OPINION


Defendant WM Financial Services, Inc., has filed a motion to dismiss or in the alternative to strike portions of counts four and six of Plaintiffs' complaint. Count four alleges that Defendant violated a New Jersey Wage and Hour Law and requests, inter alia, statutory damages. Count six alleges that Defendant breached its implied contract with Plaintiff to obey this law and to provide Plaintiff with other, unspecified benefits. With respect to count four, the Court holds that Plaintiffs, as private parties, are not entitled to statutory damages, so the Court strike their complaint's request for such damages. With respect to count six, the Court holds that Defendants cannot be under a contractual obligation to fulfill a statutory duty. Also with respect to count six, the Court holds that Plaintiffs' remaining allegations of breach of contract are mere formulaic recitations and are thus insufficiently pled. The Court accordingly dismisses count six without prejudice. In summary, Defendant's motion is GRANTED.

I. FACTS AND PROCEEDINGS

This is an employment dispute. Named Plaintiffs Susan Hyman, Christine L. Bonardi, and Barry N. Sugar are former employees of Defendant WM Financial Services, Inc. (Compl. ¶¶ 1, 6, 7, 8.) Plaintiffs allege a number of employment claims against WM, two of which are relevant to this Motion.

Plaintiffs bring this suit as a class action. (Compl. ¶ 1.) However, the class nature of the suit is irrelevant to the disposition of this motion. The Court will not further discuss it.

First, Plaintiffs allege in count four that after their employment ended, WM failed to pay Plaintiffs all wages due in a timely fashion, in violation of N.J. Stat. Ann. 34:11-4.3. (Compl. ¶¶ 44-47.) Plaintiffs request several forms of relief for this alleged violation, including compensatory damages, restitution, and — importantly — "penalties" under N.J. Stat. Ann. § 34:11-4.10. (Compl. ¶¶ 44-47; Pl.'s Br. in Opp'n to Def.'s Mot.5-7.)

Under § 34:11-4.10, the Commissioner of Labor is authorized to seek certain administrative penalties for violations of, inter alia, § 34:11-4.3.

Second, Plaintiffs allege in count six that WM breached their employment contract. (Compl. ¶¶ 51-55.) Plaintiffs allege the existence of a contract implied by conduct, "including the promise of the defendant WMFS to pay plaintiffs . . . all amounts due to them in compliance with state and/or federal law." (Compl. ¶ 52.) Plaintiffs further allege that WM breached this contract by "failing to pay the plaintiffs . . . other benefits." (Compl. ¶ 55.)

WM now moves to dismiss or in the alternative to strike portions of counts four and six. With respect to count four, WM alleges that "penalties" under § 34.11-4.10 are not available to private plaintiffs. (Mem. of Law in Supp. of Def.'s Mot. to Dismiss 4-6.) With respect to count six, WM alleges that promises to comply with the law are not enforceable in contract actions and that Plaintiffs' complaint fails to identify any other breach. (Def.'s Mot. 7-9.)

II. DISCUSSION

A. Count Four

Bell Atl. Corp. v. Twombly 127 S. Ct. 19551964-65Id.

As stated above, WM moves to dismiss or strike portions of count four, Plaintiffs' § 34:11-4.3 claim. (Def.'s Mot. 4-6.) WM argues that Plaintiffs' requested damages for this count, penalties under § 34.11-4.10, are not available to private plaintiffs. (Def.'s Mot. 4-6.) The Court agrees that Plaintiffs may not recover such penalties. Accordingly, the Court strikes Plaintiffs' request for penalties from count four of the complaint, although the Count finds that dismissal of that count is not warranted.

Penalties under § 34:11-4.10 are not available to private plaintiffs. That section provides "when the Commissioner of Labor finds that an employer has violated [certain New Jersey employment laws, including § 34:11-4.3], the commissioner is authorized to assess and collect administrative penalties." This section evidences the New Jersey legislature's intent to vest the Commissioner of Labor with the power to seek administrative penalties. It does not expressly provide a private right of action to seek such fees. While New Jersey courts have not addressed whether § 34:11-4.10 implies a private right of action, see Shelter Sys. of N.J., Inc. v. Fair, 2006 WL 2192904, at *4 n. 5 (N.J.Sup.Ct. App. Div. July 18, 2006) ("For purposes of this appeal, we need not resolve whether [§ 34:11-4.10] does or does not imply a private right of action."), they have generally declined to infer a private right of action in statutes where the statutory scheme contains civil penalties. R.J. Gaydos Ins. Agency, Inc. v. Nat'l Consumer Ins. Co., 773 A.2d 1132, 1144 (N.J. 2001). Furthermore, a new cause of action in New Jersey should generally be created only by legislative enactment or by the New Jersey Supreme Court.Proske v. St. Barnabas Med. Ctr., 712 A.2d 1207, 1210 (N.J.Super.Ct. App. Div. 1998). Accordingly, the Court declines to hold that Plaintiffs may seek administrative penalties under § 34:11-4.10.

As a remedy, the Court strikes the portion of count four in which Plaintiffs request administrative fees. Under Federal Rule of Civil Procedure 12(f), "[t]he court may strike from a pleading . . . any redundant, immaterial, impertinent, or scandalous matter." Rule 12(f) allows this Court to strike portions of a complaint in which a plaintiff requests relief to which she is not entitled as a matter of law. See Sirota v. Welbilt Appliance, Inc., 840 F. Supp. 11, 14 (E.D.N.Y. 1994) (striking a portion of a complaint requesting compensation for pain and suffering where such damages were unavailable); Hofmayer v. Dean Witter Co., 459 F. Supp. 733, 740 (N.D. Cal. 1978) (striking a claim for punitive damages in a contract claim where state law did not permit such damages). Because Plaintiffs cannot recover administrative fees under § 34:11-4.10, as explained above, the Court strikes from the complaint their request for such fees.

