Hurley v. Kincaid

U.S.
Feb 23, 1932
285 U.S. 95 (1932)

Summary

holding that governmental action was not unconstitutional because “the complainant can recover just compensation under the Tucker Act in an action at law ... [and t]he compensation which he may obtain in such a proceeding will be the same as that which he” is entitled to under the constitution

Summary of this case from City of Dallas v. Vsc Llc

Opinion

CERTIORARI TO THE CIRCUIT COURT OF APPEALS FOR THE FIFTH CIRCUIT.

No. 457.

Argued January 4, 5, 1932. Decided February 23, 1932.

1. An owner of land lying within the proposed channel of the Boeuf Floodway, part of the plan authorized by the Mississippi River Flood Control Act, brought suit to enjoin the carrying out of the work in the floodway and specifically to enjoin the receiving of bids for the construction of the guide-levees therefor, claiming that if the work should be commenced without proceedings first having been instituted to condemn his land or the flowage rights thereon, the United States would in effect be taking his property without due process of law and without just compensation. Complainant conceded that the Act was valid and that it authorized those charged with its execution to take his lands or an easement therein. Held, that injunction was not the proper remedy, for if what was done, or was contemplated, constituted a taking of the property, then under the Tucker Act there was a plain, adequate and complete remedy at law. P. 104. 2. The Fifth Amendment does not entitle the owner of lands taken for public use to be paid in advance of the taking. Id. 3. Where large public interests are concerned and the issuance of an injunction may seriously embarrass the accomplishment of important governmental ends, a court of equity acts with caution and only upon clear showing that its intervention is necessary in order to prevent an irreparable injury. P. 104, n. 49 F.2d 768, reversed.

CERTIORARI, 284 U.S. 610, to review a judgment of the Circuit Court of Appeals which affirmed a decree of the District Court enjoining petitioners from carrying out a project authorized by the Mississippi River Flood Control Act. The case is stated fully in the opinion.

Solicitor General Thacher, with whom Assistant Attorney General Richardson and Messrs. G.A. Iverson and Paul D. Miller were on the brief, for petitioners.

The only flowage rights which § 4 of the Act requires the United States to "provide" are those which the Secretary and the Chief of Engineers have determined to be necessary.

The first paragraph of § 4 has no general application to the respondent's land. It applies only where the plan contemplates the deliberate diversion, by eliminating or diminishing existing flood protection, of destructive flood waters over lands not previously subjected to like destructive flood waters.

Neither the findings of the District Court nor the evidence establish that § 4 is applicable to the respondent's land.

Assuming that § 4 requires the acquisition of flowage rights over the respondent's land, the statute does not require that such rights must be condemned or purchased prior to the construction of the proposed levees in the Boeuf Basin.

If petitioners are acting pursuant to a lawful statute, they can not be enjoined even if their acts would result in a taking. But nothing which the petitioners have done or propose to do constitutes a "taking." There must be "an actual invasion or appropriation of land as distinguished from consequential damage." Sanguinetti v. United States, 264 U.S. 146, 149.

The bill is not based upon actual or threatened impairment of the respondent's rights, but "upon assumed potential invasions." Arizona v. California, 283 U.S. 423, 462. Where there has been no actual appropriation or physical invasion, an injunction will not issue to interfere with the consummation of a public improvement.

If respondent is entitled to compensation, he is entitled to sue the United States upon an implied contract in the Court of Claims, or in the District Court under the Tucker Act. If the petitioners were not acting illegally, no cause of action against them as individuals existed, and the United States was an indispensable party to the suit.

Messrs. Wm. C. Dufour and Harry H. Russell, with whom Messrs. T.J. Freeman, John St. Paul, Jr., and G.L. Porterie were on the brief, for respondent.

The constitutional guaranty that property shall not be taken for public use without just compensation by agents of the State to whom this power is delegated, is deemed to establish a right of so high and sacred a character that any threatened infringement of the right should be restrained without consideration of the adequacy of the legal remedy. Lewis, Eminent Domain, § 632; Pomeroy, Equitable Remedies, § 465; McElroy v. Kansas City, 21 F. 261; Bass v. Metropolitan R. Co., 82 F. 857.

