From Casetext: Smarter Legal Research

Evergrass, Inc. v. Lexington, No

Commonwealth of Massachusetts Superior Court. MIDDLESEX, SS
Jan 16, 2004
No. 03-1027 (Mass. Cmmw. Jan. 16, 2004)

Opinion

No. 03-1027.

January 16, 2004.


MEMORANDUM OF DECISION AND ORDER ON DEFENDANT GELLER SPORT, INC.'S MOTION FOR SUMMARY JUDGMENT AND RELATED MOTIONS


INTRODUCTION

This action arises from the Town of Lexington's rejection of the plaintiffs' bid for a public construction contract. Before the Court is the summary judgment motion of defendant Geller Sport, Inc., the architect for the project, along with related motions to strike and for sanctions. For the reasons that will be explained, the motion for summary judgment will be allowed.

BACKGROUND

The record before the Court establishes the following factual and procedural background, considered in the light most favorable to the plaintiffs. In May of 2002, the voters of the Town of Lexington approved funding for a project to renovate three outdoor athletic fields, known as the Lincoln Park Athletic Fields. The Town engaged defendant Geller Sport, Inc. ("Geller") to provide landscape architectural services for the project. Geller designed the project to include synthetic turf, referred to as "Infilled Synthetic Turf System."

The facts recited derive from the parties' statements under Superior Court Rule 9A(b)(5), along with affidavits and appended exhibits referred to in those statements, as well as the pleadings and exhibits thereto. The Court notes that the plaintiff's responses to a number of the factual assertions in the defendant's Rule 9A(b)(5) statement assert the existence of a factual dispute but fail to identify any supporting evidentiary material. As to these responses, the Court deems the defendant's factual assertions admitted, pursuant to the Rule. Similarly, the plaintiffs' statement of additional facts asserts facts for which no evidentiary support is identified. The Court disregards those assertions. The Court also disregards factual assertions appearing in the plaintiffs' memoranda but not presented in the manner required by Rule 9A(b)(5), as well as argumentative and hyperbolic characterizations of the facts appearing in the plaintiffs' Rule 9A(b)(5) statement. See generally Dziamba v. Warner Stackpole, 56 Mass. App. Ct. 397, 398-399 (2002). The Court has, however, reviewed all evidentiary materials submitted, in an effort to determine whether any genuine dispute of material fact exists.

After the approval of the plan, opposition to the project arose within the Town. Geller assisted Town officials in responding to the objections raised. Town officials, while addressing the arguments of the opposition, moved to speed the project to conclusion. An e-mail communication from Geller's principal to a colleague, dated December 4, 2002, states "the drawings and specs hit the street yesterday with bids due back on January 2nd. . . . The Town really pushed us to get the drawings out and the bids back ASAP because there has been a recent groundswell to stop the project, despite the fact that it was approved by an override vote. I didn't anticipate putting this out to bid until the first week in January." A December 10, 2002, e-mail exchange discussed a delay in preparation of documents. Geller's principal commented, "Not your fault. The fault lies with me for poor coordination. Also for the town's exceralated (sic) schedule to get this thing out to bid before a group in town is able to derail the project by calling a special town meeting in an effort to overturn the override vote."

Geller's principal and certain Town officials appear to have adopted a personalized attitude toward the conflict; their e-mail communications include references to the members of opposition group, and to their arguments, in less than civil terms.

The opponents of the project focused their objections on the synthetic turf. They contended that synthetic turf would be less safe than grass, and more costly over the long term, due to the need for periodic replacement. Geller and Town officials discussed these questions by e-mail. Among the communications was this statement, in an e-mail dated December 15, 2002, from a town official to Geller's principal, referring to a conversation with one of the project opponents: "He claims that Field Turf [a manufacturer of synthetic turf] has said that after 10 years, the surface, including the infill, needs to be replaced." In a further message between the same two the next day, the town official inquired, "Did Field Turf actually say that their field would need to be replaced after 10 years?" Geller's principal responded "FT usually says they expect 12 to 15 years, but expect 10 in the worst case." After a special meeting on December 16, 2002, the Board of Selectmen decided to proceed with the project.

