suit seeking to foreclose his lien claim. After trial to the court, judgment was entered in his favor in the amount of $62,053.07. Defendants appeal contending that plaintiff breached the original contract; that plaintiff could not recover on a quantum meruit basis when a contract establishing a fixed price was in existence; and that defendants should have been permitted to make discovery pending appeal. We affirm.

BREACH

The oral contract between Archie's Electric and defendants had a contract price of $65,000. This figure was agreed upon orally on approximately December 6, 1971. Under the terms of that oral agreement, defendants were to make monthly payments to the electrical contractor based upon materials delivered and incorporated into the project. At the time plaintiff assumed the contract, Archie's Electric had delivered approximately $20,000 worth of materials to the building site. Defendants were billed for this amount and for subsequent labor and materials incorporated into the project, but defendants refused to make any payments until a written contract was signed. In the meantime, defendants revised the plans for the apartment project and made significant field changes, alterations and additions to the electrical work, thereby increasing the scope of the labor and materials required beyond that contemplated in the original contract. Thereafter, on various occasions until June 2nd, the parties discussed the written contract and payments to be made; on that date, plaintiff left a proposed written contract with defendants which provided for a total contract price of $75,841. Defendants rejected that contract.

On June 6th, plaintiff wrote to defendants giving them the alternative of either accepting the $75,841 contract covering the expanded scope of electrical work or paying plaintiff for labor and materials expended to date, in which case plaintiff would complete the contract on a cost-plus basis. If neither of these alternatives were accepted, plaintiff stated that he would terminate work on the job and would seek to use available legal means to protect his position. No further contacts were made between the parties relative to a renegotiated contract.

On June 14th, a transformer was placed on the premises by the city, and defendants requested that power be connected so that it would be available in the buildings. Plaintiff advised defendants that he would not turn the power on until the contract issue was resolved, but he continued working on the project. On the morning of June 16th, defendants' security forces prevented plaintiff's employees from entering the project and thereafter continued to refuse them admittance.

The trial court found that the changes and additions requested by the defendants substantially increased the scope of the labor and materials required beyond that contemplated by the original oral contract. Further, the court found that plaintiff continued work under the original contract until June 16th, when defendants' security guards prevented access to the project. Since these findings were amply supported by the evidence, they will not be disturbed on review. Carter v. Pigg, 146 Colo. 306, 361 P.2d 437. [2,3] Plaintiff sought to renegotiate the total contract price to conform to additional work required by defendants. A meeting of minds of contracting parties is required not only to make a contract, but also to modify it after it is made. See Western Air Lines, Inc. v. Hollenbeck, 124 Colo. 130, 235 P.2d 792. Here, the original contract between the parties was negotiated on a unit-price basis covering the scope of work set forth in Archie's Electric's proposal of December 6, 1971, and the changes required by defendants substantially extended the scope of the electrical work beyond that contemplated in the agreement. The trial court correctly held that plaintiff was justified in seeking to negotiate new terms for the modified contract and that such action did not constitute a breach of contract by him.

[4-6] Defendants argue that plaintiff's letter of June 6th, which stated alternative proposals, constituted a repudiation of the contract. We disagree. A repudiation of a contract must consist of a present, positive, unequivocal refusal to perform the contract, and a mere threat alone to abandon is not a "repudiation." Gold Mining Water Co. v. Swinerton, 23 Cal.2d 19, 142 P.2d 22. Likewise, a mere declaration of a contingent intention not to be bound will not of itself amount to a breach, so as to constitute a renunciation of the contract. See Atkinson v. District Bond Co., 5 Cal. App.2d 738, 43 P.2d 867. Thus, we conclude that plaintiff's letter in the context of negotiation was not a repudiation of the contract.

Since the trial court found that plaintiff continued work under the original contract until he was prevented from further efforts by defendants, plaintiff was justified in negotiating the terms of modifications to the contract, and his letter stating alternative proposals did not constitute a repudiation of the contract. Accordingly, we hold that there was no breach of contract by plaintiff, and that defendants did breach the contract by refusing to allow plaintiff to continue performance. Such action on the part of defendants excused further performance by plaintiff. Jacobs v. Jones, 161 Colo. 505, 423 P.2d 321.

DAMAGES

On appeal, defendants argue that the trial court erred by awarding plaintiff the reasonable value of the labor and material utilized in the project because the construction contract fixed the total price to be paid and that price limits plaintiff's recovery to the percentage of completion of the contract performed by plaintiff. However, the trial court found that defendants' conduct constituted a breach of the contract which entitled plaintiff to rescind the contract and recover on a quantum meruit basis for the reasonable value of labor and materials. The complaint states a cause of action for the reasonable value of labor and materials without reference to the contract. When a construction contractor is confronted by a breach on the part of the other party, he may relinquish his rights under the contract and sue on a theory of quantum meruit, and, under such circumstances, his recovery is not limited by the contract rate. Jacobs v. Jones, supra; Zion Baptist Church v. Hebert, 94 Colo. 59, 28 P.2d 799; C. McCormick, Damages § 166.

Plaintiff testified as to the value of labor and materials furnished, which amounted to a total of $62,053.07. Plaintiff's records were examined by defendants' accountant and he testified that they were mathematically accurate. Two independent electrical contractors from the same area testified with respect to the reasonableness of plaintiff's charges. There was sufficient evidence to support the findings of the trial court as to the reasonable value of the materials and services furnished to the project, and accordingly, these findings will not be disturbed on review.

DISCOVERY

Defendants complain that the trial court refused to allow them to take the deposition of plaintiff during appeal. C.R.C.P. 27(b) provides the circumstances under which a deposition may be taken pending the appeal of a judgment. It is contended that testimony could be elicited in the deposition which would impeach certain testimony given by plaintiff at the trial. However, at the time of trial, each party signified that it was ready for trial and no objection was made to proceeding to trial. Whether to allow such a deposition is within the discretion of the trial court, and our review of the record discloses no abuse of discretion. Indeed, under the facts before us, we can see no basis on which it would have been proper to have allowed such a deposition to be taken.

Judgment affirmed.

SILVERSTEIN, C. J., and RULAND, J., concur.


Summaries of

Meinhardt v. Investment Builders

Colorado Court of Appeals. Division I
Jan 8, 1974
518 P.2d 1376 (Colo. App. 1974)
Case details for

Meinhardt v. Investment Builders

Case Details

Full title:Ben W. MEINHARDT, Plaintiff-Appellee, v. INVESTMENT BUILDERS PROPERTIES…

Court:Colorado Court of Appeals. Division I

Date published: Jan 8, 1974

Citations

518 P.2d 1376 (Colo. App. 1974)

Citing Cases

United States ex rel. Mobile Premix Concrete, Inc. v. Santa Fe Engineers, Inc.

Under Colorado law, use plaintiff cannot unilaterally modify the contract. A meeting of the minds of the…

Roe v. Aegis Wholesale Corp.

Albright v. McDermond, 14 P.3d 318, 324 (Colo. 2000). See also Lake Durango Water Co., Inc. v. Pub. Utils.…