The respondent has no remedy against what in legal effect amounts to a taking of his property without just compensation, except by injunction. Pine v. Mayor, 103 F. 337, St. Louis S.F.R. Co. v. Tulsa, 213 F. 87; Ashland Elec. Power Co. v. Ashland, 217 F. 158; Toledo v. Toledo Rys. Light Co., 259 F. 450; Thornton v. Road Imp. Dist., 291 F. 518; Wilmington Ry. Co. v. Taylor, 198 F. 159.

Federal courts have the power to restrain unlawful, arbitrary, and unwarranted acts of federal officers.

There is no question of any claim resulting from the construction of levees as such. There is no denial of the right of the Government to construct standard levees or adequate levees at this or other points. The denial is of the right to construct what are known as guide levees — levees which will fix by design the Boeuf Diversion Channel, provided for in the adopted plan, and include respondent's land between the bounds of this designed channel. Waters from the main channel of the Mississippi will be designedly diverted through this diversion channel by what is termed a fuse-plug section, which automatically functions when the river reaches a certain stage. The purpose of this diversion channel is to protect other portions of the territory through which the Mississippi flows, and the territory outside of these guide levees. The suit is directed at the designed dedication of this and other property within these guide levees, to be flooded in the interest of the public at large.

The deprivation of its use, the elimination of its possibilities, the depreciation of its value resulting from being dedicated and enclosed in a basin to be designedly flooded, is the taking of his property. Ambler Realty Co. v. Euclid, 207 F. 312; Richards v. Washington Terminal Co., 233 U.S. 546; Peabody v. United States, 231 U.S. 541; Gibson v. United States, 166 U.S. 269; Bedford v. United States, 192 U.S. 217; Pennsylvania Coal Co. v. Mahon, 260 U.S. 393; United States v. Cress, 243 U.S. 316; Monongahela Nav. Co. v. United States, 148 U.S. 324, 326; United States v. Lynah, 188 U.S. 445.

The Act says that the United States shall provide flowage rights, if they are necessary to carry out the plan; and as some one had to be authorized to select places for these flowage rights, the Secretary of War and Chief of Engineers were designated; and in the present case they have selected the lands of respondent.

The fact that it may be years before this diversion channel is flooded and respondent's property absolutely destroyed has no bearing whatsoever upon respondent's right to protect himself in advance of a taking without compensation.

Immunity of the Government from suit does not extend to its officers when acting unlawfully. Philadelphia Co. v. Stimpson, 223 U.S. 605.


On June 15, 1929, Kincaid brought this suit in the federal court for western Louisiana against the United States, the Secretary of War, the Chief of Engineers, the Mississippi River Commission and its members, to enjoin the carrying out of any work in the Boeuf Floodway under the Mississippi River Flood Control Act, May 15, 1928, c. 569, 45 Stat. 534, and specifically to enjoin the receiving of bids and awarding of contracts for the construction of certain guide-levees bounding the Floodway.

The Mississippi River Flood Control Act adopted the Jadwin Plan for protection against floods. The Act provides for raising the levees generally three feet; for improving the carrying capacity of the main channel of the river by revetment work; and for limiting the flood-waters in this channel to its safe capacity through the provision of specified diversion channels. Among these is the Boeuf Floodway, which will carry excess flood-waters from a point below the mouth of the Arkansas through the Boeuf Basin West of the Mississippi into the backwater area at the mouth of the Red River. Such diversion has taken place to some extent in the past, when flood-waters have passed over, or through crevasses in, the twenty mile section of the levee at the head of the Basin, known as the Cypress Creek levee. Before this section was completed, in 1921, the Boeuf Basin and the parallel Tensas Basin, lying between it and the main channel, served as natural overflow areas of the Mississippi in flood periods. The Plan leaves the Cypress Creek section at its present height. But as the levees elsewhere are to be raised three feet and materially strengthened, preventing overflow at other points, the volume of water passing into the diversion channel may be greatly increased. Moreover, guide, or protection, levees running in a southerly direction are to be built on either side of the Floodway, which will direct the waters into a specified channel of a width varying from ten to twenty miles; and new levees are to be constructed which will cause this Floodway to carry waters formerly overflowing into the Tensas Basin. The maximum previous flow of water into the Boeuf Basin occurred in 1927, and is estimated at 450,000 cubic feet per second. Under the new Plan the flow may reach 1,250,000 feet per second in times of extraordinary flood. The War Department advertised for bids for the construction of guide-levees for the Boeuf Floodway, to be received June 17, 1929. To complete the project will probably require ten years.

