From Casetext: Smarter Legal Research

Dima Contracting Corp. v. Goldin

Appellate Division of the Supreme Court of New York, First Department
Feb 3, 1983
92 A.D.2d 460 (N.Y. App. Div. 1983)

Opinion

February 3, 1983


Judgment of the Supreme Court, New York County (Lehner, J.), entered on May 5, 1982, which dismissed the petitioner's CPLR article 78 proceeding seeking to review and annul the respondent's order and determination dated June 25, 1981, is unanimously reversed, on the law, and the petition granted to the extent of remanding the matter for a hearing to determine the validity of petitioner's consent to the stipulation entered into with respondent Comptroller of the City of New York, without costs or disbursements. On March 19, 1981, petitioner, a contractor who has bid upon and performed contracts for the respondent Board of Education of the City of New York, was served by respondent Comptroller of the City of New York with a notice of hearing and complaint alleging noncompliance with section 220 Lab. of the Labor Law (failure to pay the petitioner's employees with the prevailing wage rates). At the subsequent hearing, which was held in May of 1981, the petitioner entered into a stipulation conceding that it had willfully violated section 220 Lab. of the Labor Law. It consented to reimburse its employees for the wage differential and also agreed to discharge its legal counsel. Based upon petitioner's admissions, the hearing officer issued a written decision finding the petitioner in violation of the Labor Law, and, by order dated June 25, 1981, the comptroller adopted this determination. On September 23, 1981, the petitioner commenced the instant article 78 proceeding seeking to review and annul the comptrollers' order of June 25, 1981, as well as an order by the board of education forbidding the petitioner from receiving contracts for a period of three years. According to the petitioner, its agreement to the stipulation was procured by the false and fraudulent representations of the comptroller's representatives that it would suffer only certain monetary damages (moneys withheld from future contracts). However, its plea of guilty, did, in fact, cause it to be barred for three years from obtaining the board's contracts. Special Term, in dismissing the petition, held that the proceeding was untimely commenced in that it was instituted more than 30 days after the petitioner first became aware of the purported fraud. However, "where a governmental subdivision acts or comports itself wrongfully or negligently, inducing reliance by a party who is entitled to rely and who changes his position to his detriment or prejudice, that subdivision should be estopped from asserting a right or defense which it otherwise could have raised." ( Bender v. New York City Health Hosps. Corp., 38 N.Y.2d 662, 668.) Under the circumstances, the court should have directed a hearing on the issue of whether or not there is any merit to the petitioner's contention that its consent to the stipulation was the result of fraud and misrepresentation on the part of respondent comptroller.

Concur — Murphy, P.J., Carro, Asch, Silverman and Milonas, JJ.


Summaries of

Dima Contracting Corp. v. Goldin

Appellate Division of the Supreme Court of New York, First Department
Feb 3, 1983
92 A.D.2d 460 (N.Y. App. Div. 1983)
Case details for

Dima Contracting Corp. v. Goldin

Case Details

Full title:In the Matter of DIMA CONTRACTING CORP., Appellant, v. HARRISON GOLDIN, as…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Feb 3, 1983

Citations

92 A.D.2d 460 (N.Y. App. Div. 1983)

Citing Cases

Waterside Associates v. New York State Department of Environmental Conservation

As previously discussed, the Colvin letter was clearly authorized and in fact it was mandated by statute. The…