From Casetext: Smarter Legal Research

Marek v. City of Alpena

Supreme Court of Michigan
Jun 6, 1932
246 N.W. 171 (Mich. 1932)

Opinion

Docket No. 2, Calendar No. 36,022.

Submitted April 5, 1932.

Decided June 6, 1932. Submitted on rehearing October 13, 1932. Decided January 3, 1933.

Appeal from Alpena; Smith (Fred P.), J. Submitted April 5, 1932. (Docket No. 2, Calendar No. 36,022.) Decided June 6, 1932. Submitted on rehearing October 13, 1932. Decided January 3, 1933.

Case by Constantine Marek against the City of Alpena, a municipal corporation, for damages alleged to be due to negligent maintenance of a bridge. Directed verdict and judgment for defendant. Plaintiff appeals. Reversed, and new trial granted. Former opinion affirmed on rehearing.

Isadore Isackson, for plaintiff.

Carl R. Henry, for defendant.


(ON REHEARING.)


In our former opinion ( 258 Mich. 637) we reversed the judgment because the court erred in directing a verdict in favor of the defendant on the ground that there was no evidence of negligence on its part. We based our conclusion on evidence showing that there was a bump or sharp rise at the point where the approach connects with the floor of the bridge. The question on rehearing is whether there was any such evidence.

The record shows that John Nelson, an experienced bridge builder and former county commissioner of roads, testified as follows in response to a question as to how the bridge was built:

"Well, the bridge is built with a bump at both ends. * * *

" Q. Do you know the rise of that bump?

" A. Oh, I should judge three or four feet."

Samuel Tokoly, an engineer, testified that there was a rise of one and a half feet from the level of the old bridge floor to the level of the new bridge floor.

" Q. Can you tell the jury how that rise was attained in the construction of the bridge?

" A. I believe with timbers. * * * There were timbers laid on top of the old concrete floor. I can't tell you just the size of them. The main timbers of the present wooden structure were laid on top of the old bridge floor, which would make the floor of the wooden structure the thickness of that timber higher than the old concrete floor.

" The Court: So that do I understand then that right where the end of the wooden bridge rests on the old cement bridge the wooden bridge is a foot and a half higher than the floor of the old cement bridge?"

Counsel for the defendant contends that witnesses were referring to a grade in the approach and not to a sharp rise or bump where the approach connects with the floor of the bridge. Their testimony does not support his contention. We admit some confusion in the record as to the actual condition of the bridge, but, in deciding the question as to whether the court was right in directing a verdict for the defendant, we must construe the testimony most favorably to the plaintiff. We adhere to our former opinion.

The judgment is reversed, and a new trial granted, with costs to the plaintiff.

CLARK, POTTER, SHARPE, NORTH, FEAD, WIEST, and BUTZEL, JJ., concurred.


Summaries of

Marek v. City of Alpena

Supreme Court of Michigan
Jun 6, 1932
246 N.W. 171 (Mich. 1932)
Case details for

Marek v. City of Alpena

Case Details

Full title:MAREK v. CITY OF ALPENA

Court:Supreme Court of Michigan

Date published: Jun 6, 1932

Citations

246 N.W. 171 (Mich. 1932)
246 N.W. 171

Citing Cases

Marek v. City of Alpena

Decided June 6, 1932. Rehearing granted September 14, 1932. See 261 Mich. 154. Case by Constantine Marek…

Brown v. County of Oakland

"The rule that a driver must see objects and be able to stop within the range of his lights, applied to…