Kincaid owns a 160-acre farm in the Boeuf Basin at a point 125 miles below the point of diversion. No part of the guide-levees is to be built on his land; but the land lies within the proposed channel of the Floodway. He alleges that the project will expose his property to additional destructive floods and thus subject it to a new servitude; that the mere "setting apart [of] this property as a flood way and diversion channel and . . . advertising for and receiving bids for . . . construction of the guide levees" casts a cloud upon his title; and that the Government is proposing to commence the work without having instituted condemnation proceedings. He charges that the acts of the defendants in advertising for bids for the construction of the guide-levees, to be followed by the letting of contracts, without having taken proceedings to condemn his land, "will mean the taking by the United States Government of complainant's lands and properties without due process of law and without just compensation."

The allegation is: "That the acts of the defendants in setting apart this property as a floodway and diversion channel and in advertising for and receiving bids for the doing of the proposed work, to wit, the construction of the guide levees and the contemplated acts Page 101 of the defendants in the awarding of contracts therefore [ sic], have already had the effect of casting a cloud upon the title of complainant to his said lands and properties and have materially affected his use and enjoyment of same and have materially affected and impaired the value thereof. That, [as] the result of setting apart this area as a floodway or diversion channel and the publication by defendants of said advertisements for bids for the construction of the guide levees, this property has not only deteriorated in value but complainant's title to same has been seriously clouded, his use of same has been seriously affected, and complainant would be unable to borrow money on said lands, sell or dispose of same, or interest persons in operating said lands for farms or for any other purposes, owing to the fact that the Government has indicated that it has taken possession or intends to take immediate possession of this property for a diversion channel or a floodway. That, as a result of making this area, in which complainant's lands and those of others are situated, a floodway or diversion channel, these lands will be rendered unfit for agricultural or any other purpose. That the title to complainant's lands is seriously clouded by said acts, and his ability to use said properties or obtain credit thereon is seriously affected, and, as stated above, this property is well worth the sum of $9,000.00."

All the defendants moved to dismiss the bill on the grounds, among others, that the United States had not consented to be sued, and that the bill disclosed no ground for equitable relief. The District Court held that the United States could not be made a party, since it had not consented to be sued; but overruled the motion to dismiss the suit, on the ground that the United States was not an indispensable party; that § 4 of the Act declares that "the United States shall provide flowage rights for additional destructive flood waters that will pass by reason of diversion from the main channel of the Mississippi River"; that, on the allegations of the bill, the creation of the Boeuf Floodway would subject Kincaid's land to additional destructive flood-waters; that the Act required the Government to condemn, or otherwise to acquire flowage rights over, the property before proceeding with the flood-control project in the Boeuf Basin; and that, by starting work before acquiring such rights, the defendants were proceeding in violation of both the Act and the Constitution. 35 F.2d 235.

