McGinley v. Hardy

Supreme Court of California
Apr 1, 1861
18 Cal. 115 (Cal. 1861)

Summary

In McGinley v. Hardy, 18 Cal. 116, there was a modification of the contract, but the case is different from this in that there was no agreement that written demand should be made for extension of time, and the court very properly held that the new contract operated to extend the time for completion of the building.

Summary of this case from Suhr v. Metcalfe

Opinion

         Appeal from the Eleventh District.

         Suit for a balance claimed to be due on a written contract between plaintiff and defendants, by which the former was to erect for the latter a brick building of specified dimensions. The contract was dated October 20th, 1859, and the work was to be finished in seven weeks, for the price of $ 2,600. December 6th, 1859, the parties amended their contract by an endorsement thereon as follows, to wit: " It is further agreed between the above parties that the terms of the above contract be so far changed that said building shall be thirty-nine feet front, and the party of the first part (defendant) pay the party of the second part (plaintiff) one hundred and ten dollars extra." This would make the building several feet more front than per the original contract. October 20th, 1859, defendant leased to a responsible tenant for eighteen months one room in the building at seventy-five dollars per month, from December 20th, 1859, or as soon as the building was completed; and November 5th, 1859, defendant leased the other rooms for two years from January 1st, 1860, or as soon as the building was completed, at sixty-five dollars per month. Building completed February 28th, 1860. Defendant took possession February 21st, 1860, and two days thereafter paid plaintiff $ 2,392 " on said agreement," making no objection as to time. Plaintiff did extra work, besides altering the front, to the amount of forty-six dollars and seventy-five cents, and sues for three hundred and sixty-four dollars and seventy-five cents, being the balance claimed on the original contract, together with the forty-six dollars and seventy-five cents, and the one hundred and ten dollars for changing the front. The Court below gave plaintiff judgment for the amount claimed, holding that the agreement of December 6th, as to the front, being but one day prior to the time fixed in the contract for the completion of the building, necessarily extended the time, and waived damages, and that hence plaintiff could sue on the contract without resorting to the common counts, in which latter case only could defendant recoup.

         Defendant appeals.

         COUNSEL:

         Tuttle & Hillyer, for Appellant, cited 5 Hill, 63 and 76; 3 Id. 171; 1 Id. 48, 484; 22 Wend. 155; 7 Pick. 184; 8 Id 178; 14 Barb. 174.

          Hereford & Long, and Mills & Rowell, for Respondent, cited Chittyon Cont. 382; Vanderbilt v. Eagle Iron Works, 25 Wend. 665.


         JUDGES: Cope, J. delivered the opinion of the Court. Field, C. J. concurring.

         OPINION

          COPE, Judge

         We have examined the record in this case, and find no error for which the judgment should be reversed. The alterations in the plan of the building constitute a sufficient answer to any claim on the part of the defendant growing out of a failure to complete the contract within the time specified. The circumstances show very clearly a modification of the contract in this respect.

         Judgment affirmed.


Summaries of

McGinley v. Hardy

Supreme Court of California
Apr 1, 1861
18 Cal. 115 (Cal. 1861)

In McGinley v. Hardy, 18 Cal. 116, there was a modification of the contract, but the case is different from this in that there was no agreement that written demand should be made for extension of time, and the court very properly held that the new contract operated to extend the time for completion of the building.

Summary of this case from Suhr v. Metcalfe
Case details for

McGinley v. Hardy

Case Details

Full title:McGINLEY v. HARDY

Court:Supreme Court of California

Date published: Apr 1, 1861

Citations

18 Cal. 115 (Cal. 1861)

Citing Cases

Suhr v. Metcalfe

The extras, therefore, fall within said subdivision 3, and in order to claim an extension of time it was…

Semas v. Bergmann

It necessarily was a waiver of the time set for completion. (See McGinley v. Hardy (1861), 18 Cal. 115, to…