In a proceeding pursuant to Lien Law article 2, inter alia, to discharge a public improvement mechanic's lien undertaking and the surety, the petitioner appeals from an order of the Supreme Court, Suffolk County (Gerard, J.), dated April 30, 1998, which denied its motion for that relief.

Marshall M. Stern, Huntington Station, N.Y., for appellant.

Mokotoff Mondshine, Garden City, N.Y. (Milton M. Mokotoff of counsel), for respondent.

SONDRA MILLER, J.P., THOMAS R. SULLIVAN, DANIEL W. JOY, MYRIAM J. ALTMAN, JJ.


DECISION ORDER

ORDERED that the order is reversed, on the law, with costs, and the motion is granted.

Prior to the termination of the public improvement lien obtained by Italia Construction Company (hereinafter Italia), the petitioner Bat-Jac Contracting, Inc. (hereinafter Bat-Jac), obtained an undertaking "conditioned for the payment of any judgment which may be recovered in an action to enforce the lien" (Lien Law § 21; see, Russell Erwin Mfg. Co. v. City of New York, 118 App. Div. 88). "Upon the posting of the [undertaking], a `shifting' occurs and the lien detaches from its original adherence (appropriated funds or property) and attaches to the substitute, the bond" ( Tri-City Elec. Co. v. People, 96 A.D.2d 146, 150, affd 63 N.Y.2d 969).

Although the lien attached to the undertaking, the lien nevertheless was extinguished because, within six months from the filing of the lien, Italia did not commence an action to foreclose its lien, file a notice of pendency, or obtain an order extending the lien (Lien Law §§ 18 Lien, 21 Lien[2]; CLG, Inc. v. Bat-Jac Contr., 230 A.D.2d 701; Tri-City Elec. Co. v. People, supra; Matter of Syracuse Castings Sales Corp., 159 Misc.2d 61).

Payment of any judgment which may be rendered in Italia's action alleging a non-Lien Law cause of action to recover damages for work, labor, and services, was not bonded by the undertaking, which conditioned payment upon the recovery of a judgment in an action to enforce Italia's public improvement mechanic's lien ( see, Harley v. Plant, 210 N.Y. 405; Berger Mfg. Co. v. City of New York, 206 N.Y. 24; Audley Clarke Co. v. W.F. Plass Bro., 187 App. Div. 904). As a result, Bat-Jac's motion to discharge the undertaking and the surety should have been granted.


Summaries of

Matter of Bat-Jac Contract. v. Italia Const

Appellate Division of the Supreme Court of New York, Second Department
Jun 1, 1999
262 A.D.2d 314 (N.Y. App. Div. 1999)
Case details for

Matter of Bat-Jac Contract. v. Italia Const

Case Details

Full title:In the Matter of BAT-JAC CONTRACTING, INC., appellant, v. ITALIA…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Jun 1, 1999

Citations

262 A.D.2d 314 (N.Y. App. Div. 1999)
691 N.Y.S.2d 213

Citing Cases

D.A.G. Floors v. St. Paul Mercury Insurance Co.

A mechanic's lien filed on a public improvement contract may be discharged by execution of a bond or…

KBC Conc. Constr. Corp. v. Nat'l Envtl. Saf. Co.

That branch of the motion which is for summary judgment dismissing the fourth cause of action, which is to…