The plaintiffs seize on the phrase "their field," taking it out of the context of the exchange, and construe it to indicate that the defendants had decided in advance that the contract would go to an installer of Field Turf. The argument is disturbingly disingenuous. No reasonable jury, presented with the full exchange on the subject, could adopt that interpretation. In further support of this theory, the plaintiffs offer an affidavit of a Vice President of Evergrass, asserting that, at the bid opening, Lexington officials "looked surprised," and that Geller's principal "turned red as a beet and looked deeply surprised and embarrassed," and "would not speak with" or congratulate the affiant. Even if the affiant's interpretation of others' demeanor were to be admitted in evidence, it would not support the plaintiffs' contention. Evergrass had existed for only sixteen months at the time; a reaction of surprise at its bid might well be expected, and would hardly suggest predetermination of the outcome.

Geller prepared specifications for the project. Part 1.05 of Section 02792 provided:

Infilled Synthetic Turf System installation shall be performed by an experienced specialty firm which shall have lain at least 10 outdoor athletic fields of 50,000 s.f. or greater of the type herein specified within the last 3-year period. The Contractor shall submit references, with contract (sic) name, address and telephone number to enable such data to be validated at the time of the submission of bids. It is noted that references will be contacted. Information received from references may be used as a basis for the rejection of a bid.

Apparently this word was meant to be "contact."

The bids were opened on January 2, 2002. The low bidder, at $2,541,857, was the plaintiff Emanouil Brothers, Inc., with the plaintiff Evergrass, Inc., as its sub-contractor for installation of the turf. Evergrass was founded in September of 2001. During the sixteen months of its existence, Evergrass had performed two installations of synthetic turf in outdoor fields, and one indoors. On March 1, 2002, James Street became employed with Evergrass. He had previously been employed with other turf installation companies, and in the course of his previous employment he had worked on a number of other turf installation projects, both indoor and outdoor.

In an answer to an interrogatory, Evergrass indicates that Street became a 5% equity owner of the company in March of 2003, after the initiation of this litigation.

Emanouil's bid included a form bearing the question "What project has your present organization completed of character similar to that proposed? Experience shall be in accordance with Part 1.05 in Section 02792 of the Technical Specifications." Evergrass listed 10 installation projects, nine outdoor and one indoor, and one indoor turf repair project. For each project, it gave a name of the project or of the owner, along with the city and state of the project, but no address, telephone number, or name of a contact person. Evergrass identified its role as subcontractor for one of the outdoor installation projects and as contractor for one outdoor and the one indoor installation project. As to the other seven installation projects and the repair project, the form indicated "* Installer." Lower on the page appeared the legend, "* Installation work done and supervised by James Street." Under the heading "Approximate Completion Date of Work," Evergrass listed dates ranging from May of 1999 until September of 2002. Four of the dates of installation projects, three outdoor and the one indoor, as well as the date of the indoor turf repair project, fell within the time during which Evergrass had existed; the other dates all were before that time. Eight of the dates were within the past three years; among these were the repair project and four of the projects identified as having been done by James Street. Thus, Evergrass's list of previous projects contained a total of two projects meeting the requirements of the specification — performed by Evergrass, in an outdoor field, within three years. The other nine projects listed all departed from the specifications in at least one respect. One was indoors, while the other eight were performed not by Evergrass, but by Street's former employers. Of those eight, four departed from the specifications in other respects as well; one was indoors and involved repair rather than installation, and three others were more than three years old.

The Town indicates that the form was not included in its bid documents or issued by the Town, but was apparently taken from a submission to another municipality.

Also included was a resume of James Street, showing that he had worked as an installer for a series of other employers until he became Director of Installations for Evergrass on March 1, 2002. The resume lists his projects for the previous employers, including the eight listed in connection with his name on the bid form.