The following are the provisions of the Act relevant to the payment of damages and of compensation for the taking of land.
"Sec. 3. . . . No liability of any kind shall attach to or rest upon the United States for any damage from or by floods or flood waters at any place: Provided, however, That if in carrying out the purposes of this Act it shall be found that upon any stretch of the banks of the Mississippi River it is impracticable to construct levees, either because such construction is not economically justified or because such construction would unreasonably restrict the flood channel, and lands in such stretch of the river are subjected to overflow and damage which are not now overflowed or damaged by reason of the construction of levees on the opposite banks of the river it shall be the duty of the Secretary of War and the Chief of Engineers to institute proceedings on behalf of the United States Government to acquire either the absolute ownership of the lands so subjected to over-flow and damage or floodage rights over such lands.
"Sec. 4. The United States shall provide flowage rights for additional destructive flood waters that will pass by reason of diversions from the main channel of the Mississippi River. . . ..
"The Secretary of War may cause proceedings to be instituted for the acquirement by condemnation of any lands, easements, or rights of way which, in the opinion of the Secretary of War and the Chief of Engineers, are needed in carrying out this project, the said proceedings to be instituted in the United States district court for the district in which the land, easement, or right of way is located. . . . The provisions of sections 5 and 6 of the River and Harbor Act of July 18, 1918, are hereby made applicable to the acquisition of lands, casements, or rights of way needed for works of flood control. . . .

Thereupon an answer was filed and the case was heard on evidence on final hearing. The defendants showed that, in the opinion of the Secretary of War and the Chief of Engineers, it was unnecessary to acquire any flowage rights over complainant's lands; insisted that these lands would be better protected under the Plan than heretofore; and claimed that § 4 of the Act was not applicable, because the Plan would not subject the property to "additional destructive flood waters." The District Court found on these issues against the Government; held that upon the evidence the Plan involved a taking of rights in respect to Kincaid's land; and that although the physical occupancy of it would not occur until the land had been overflowed in time of flood, "the process of subjecting it to that service and the taking possession in so far as is either necessary or contemplated by the act will begin with the construction of the first levee or works which are intended to direct the water upon the land." It enjoined the defendants, other than the United States, "from proceeding with the construction authorized by or carrying out the plan adopted by . . . the Mississippi River flood-control act in the Boeuf Basin flood way, . . . until the property of the said complainant has been acquired by the United States Government or the flowage rights over the same acquired either by purchase or condemnation for such purpose." 37 F.2d 602. The Circuit Court of Appeals affirmed the judgment of the District Court. 49 F.2d 768. This Court granted a writ of certiorari.

We have no occasion to determine any of the controverted issues of fact or any of the propositions of substantive law which have been argued. Kincaid concedes that the Act is valid and that it authorizes those entrusted with its execution to take his lands or an easement therein. We may assume that, as charged, the mere adoption by Congress of a plan of flood control which involves an intentional, additional, occasional flooding of complainant's land constitutes a taking of it — as soon as the Government begins to carry out the project authorized. Compare United States v. Lynah, 188 U.S. 445, 469; United States v. Cress, 243 U.S. 316, 328; Peabody v. United States, 231 U.S. 530, 538; Portsmouth Harbor Land Hotel Co. v. United States, 250 U.S. 1; 260 U.S. 327, 329. If that which has been done, or is contemplated, does constitute such a taking, the complainant can recover just compensation under the Tucker Act in an action at law as upon an implied contract, since the validity of the Act and the authority of the defendants are conceded. United States v. Great Falls Mfg. Co., 112 U.S. 645, 658; Great Falls Mfg. Co. v. Attorney General, 124 U.S. 581, 600; Tempel v. United States, 248 U.S. 121, 129; Marion Rye Valley Ry. Co. v. United States, 270 U.S. 280, 283. The compensation which he may obtain in such a proceeding will be the same as that which he might have been awarded had the defendants instituted the condemnation proceedings which it is contended the statute requires. Nor is it material to inquire now whether the statute does so require. For even if the defendants are acting illegally, under the Act, in threatening to proceed without first acquiring flowage rights over the complainant's lands, the illegality, on complainant's own contention, is confined to the failure to compensate him for the taking, and affords no basis for an injunction if such compensation may be procured in an action at law. The Fifth Amendment does not entitle him to be paid in advance of the taking. Crozier v. Krupp, 224 U.S. 290, 306. Compare Backus v. Fort Street Union Depot Co., 169 U.S. 557, 568; Bragg v. Weaver, 251 U.S. 57, 62; Joslin Mfg. Co. v. City of Providence, 262 U.S. 668, 677; Dohany v. Rogers, 281 U.S. 362, 366.

