In an action to impose a constructive trust on certain real property to the extent of $15,000, the defendant appeals from (1) an order of the Supreme Court, Westchester County (Lefkowitz, J.), dated June 12, 2000, which denied its motion pursuant to CPLR 3012(d) to compel acceptance of its late answer, and (2) a judgment of the same court, dated July 24, 2000, which is in favor of the plaintiff and against it imposing a constructive trust upon the subject real property to the extent of $15,000.

Alyse Walker Greenberg, Rye Brook, N.Y., for appellant.

Jeffrey I. Klein, White Plains, N.Y., for respondent.

Before: DAVID S. RITTER, J.P., MYRIAM J. ALTMAN, LEO F. McGINITY, NANCY E. SMITH, BARRY A. COZIER, JJ.


ORDERED that the appeal from the order is dismissed; and it is further,

ORDERED that the judgment is reversed, as a matter of discretion, the order is vacated, the motion is granted, and the matter is remitted to the Supreme Court, Westchester County, for further proceedings; and it is further,

ORDERED that the appellant is awarded one bill of costs.

The appeal from the intermediate order must be dismissed because the right of direct appeal therefrom terminated with the entry of judgment in the action (see, Matter of Aho, 39 N.Y.2d 241, 248). The issues raised on appeal from the order are brought up for review and have been considered on the appeal from the judgment (see, CPLR 5501[a][1]).

To prevail on its motion to compel acceptance of its late answer, the defendant was obligated to demonstrate a reasonable excuse for the delay (see, CPLR 3012[d]). Under the facts of this case, the excuse offered by the defendant was reasonable, and thus, the defendant's motion should have been granted.

RITTER, J.P., ALTMAN, McGINITY, SMITH and COZIER, JJ., concur.


Summaries of

Frank Mar Construction Corp. v. Precision Partners Realty Corp.

Appellate Division of the Supreme Court of New York, Second Department
Jun 25, 2001
284 A.D.2d 496 (N.Y. App. Div. 2001)
Case details for

Frank Mar Construction Corp. v. Precision Partners Realty Corp.

Case Details

Full title:FRANK MAR CONSTRUCTION CORPORATION, respondent, v. PRECISION PARTNERS…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Jun 25, 2001

Citations

284 A.D.2d 496 (N.Y. App. Div. 2001)
726 N.Y.S.2d 580

Citing Cases

Rockaway Blvd. Med. v. Travelers Prop. Cas. Corp.

Thereafter, defendant moved to compel plaintiff to accept the answer. In order to be entitled to the relief…

Jimenez v. N.Y. Cent. Mut. Fire Ins.

To prevail on its motion to compel acceptance of its late answer, the defendant is obligated to demonstrate a…