From Casetext: Smarter Legal Research

G.A. Con. v. Bd. of Educ. of the City of N.Y

Appellate Division of the Supreme Court of New York, Second Department
Oct 21, 1991
176 A.D.2d 856 (N.Y. App. Div. 1991)

Opinion

October 21, 1991

Appeal from the Supreme Court, Kings County (Greenstein, J.).


Ordered that the order is reversed, without costs or disbursements, and the matter is remitted to the Supreme Court, Kings County, for an immediate trial pursuant to CPLR 3212 (c) to determine the date upon which the plaintiff's claim for extra work accrued and whether service of the notice of claim with respect thereto was timely under Education Law § 3813 (1).

The record reveals that the parties entered into a contract wherein the plaintiff agreed to perform certain construction work at a school building owned by the defendant Board of Education of the City of New York (hereinafter the Board). The plaintiff alleges that, at the Board's request, it also performed certain extra work which was outside the specifications of the contract, and that it is entitled to payment therefor. In a document bearing the date January 30, 1987, the Board indicated that no change order had been issued with respect to the extra work claimed by the plaintiff and that any such work had been unauthorized. The plaintiff thereafter sought, inter alia, payment for the extra work, by filing a notice of claim dated February 2, 1987, and subsequently commenced the instant action. The Board moved for partial summary judgment dismissing the claim for extra work, reasoning that the claim accrued in or before April 1986, and that the notice of claim had not been timely filed under Education Law § 3813 (1). The Supreme Court denied the motion, finding that the claim did not accrue until January 1987 when the Board indicated that it would not pay for the alleged extra work. We now reverse and remit the matter to the Supreme Court for an immediate trial to determine the date on which the plaintiff's claim accrued and whether the notice of claim in this case was timely filed.

The timely filing of a notice of claim is a condition precedent to the commencement of an action against the Board (see, Parochial Bus Sys. v. Board of Educ., 60 N.Y.2d 539; Public Improvements v. Board of Educ., 56 N.Y.2d 850). Pursuant to Education Law § 3813 (1), a notice of claim must be filed with the Board within three months after the accrual of the claim. It is well settled that in actions involving construction claims against the Board, the claim accrues and the three-month period commences running at the time the contractor's damages become ascertainable rather than on the date the Board refuses payment (see, Matter of Board of Educ. [Wager Constr. Corp.], 37 N.Y.2d 283; Amsterdam Wrecking Salvage Co. v. Greater Amsterdam School Dist., 83 A.D.2d 654, affd 56 N.Y.2d 828; Public Improvements v Board of Educ., 81 A.D.2d 537, affd 56 N.Y.2d 850, supra). While the date upon which a contractor's damages become ascertainable necessarily depends upon the particular facts of each case, it generally has been recognized that damages are ascertainable once the work is substantially completed or a detailed invoice of the work performed is submitted to the Board (see, e.g., Castagna Son v. Board of Educ., 151 A.D.2d 392; Philson Painting Co. v Board of Educ., 133 A.D.2d 619; Matter of Board of Educ. [Trombley Constr. Co.], 122 A.D.2d 421; Acme Skillman Constr. Co. v. Board of Educ., 106 A.D.2d 533; F G Heating Co. v. Board of Educ., 103 A.D.2d 791; Almar Constr. Corp. v. Hughes Sons, 58 A.D.2d 615; Central School Dist. No. 3 v. Kosoff Sons, 53 A.D.2d 1058).

In the instant case, the Board contends that the plaintiff's damages were ascertainable either on April 17, 1986, when the plaintiff's president wrote a letter to an employee of the Board indicating that "the job is 98% complete", or in September 1986 when the plaintiff submitted its payment application to the Board. However, the plaintiff contends that these documents referred only to the contract work and did not include the extra work for which the plaintiff seeks to recover. Inasmuch as these factual issues cannot be resolved on the record before us, we remit the matter to the Supreme Court for an immediate trial pursuant to CPLR 3212 (c) to determine the date upon which the plaintiff's damages became ascertainable and its claim accrued. In resolving this question, the court should accord due weight to any evidence regarding the point at which the extra work was substantially completed and/or a detailed bill for the extra work was submitted by the plaintiff to the Board. Upon fixing the date of accrual, the court should then determine whether the notice of claim was timely filed pursuant to Education Law § 3813.

The plaintiff's estoppel contention is improperly raised for the first time on appeal (see, Orellano v. Samples Tire Equip. Supply Corp., 110 A.D.2d 757). In any event, the facts of this case fail to support the application of estoppel (cf., D'Onofrio Bros. Constr. Corp. v. Board of Educ., 72 A.D.2d 760). Bracken, J.P., Sullivan, O'Brien and Ritter, JJ., concur.


Summaries of

G.A. Con. v. Bd. of Educ. of the City of N.Y

Appellate Division of the Supreme Court of New York, Second Department
Oct 21, 1991
176 A.D.2d 856 (N.Y. App. Div. 1991)
Case details for

G.A. Con. v. Bd. of Educ. of the City of N.Y

Case Details

Full title:G.A. CONTRACTORS, INC., Respondent, v. BOARD OF EDUCATION OF THE CITY OF…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 21, 1991

Citations

176 A.D.2d 856 (N.Y. App. Div. 1991)

Citing Cases

VOLMAR CONSTR. CORP. v. NYC SCH. CONSTR. AUTH.

Pursuant to Public Authorities Law § 1744(2), an action relating to the construction, reconstruction,…