From Casetext: Smarter Legal Research

Leonard E. Riedl Constr., Inc. v. Homeyer

Supreme Court, Appellate Division, Fourth Department, New York.
Apr 26, 2013
105 A.D.3d 1391 (N.Y. App. Div. 2013)

Opinion

2013-04-26

LEONARD E. RIEDL CONSTRUCTION, INC., Plaintiff–Respondent, v. Michael HOMEYER and Clara Homeyer, Defendants–Appellants. (Appeal No. 1.)

Dirk J. Oudemool, Syracuse, for Defendants–Appellants. Goris & O'Sullivan, LLC, Cazenovia (Mark D. Goris of Counsel), for Plaintiff–Respondent.



Dirk J. Oudemool, Syracuse, for Defendants–Appellants. Goris & O'Sullivan, LLC, Cazenovia (Mark D. Goris of Counsel), for Plaintiff–Respondent.
PRESENT: SCUDDER, P.J., PERADOTTO, CARNI, LINDLEY, AND WHALEN, JJ.

MEMORANDUM:

Plaintiff commenced this action seeking damages for, inter alia, breach of contract based upon defendants' alleged failure to pay for work performed by plaintiff pursuant to a construction contract. In appeal No. 1, defendants appeal from an order and judgment entered after a nonjury trial that awarded plaintiff damages in the amount of $70,175.55, i.e., $54,466 in damages for the balance owed under the contract, and $15,709.55 in interest provided for in the contract. In appeal No. 2, defendants appeal from an order granting plaintiff's application for attorney's fees and costs incurred in obtaining the order and judgment in appeal No. 1.

Contrary to defendants' contention in appeal No. 1, the court's conclusion that plaintiff did not waive its right to payment is supported by a fair interpretation of the evidence ( see Farace v. State of New York, 266 A.D.2d 870, 870, 698 N.Y.S.2d 376;see generally Northern Westchester Professional Park Assoc. v. Town of Bedford, 60 N.Y.2d 492, 499, 470 N.Y.S.2d 350, 458 N.E.2d 809). “It is well settled that a general release is governed by principles of contract law ... and that, where a release is unambiguous, the intent of the parties must be ascertained from the plain language of the agreement” ( Dommer Constr. Corp. v. Savarino Constr. Servs. Corp., 85 A.D.3d 1617, 1617–1618, 925 N.Y.S.2d 305 [internal quotation marks omitted] ). “However, when the evidence in the record including, inter alia, the circumstances surrounding the release, as well as the parties' course of dealings, evinces that the parties' intentions were not reflected in the general terms of the release, the release does not conclusively establish a defense as a matter of law” ( Orangetown Home Improvements, LLC v. Kiernan, 84 A.D.3d 902, 903–904, 923 N.Y.S.2d 161;see Penava Mech. Corp. v. Afgo Mech. Servs., Inc., 71 A.D.3d 493, 495, 896 N.Y.S.2d 349). Thus, “ ‘[w]here a waiver form purports to acknowledge that no further payments are owed, but the parties' conduct indicates otherwise, the instrument will not be construed as a release’ ” ( E–J Elec. Installation Co. v. Brooklyn Historical Socy., 43 A.D.3d 642, 644, 841 N.Y.S.2d 294;see generally CNP Mech., Inc. v. Allied Bldrs., Inc., 84 A.D.3d 1748, 1749, 922 N.Y.S.2d 688).

Here, plaintiff's representative signed a document entitled “Contractor's Final Waiver and Affidavit,” which provided that the construction project was “fully completed”; “all bills for labor and/or materials furnished in connection with the construction of said buildings and work of improvement have been fully paid”; and plaintiff “waives any and all lien rights which he may have or may have had on account of or arising out of the construction of said buildings and work of improvement.” Nevertheless, the evidence at trial established that, at the time that document was signed, the work had not been completed and defendants had verbally agreed to make additional payments for the completion of additional work. The evidence at trial further established that defendants complied with that verbal agreement by making additional payments to plaintiff after plaintiff's representative had signed the purported waiver. The court thus properly concluded that the parties did not treat the document signed by plaintiff's representative as a final and complete waiver of any further claims by plaintiff ( see generally E–J Elec. Installation Co., 43 A.D.3d at 644, 841 N.Y.S.2d 294). Contrary to defendants' further contentions in appeal No. 1, the evidence at trial supports the court's award of damages and the court's conclusion that plaintiff is entitled to contractual interest on that portion of the unpaid balance that was not withheld by defendants pursuant to General Business Law § 756–a(2)(a)(i) ( see generally Farace, 266 A.D.2d at 870, 698 N.Y.S.2d 376).

With respect to appeal No. 2, the parties' contract provides that “[t]he prevailing party shall be entitled to all costs, including but not limited to reasonable attorney fees, related to any proceeding” to enforce the terms of the contract. Contrary to defendants' contention, plaintiff is entitled to attorney's fees under the contract because plaintiff herein “prevail[ed] on the central claims advanced, and receive[d] substantial relief in consequence thereof” ( Sykes v. RFD Third Ave. I Assoc., LLC, 39 A.D.3d 279, 279, 833 N.Y.S.2d 76).

It is hereby ORDERED that the order and judgment so appealed from is unanimously affirmed without costs.


Summaries of

Leonard E. Riedl Constr., Inc. v. Homeyer

Supreme Court, Appellate Division, Fourth Department, New York.
Apr 26, 2013
105 A.D.3d 1391 (N.Y. App. Div. 2013)
Case details for

Leonard E. Riedl Constr., Inc. v. Homeyer

Case Details

Full title:LEONARD E. RIEDL CONSTRUCTION, INC., Plaintiff–Respondent, v. Michael…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Apr 26, 2013

Citations

105 A.D.3d 1391 (N.Y. App. Div. 2013)
964 N.Y.S.2d 789
2013 N.Y. Slip Op. 2897

Citing Cases

United Airconditioning Corp. v. Axis Piping, Inc.

Specifically, Axis's papers in opposition to United's motion demonstrated that United made payments to Axis…

Patti Constr. Corp. v. 111-16 Atl. Ave. Realty Corp.

Here, the defendants presented proof, specifically the general release and the waiver, demonstrating their…