However, the mere fact that Plaintiffs request unavailable administrative penalties in count four does not justify dismissal of that count. A demand for relief is not part of a plaintiff's claim, so a failure to specify relief to which the plaintiff is entitled generally does not warrant dismissal of that claim.Bontkowski v. Smith, 305 F.3d 757, 762 (7th Cir. 2002); see Fed.R.Civ.P. 54(c) (stating that a final judgment "should grant the relief to which each party is entitled, even if the party has not demanded that relief in its pleadings"). Plaintiffs may be entitled to some other kind of relief if they succeed on this claim. Indeed, Plaintiffs here request an array of remedies, including compensatory damages and restitution. Accordingly, dismissal of count four would be inappropriate.

B. Count Six

WM also moves to dismiss or strike portions of count six, Plaintiffs' contract claim. WM argues that this claim is based solely on its alleged violation of New Jersey statutes and not on any real contractual agreement. (Def.'s Mot. 7-9.) Plaintiffs answer that their contract claims stem not only from WM's violations of statutory duties but also from WM's failure to provide "other benefits." (Pl.'s Opp'n 8.) The Court finds that Plaintiffs' contract claims stem largely from alleged violations of New Jersey statutes and that such violations may not serve as the basis for a contract claim. The Court further finds that to the extent Plaintiffs' contract claims stem from obligations to provide "other benefits" independent of any statutory entitlement, they are insufficiently pled to give WM notice and an opportunity to answer them. Accordingly, the Court dismisses count six in its entirety without prejudice.

Plaintiffs' contract claims largely comprise violations of New Jersey statutory law and are thus not cognizable contract claims. Contractual agreements to comply with preexisting legal duties are unenforceable for lack of consideration. Berel Co. v. Sencit F/G McKinley Assocs., 710 F. Supp. 530, 536 (D.N.J. 1989); see Gray v. Martino, 103 A. 24, 24 (N.J. 1918). Here, Plaintiffs alleged an implied contract "to pay plaintiffs . . . all amounts due to them in compliance with state and/or federal law." (Compl. ¶ 52.) If WM was already obligated by state and federal law to pay these amounts, then WM's obligation to pay cannot arise out of any contract. Thus WM's failure to pay cannot serve as the basis for a breach contract claim.

Furthermore, to the extent that Plaintiffs' contract claims allege a violation of extra-statutory duties, they are insufficiently pled to give WM notice and an opportunity to defend against them. While a complaint need not set forth detailed factual allegations, it must provide a defendant with fair notice of the plaintiff's claim and the grounds upon which it rests. Phillips v. County of Allegheny, 515 F.3d 224, 231 (3d Cir. 2008). The complaint must set forth sufficient factual allegations to raise the right to relief above mere speculation.Id. at 231-32. Here, count six of Plaintiffs' complaint alleges that WM breached an implied employment contract "to pay the plaintiffs . . . other benefits." (Compl. ¶ 55.) Count six is thus little more than a recitation of the elements for a breach of contract claim. It does not discuss the terms of the contract or how WM has allegedly breached it. Indeed, Plaintiffs admit in their opposition to this motion that they are unable to "precisely determine the specific contractual obligations the Defendant owed to the Plaintiffs under their employment contracts." (Pl.'s Opp'n 8.) Plaintiffs' claim appears to be purely speculative — precisely what is now held insufficient under the federal pleading standards. Id. If Plaintiffs cannot set forth with some minimal specificity the nature of WM's contractual obligation and failure to abide thereby, WM cannot be expected to defend against Plaintiffs' allegations. See Data Gen. Corp. v. Computerized Indus., Inc., 573 F. Supp. 115, 116 (E.D. Pa. 1983) (holding that a contract claim was insufficiently pled because, inter alia, it failed to mention "the written or oral terms" of the contract). Thus count six is insufficiently pled.

Accordingly, the Court dismisses count six in its entirety without prejudice under Federal Rule of Civil Procedure 12(b)(6). If Plaintiffs become able to plead a contract claim with the minimal factual allegations necessary to satisfy the rules of pleading, then they may move to amend their complaint.

III. CONCLUSION

The Court strikes from the complaint paragraph forty-seven of count four, which reads as follows: "Therefore, plaintiffs, on behalf of themselves and members of the Class, demand appropriate penalties for defendants' failure to timely pay wages during the Class Period." The Court also dismisses count six in its entirety without prejudice. Accordingly, WM's motion is GRANTED. An Order accompanies this Opinion.


Summaries of

Hyman v. WM Financial Services

United States District Court, D. New Jersey
Apr 29, 2008
MASTER FILE: 07-CV-3497 (WJM) (D.N.J. Apr. 29, 2008)
Case details for

Hyman v. WM Financial Services

Case Details

Full title:SUSAN HYMAN, CHRISTINE L. BONARDI, BARRY N. SUGAR, individually and on…

Court:United States District Court, D. New Jersey

Date published: Apr 29, 2008

Citations

MASTER FILE: 07-CV-3497 (WJM) (D.N.J. Apr. 29, 2008)

Citing Cases

Shakib v. Back Bay Restaurant Group, Inc.

"Contractual agreements to comply with preexisting legal duties are unenforceable for lack of consideration."…

Merlo v. Federal Express Corporation

Therefore, "[c]ontractual agreements to comply with preexisting legal duties are unenforceable." Hyman v. WM…