Even where the remedy at law is less clear and adequate, where large public interests are concerned and the issuance of an injunction may seriously embarrass the accomplishment of important governmental ends, a court of equity acts with caution and only upon clear showing that its intervention is necessary in order to prevent an irreparable injury. Compare Osborne v. Missouri Pacific Ry. Co., 147 U.S. 248, 258, 259; New York City v. Pine, 185 U.S. 93, 97. No such showing was made here.

See also Cherokee Nation v. Southern Kansas Ry. Co., 135 U.S. 641, 659; Sweet v. Rechel, 159 U.S. 380, 400, 407; Adirondack Ry. Co. v. New York, 176 U.S. 335, 349; Williams v. Parker, 188 U.S. 491, 502, 503; Manigault v. Springs, 199 U.S. 473, 485, 486; Hays v. Port of Seattle, 251 U.S. 233, 238.

As the complainant has a plain, adequate and complete remedy at law, the judgment is reversed with direction to dismiss the bill without prejudice.

Reversed.


Summaries of

Hurley v. Kincaid

U.S.
Feb 23, 1932
285 U.S. 95 (1932)

holding that governmental action was not unconstitutional because “the complainant can recover just compensation under the Tucker Act in an action at law ... [and t]he compensation which he may obtain in such a proceeding will be the same as that which he” is entitled to under the constitution

Summary of this case from City of Dallas v. Vsc Llc

holding that governmental action was not unconstitutional because "the complainant can recover just compensation under the Tucker Act in an action at law . . . [and t]he compensation which he may obtain in such a proceeding will be the same as that which he" is entitled to under the constitution

Summary of this case from City of Dallas v. VSC, LLC

rejecting a request to "enjoin the carrying out of any work" on a flood control project because the Tucker Act provided the plaintiff with "a plain, adequate, and complete remedy at law"

Summary of this case from Knick v. Township of Scott

In Hurley v. Kincaid, 285 U.S. 95, 104, 52 S.Ct. 267, 76 L.Ed. 637 (1932), the Court repeated that the "Fifth Amendment does not entitle [a property owner] to be paid in advance of the taking."

Summary of this case from Knick v. Township of Scott

In Hurley v. Kincaid, 285 U.S. 95, 52 S.Ct. 267, 76 L.Ed. 637, an owner of land within the proposed channel of the Boeuf Floodway, part of the plan now under consideration, brought suit to enjoin the carrying out of the work in the floodway without proceedings first having been instituted to condemn his land or the flowage rights thereon.

Summary of this case from Sponenbarger v. United States

In Hurley v. Kincaid, 285 U.S. 95, 52 S.Ct. 267, 76 L.Ed. 637, petitioner had obtained an injunction in the District Court restraining certain Government officials from proceeding further with the construction of a flood control project then being carried out under the Federal Flood Control Act, 33 U.S.C.A. § 702a et seq.

Summary of this case from Central Eureka Mining Company v. United States, (1956)

In Hurley v. Kincaid, 285 U.S. 95, 76 L.Ed. 637, 52 S.Ct. 267, the action was brought to enjoin the receiving of bids and awarding of contracts for the construction of certain guide levees bounding a floodway.

Summary of this case from Garrett v. Jones
Case details for

Hurley v. Kincaid

Case Details

Full title:HURLEY, SECRETARY OF WAR, v . KINCAID

Court:U.S.

Date published: Feb 23, 1932

Citations

285 U.S. 95 (1932)
52 S. Ct. 267

Citing Cases

Knick v. Township of Scott

They concerned requests for injunctive relief, and the availability of subsequent compensation meant that…

United States ex rel. Tennessee Valley Authority v. Lacy

48 Stat. 58(1933), as amended, 16 U.S.C.A. § 831 et seq. It is true that, accepting the facts alleged in the…