Quirk Construction Co. was the second lowest bidder, at $2,627,200. Quirk listed as its installation subcontractor North East Turf Hue, Inc., a company founded in 1994, and a distributor for FieldTurf, Inc. Quirk's bid listed twenty-six previous projects of North East Turf Hue, Inc., seven identified as indoors, all with dates within three years. It provided a contact name and telephone number for each.

Quirk did not provide the square footage of the projects. Since it did provide full contact information, that question was susceptible of ready answer. Nothing in the record indicates that the previous projects did not in fact meet the square footage requirement.

Within an hour of the bid opening, Geller faxed a letter to Emanouil. The letter called attention to the requirements set forth at Part 1.05 of Section 02792 of the Technical Specifications, and stated: "The submitted turf manufacturer, Evergrass, lists only three (3) field installations. If Evergrass has failed to identify fields meeting the above criteria that have been installed by Evergrass in the past three years, please notify us immediately and provide us with installations and references." The next day, Emanouil's principal confirmed that Emanouil had no additional information regarding Evergrass's qualifications. Geller had no communication on the subject directly with Evergrass.

On January 3, 2002, the Lexington Town Manager sent Emanouil a letter announcing that "Since your bid did not include submittals from a qualified infilled synthetic turf vendor it has been deemed by the Town of Lexinton as non-reponsive and has been disqualified. Specifically, EverGrass can claim only three field installations where ten are required. . . . Although EverGrass lists additional installations performed by their installer while working for other companies, they not do qualify because they are not EverGrass fields." The letter also pointed out Evergrass's failure to list references with contact information. Accordingly, the letter announced, Lexington had awarded the project to Quirk.

Emanouil and Evergrass filed a protest with the Office of the Attorney General, by letter from their present counsel dated January 8, 2003. The letter asserted that the Town had disqualified their bid because "prior projects performed by Evergrass's predecessor business entity could not be included in the work experience," and because the bid did not list "references, with contract name, address and telephone number" of previous projects. The letter argued that the former ground was unlawful, and that the bid specifications had not required the missing information.

Both arguments find no support in the record, and the plaintiffs appear to have abandoned them. Nothing in the record suggests that any of Street's former employers was a "predecessor business entity" of Evergrass, or had any relationship with it. The specifications did require "references, with contract (sic) name, address and telephone number." The specifications did not explicitly state that references must be provided for each of the ten required projects, but that inference is plainly apparent from the requirement of ten, together with the advice that references would be contacted. Evergrass had not provided the required information for any of the listed projects. The protest letter was apparently inaccurate in another respect as well; it referred to Street as "an owner of Evergress," in contrast to the plaintiffs' interrogatory answer indicating that Street obtained his five percent equity interest in March of 2003, some weeks after the date of the letter.

Both the Town and Quirk submitted responses to the bid protest, by letters dated, respectively, February 4 and February 13, 2003, the latter by fax. In addition to arguing the merits of the issues raised, Quirk informed the Attorney General's Office that "As a practical matter, Quirk Construction received a Notice to Proceed, executed the general contract, committed substantial resources to mobilize for the job, and has completed roughly 10% of the contract work as of the date of this letter." The plaintiffs responded to that information by withdrawing their protest, by letter dated February 13, 2003. The plaintiffs' letter indicated that "our investigation has revealed substantial irregularities in the entire bid process which clearly warrants the type of investigation permissible under the discovery procedures of the Massachusetts Rules of Civil Procedure."

In the motion papers, the plaintiffs question the accuracy of this statement, again relying on distorted interpretations of e-mail communications. A communication dated January 7, 2003, from a Town official to Geller's principal, indicates that the Town's Appropriation Committee "would like to know how much would it cost the town to cancel the contract. They are looking at total damages." Geller responded, "I will get you the numbers by Thursday. Should the numbers assume that Quirk has been on site and has been doing work for a few weeks?" The plaintiffs construe this latter statement as indicating an effort to fabricate information about the progress of the project. No reasonable jury could construe it that way; in context, it is apparent that Geller was inquiring as to what assumption to make regarding the timing of termination in relation to work on the project, in projecting costs. The other communications plaintiffs cite — a message dated January 17, 2003, stating that a Town official "thinks we should have Quirk wait until Thursday the 23rd to put up the construction snow fence . . . but he can begin the erosion control now," another dated January 20, 2003, referring to tasks to occur "before the project starts," and another, dated Thursday, January 23, 2003, indicating that "we do not have anyone on site today," — convey no information as to the status of the project on February 13, 2003.

