William J. Lohr, Columbus, Ohio (Robert Dow Hamilton, Columbus, Ohio, on the brief), for appellants.

Joe F. Asher, Columbus, Ohio (Vernon L. Stouffer, Calland, Stouffer Asher, Columbus, Ohio, on the brief), for appellee.

Before ALLEN, McALLISTER and STEWART, Circuit Judges.


Appellee furnished materials and labor to a subcontractor employed on a government project. The appellant was the prime contractor. The subcontractor went into receivership, and the appellee thereafter filed the present action under the Miller Act, 40 U.S.C.A. § 270b to recover the balance owing for labor and materials. This appeal is from the district court's judgment against the appellant general contractor for the amount owed appellee under its contract with the subcontractor.

Appellant contends (1) that the appellee failed to file his claim with appellant within ninety days after performing the last work under the contract, thus losing the right to recover under the statute, and (2) that the district court erred in refusing to admit evidence to show that the contract price exceeded the reasonable value of the materials furnished and services performed by the appellee.

Whether the appellee performed work under its subcontract within ninety days before it filed its claim was a question answered in the affirmative by a jury, upon a special interrogatory framed by the appellant. The jury's finding was supported by substantial evidence.

It was not error for the district court to exclude evidence of the actual value of the services performed and to enter judgment for the amount due under the contract, in the absence of any showing of fraud or collusion between the appellee and the subcontractor.

The judgment is affirmed.


Summaries of

Geis Construction Co. v. United States ex rel. Tom Igel Co.

United States Court of Appeals, Sixth Circuit
Apr 24, 1957
243 F.2d 568 (6th Cir. 1957)

affirming judgment for amount due under contract

Summary of this case from Taylor Construction Inc. v. ABT Service Corp. Inc.
Case details for

Geis Construction Co. v. United States ex rel. Tom Igel Co.

Case Details

Full title:The GEIS CONSTRUCTION CO., and United States Guarantee Company…

Court:United States Court of Appeals, Sixth Circuit

Date published: Apr 24, 1957

Citations

243 F.2d 568 (6th Cir. 1957)

Citing Cases

U.S. v. Greene Electrical Serv. of Long Island

We affirm the lower court's ruling for the amount "justly due" in the absence of any showing of fraud or…

United States v. Sovereign Construction Co.

Moreover, the court finds no merit to the defendants' assertion that the amount claimed does not represent…