Maville v. Donaghue

Municipal Court of the City of Syracuse
Jan 8, 1948
193 Misc. 11 (N.Y. Misc. 1948)

Opinion

January 8, 1948.

Paul A. Androus for plaintiff.

George T. Driscoll for defendant.


Plaintiff agreed to paint and repair defendant's house for $300. When the job was half done defendant pointed out certain defects, and told the plaintiff in vigorous language to make them good or quit. Plaintiff quit immediately, and brought this action for breach of contract.

Though a good painter, plaintiff failed to fulfill his implied obligation to do this work in a good and workmanlike manner. The contract was entire; and having broken it, he cannot now recover in an action based upon it. The rule is that recovery on an entire contract requires full performance or a valid excuse. Nor can he recover on quantum meruit, though defendant has received some benefit. ( Barney's Clothes, Inc., v. W.B.O. Broadcasting Corp., 165 Misc. 532, affd. 253 A.D. 889; Apparel Accessories Associates v. New York World's Fair, 1940, 176 Misc. 26, affd. 261 A.D. 944.)

It is unnecessary to decide plaintiff's claim that this agreement was in the nature of a building contract, as to which the full performance rule has been somewhat relaxed, since he has shown neither substantial performance nor the cost of completing the work. In the case of Spence v. Ham ( 163 N.Y. 220) plaintiff fell short of full performance of a building contract, and failed to recover for substantial performance because he failed to show the cost of completing the job. The court held that the amount to be recovered for substantial performance is the contract price less a fair deduction for defects and omissions; and that plaintiff had the burden of showing the amount of such deduction.

Following this leading case it is well settled that a plaintiff who relies on substantial performance has the burden of showing the nature of the defects and omissions, that they are not substantial, and the cost of making them good. ( Nieman-Irving Co. v. Lazenby, 263 N.Y. 91; 5 Williston on Contracts [Rev. ed.], § 1475; 2 Clark's New York Law of Contracts, § 919, p. 1403, and cases cited.)

As to plaintiff's claim that full performance was excused by defendant's emphatic remarks, it is admitted that plaintiff was in no danger of bodily harm from the aged defendant; that the latter did not order him to stop work, nor state that he would not pay as agreed, nor otherwise terminate the contract; and that plaintiff abandoned the job without offering to correct and complete the work. It is therefore unnecessary to decide the disputed question as to what words the defendant used. Plaintiff had no valid excuse for quitting. (See discussion of excuse for performance: 12 Am. Jur., Contracts, §§ 344-346; 17 C.J.S., Contracts, § 459.)

Complaint dismissed, with costs.


Summaries of

Maville v. Donaghue

Municipal Court of the City of Syracuse
Jan 8, 1948
193 Misc. 11 (N.Y. Misc. 1948)
Case details for

Maville v. Donaghue

Case Details

Full title:CARL MAVILLE, Plaintiff, v. PETER F. DONAGHUE, Defendant

Court:Municipal Court of the City of Syracuse

Date published: Jan 8, 1948

Citations

193 Misc. 11 (N.Y. Misc. 1948)
82 N.Y.S.2d 621

Citing Cases

Triple M. Roofing Corp. v. Greater Jericho

The evidence failed to establish substantial performance of the contract upon the part of plaintiff (see…