From Casetext: Smarter Legal Research

Matter of Board of Education of Schenevus

Appellate Division of the Supreme Court of New York, Third Department
Dec 29, 1994
210 A.D.2d 854 (N.Y. App. Div. 1994)

Opinion

December 29, 1994

Appeal from the Supreme Court, Otsego County (Ingraham, J.).


On August 27, 1991, respondent entered into a general construction contract with petitioner relating to the renovation and construction of an addition to the Schenevus Central School in the Village of Schenevus, Otsego County. As the result of various disputes with petitioner, on December 14, 1992, respondent served a demand for arbitration upon petitioner claiming that it was owed $25,000 in retainage funds. On January 14, 1993, respondent served an amended demand including additional claims and seeking $160,000 in damages. Thereafter, on January 28, 1993, the parties entered into an extension agreement adjourning arbitration until the time the entire project was substantially completed. Subsequently, on November 19, 1993, respondent served a second amended arbitration demand adding numerous claims and demanding $586,540 in damages. Petitioner responded by commencing this proceeding seeking a stay of arbitration on the grounds that respondent failed to comply with the requirements of Education Law § 3813 and various contractual conditions precedent to arbitration. Respondent cross-moved for leave to serve a late notice of claim.

Supreme Court stayed arbitration of a number of respondent's claims finding them barred by the Statute of Limitations or respondent's failure to comply with contractual conditions precedent to arbitration. As to the remaining claims, it permitted respondent to serve a late notice of claim. These cross appeals ensued.

Respondent initially argues that the petition was untimely as it was not filed within 20 days after the service of its December 14, 1992 demand as required by CPLR 7503 (c). We disagree since respondent's second amended demand subsumed its previous demands as it contained new claims and consolidated and modified previous demands as opposed to merely amending the amount of damages sought (see, Matter of Schneider [Newman], 88 A.D.2d 876; compare, Matter of Davis, Brody Wisniewski [Temple Emanu-El], 27 A.D.2d 842). Accordingly, since this proceeding was commenced within 20 days of the service of the second amended demand, it is timely.

The next issue we confront is whether, as a condition precedent to arbitration, respondent was required to submit its claims to petitioner's architect for his decision. Conditions precedent to arbitration are those provisions which are intended to be preliminary to the institution of an arbitration proceeding, the merits of which are to be determined by the courts (see, Matter of County of Rockland [Primiano Constr. Co.], 51 N.Y.2d 1, 9).

Inasmuch as the parties' contract contains explicit language evincing their intent that the decision of the architect is a condition precedent to arbitration, Supreme Court properly stayed arbitration of those claims which respondent did not submit to the architect for his decision (see, Matter of Board of Educ. v Hatzel Buehler, 156 A.D.2d 684, lv denied 76 N.Y.2d 703; New York Tel. Co. v Schumacher Forelle, 60 A.D.2d 151; compare, Shook of W. Virginia v York City Sewer Auth., 756 F. Supp. 848, 851-854; Matter of Town of Queensbury [Joseph R. Wunderlich, Inc.], 175 A.D.2d 946). We note that Matter of Spencer-Van Etten Cent. School Dist. (Auchinachie Sons) ( 179 A.D.2d 855, lv denied 79 N.Y.2d 759), relied upon by respondent, is distinguishable in that its holding relates to the issue of the timeliness of the submission of a claim to an architect rather than, as here, the failure to submit a claim.

The contract provides that "[a] decision by the Architect * * * shall be required as a condition precedent to arbitration or litigation of a Claim between the Contractor and Owner as to all such matters arising prior to the date final payment is due".

Education Law § 3813 (1) provides that no action or special proceeding may be maintained against a school district unless a written verified claim was presented to the school district within three months of the accrual of the claim. Where a claim was not timely served, a court, in its discretion, may extend the time to do so (see, Education Law § 3813 [2-a]). Such extension, however, cannot exceed the time limit for the commencement of an action, which in a breach of contract action is one year (see, Hall-Kimbrell Envtl. Servs. v East Ramapo Cent. School Dist., 177 A.D.2d 56, 59). Thus, the issue we must resolve is whether respondent is foreclosed from seeking relief under Education Law § 3813 (2-b) because its claims are time barred.

In actions involving construction contracts, a claim accrues at the time the contractor's damages become ascertainable (see, Matter of Board of Educ. [Wager Constr. Corp.], 37 N.Y.2d 283, 290; Castagna Son v Board of Educ. [New Dorp High School], 151 A.D.2d 392). It generally has been recognized that a contractor's damages are ascertainable once the work is substantially completed or a detailed invoice of the work has been submitted and not, as Supreme Court determined, when each discrete item of work was performed and completed (see, Eastern Envtl. Servs. v Brunswick Cent. School Dist., 188 A.D.2d 777; G.A. Contrs. v Board of Educ., 176 A.D.2d 856).

Here, the proof shows that the renovation work was substantially completed on January 8, 1993 and the work on the addition on August 30, 1993. Even if we accept the former date as the date of accrual, respondent was entitled to seek relief under Education Law § 3813 (2-b) because its cross motion pursuant thereto was made in November 1993 (compare, Matter of City School Dist. [Tougher Indus.], 173 A.D.2d 1051, 1053).

We agree that Supreme Court properly granted respondent's cross motion since the record, and particularly the January 28, 1993 extension agreement, demonstrate that petitioner was not unaware of respondent's claims; nor does it appear that petitioner will be penalized by the late filing (see, Matter of Prote Contr. Co. v Board of Educ., 198 A.D.2d 418, 421; compare, Matter of Jackson v Board of Educ., 194 A.D.2d 901, 904, lv denied 82 N.Y.2d 657).

In this agreement, petitioner agreed that "[c]urrent arbitration may be amended to include additional claims pre or post filing".

Cardona, P.J., Mercure and Peters, JJ., concur. Ordered that the order is modified, on the law, without costs, by deleting the second decretal paragraph thereof, and, as so modified, affirmed.


Summaries of

Matter of Board of Education of Schenevus

Appellate Division of the Supreme Court of New York, Third Department
Dec 29, 1994
210 A.D.2d 854 (N.Y. App. Div. 1994)
Case details for

Matter of Board of Education of Schenevus

Case Details

Full title:In the Matter of the Arbitration between BOARD OF EDUCATION OF THE SCHENEV…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Dec 29, 1994

Citations

210 A.D.2d 854 (N.Y. App. Div. 1994)
621 N.Y.S.2d 139

Citing Cases

White v. Freyman

The alternative relief sought, an application for leave to file a late notice of claim, must be denied. An…

Suburban Rest. Co. v. Wappingers C. S. Dist

Education Law § 3813 (1) requires a notice of claim to be served upon the governing body of a school district…