Matter of Emp. St. Ch. v. Bd., Ed., Buffalo

Appellate Division of the Supreme Court of New York, Fourth Department
Feb 16, 2000
269 A.D.2d 801 (N.Y. App. Div. 2000)

Opinion

February 16, 2000

Appeal from Judgment of Supreme Court, Erie County, Flaherty, J. — CPLR art 78.

PRESENT: GREEN, A. P. J., HAYES, PIGOTT, JR., AND SCUDDER, JJ.


Judgment unanimously affirmed without costs.

Memorandum:

Respondent Board of Education of City of Buffalo (Board), in soliciting bids for phase two of the construction of Northwest Academy, required the successful bidders to comply with a project labor agreement (PLA). After the Board issued the specifications including a PLA, petitioners commenced this CPLR article 78 proceeding seeking to set aside the bids and compel the Board to readvertise for bids with new specifications. Supreme Court properly granted the Board's motion to dismiss the petition on the ground that the Board's decision to adopt a PLA as a bid specification was made in conformity with the guidelines set forth by the Court of Appeals in Matter of New York State Ch., Inc., Associated Gen. Contrs. of Am. v. New York State Thruway Auth. ( 88 N.Y.2d 56). Unlike in Matter of Empire State Ch. of Associated Bldrs. Contrs. v. City of Oswego ( 239 A.D.2d 875), the record in this case contains a detailed projection of cost savings as a result of using a PLA, prepared by an engineering and architectural firm hired by the Board as a consultant. The record also demonstrates that labor unrest occurred during phase one of the project as a result of a union and non-union contractor being on the jobsite at the same time ( cf., Matter of Empire State Ch. of Associated Bldrs. Contrs. v. City of Oswego, supra, at 876).

We have examined petitioners' remaining procedural arguments for invalidation of the bidding procedure and conclude that they lack merit. In light of our determination, we do not reach respondents' arguments concerning the lack of standing of petitioner Gregory R. Jones and the failure of petitioners to name necessary parties.


Summaries of

Matter of Emp. St. Ch. v. Bd., Ed., Buffalo

Appellate Division of the Supreme Court of New York, Fourth Department
Feb 16, 2000
269 A.D.2d 801 (N.Y. App. Div. 2000)
Case details for

Matter of Emp. St. Ch. v. Bd., Ed., Buffalo

Case Details

Full title:MATTER OF EMPIRE STATE CHAPTER OF ASSOCIATED BUILDERS AND CONTRACTORS…

Court:Appellate Division of the Supreme Court of New York, Fourth Department

Date published: Feb 16, 2000

Citations

269 A.D.2d 801 (N.Y. App. Div. 2000)
703 N.Y.S.2d 418

Citing Cases

In the Matter of E.W. Tompkins Co.

Even if we were to address the merits, we would find petitioner's arguments unpersuasive. Supreme Court…

L&M Bus Corp. v. New York City Department of Education

II. The courts below properly struck the New York City Department of Education's "right" to confiscate 2% of…