From Casetext: Smarter Legal Research

Lippert v. Lasar

Supreme Court of California
Jul 31, 1893
4 Cal. Unrep. 74 (Cal. 1893)

Opinion

          Commissioners’ decision. Department 2. Appeal from superior court, city and county of San Francisco; F. W. Lawler, Judge.

         Action by John Lippert against L. Lasar and others. From an order granting a new trial, plaintiff appeals. Affirmed.

         COUNSEL

          [4 Cal.Unrep. 75] D. E. Alexander and E. I. Robinson, for appellant.

          John T. Humphreys and E. D. Peixotto, for respondents.


          OPINION

          VANCLIEF, C.

          Action to enforce a lien upon a house owned by defendant Lasar, for labor done upon an addition to said house for the defendant Sonneckson, who, as original contractor, constructed said addition. The judgment was in favor of the plaintiff, but the court granted a new trial, and this appeal is from the order granting a new trial.

         Whether or not the plaintiff had filed his claim of lien within 30 days after the completion of the additional structure was the principal question at the trial, and is the only question presented on this appeal; it being admitted that the new trial was granted on the ground of insufficiency of the evidence to justify the finding that plaintiff’s claim of lien was filed within the time required by section 1187 of the Code of Civil Procedure, namely, within 30 days after the completion of the addition which the original contractor agreed to construct. The claim of lien was filed August 29, 1890, and I think a decided preponderance of the evidence is to the effect that the addition was completed on July 16, 1890. The addition to the house was a cellar under it. By the original contract, which was in writing, the defendant Sonneckson agreed to make the necessary excavation for the cellar, and to construct walls of concrete seven feet and six inches in height, and steps to the street, for $365. That all this work was done and accepted by the owner as completed on or before July 26, 1890, there is no controversy; but the evidence shows that the placing of a door frame in the cellar [4 Cal.Unrep. 76] door by a carpenter employed by the owner, and about an hour’s work by plaintiff, at request of the owner, in filling a small hole outside of the cellar, were done in August. The court, however, considered the lack of this additional work a trivial imperfection in the improvement, if imperfection it was, in the sense of section 1187 of the Code of Civil Procedure, and not such as would have prevented the filing of plaintiff’s lien within 30 days after July 26, 1890; and the evidence contained in the record seems to justify this conclusion. I think the order granting a new trial should be affirmed.

Code Civil Proc. § 1187, as amended in 1887, provides that any person, other than the original contractor, claiming a mechanic’s lien, must file his claim within 30 days after the completion of the building or improvement, and that any trivial imperfection in the work shall not be deemed such a lack of completion as to prevent the filing of the lien claim.

          We concur: SEARLS, C.; BELCHER, C.

          PER CURIAM.

          For the reasons given in the foregoing opinion the order granting a new trial is affirmed.


Summaries of

Lippert v. Lasar

Supreme Court of California
Jul 31, 1893
4 Cal. Unrep. 74 (Cal. 1893)
Case details for

Lippert v. Lasar

Case Details

Full title:LIPPERT v. LASAR et al.

Court:Supreme Court of California

Date published: Jul 31, 1893

Citations

4 Cal. Unrep. 74 (Cal. 1893)
4 Cal. Unrep. 74

Citing Cases

Sullivan v. Moorhead

The main contention of the appellant is that, because at the time the deed was executed the plaintiffs…

People v. Munroe

It is not like the case of a counterfeit bank bill, where a letter or a figure may be the only means of…