The Assistant Attorney General assigned to the matter expressed displeasure at this turn of events, in a letter to the Town dated February 25, 2003. He commented on the Town's awarding the contract during the pendency of the protest, and the work having begun, as follows: "Such a practice undermines the bid protest proceedings conducted by this Office and could be seen as evidence of bad faith, especially if repeated. If an awarding authority has reason to believe that it cannot await a bid protest decision from this Office, it should contact us immediately. Expedited proceedings will be arranged accordingly." The Assistant Attorney General did not cite any statutory or regulatory requirement that a municipality stay the award of a contract pending a bid protest proceeding, and counsel agreed at argument that no such requirement exists.

The plaintiffs filed this action on March 3, 2003, naming the Town and Geller as defendants. Count I, against the Town, captioned "Violation of c. 149, § 44A," alleges that the Town violated that statute by "failing to prepare bid specifications in a manner designed to ensure a level and fair playing field," "failing to ensure non-arbitrary and non-capricious practices in the review of received bids," "failing to conduct fair and non-arbitrary conduct in the selection of the bid winner," "engaging in arbitrary and capricious conduct in the comparative review of bidders," "disqualifying a responsible and eligible low bidder," "undermining and sabotaging the bid protest procedure by executing a contract with Quirk in a manner that was designed to defeat the bid protest and not further the lawful goals of the Awarding Authority, and by otherwise conspiring with Geller to defeat the level playing field of c. 149, § 44A et seq."

Count II, against Geller, captioned "Misrepresentation and Fraud Predicate Acts of C. 93A," alleges that "plaintiffs relied on the representations of Geller that Geller would conduct itself and its conduct in relation to the bid process in a manner that would [be] lawful, non-arbitrary and non-capricious, and in the spirit required by c. 149, § 44A," that "Geller failed to perform according to the law, and acted in a manner that was capricious, arbitrary, unfair, unlawful and otherwise contrary to the accepted standard of conduct in the industry," that Geller "conspired with the Awarding Authority to deny the Plaintiffs their lawful rights under c. 149, § 44A," and that "Geller's conduct defrauded the Plaintiffs of their contract, and was unfair and deceptive as a matter of law." The prayer for relief seeks declaratory and injunctive relief, lost profit, treble damages, and attorneys fees, without clearly delineating the form of relief sought against each defendant.

Geller has moved for summary judgment on the claim against it. The Town supports Geller's motion, but has not as of this date filed such a motion on its own behalf.

DISCUSSION 1. The Summary Judgment Motion.

This court grants summary judgment where there are no genuine issues of material fact, and the summary judgment record entitles the moving party to judgment as a matter of law. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Mass. R. Civ. P. 56(c). The moving party bears the burden of demonstrating that there is no genuine dispute of material fact on every relevant issue. Pederson v. Time, Inc., 404 Mass. 14, 17 (1989). A party moving for summary judgment who does not bear the burden of proof at trial may demonstrate the absence of a triable issue either by submitting affirmative evidence negating an essential element of the nonmoving party's case, or by showing that the nonmoving party has no reasonable expectation of proving an essential element of its case at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). Once the moving party establishes the absence of a triable issue, the party opposing the motion must respond with evidence of specific facts establishing the existence of a genuine dispute. Pederson v. Time, Inc., 404 Mass. at 17.

Under Mass. R. Civ. P. 56(f), a court will defer consideration "if the party opposing a summary judgment motion shows that it cannot, without further discovery, `present by affidavit facts essential to justify [its] opposition.'" Commonwealth v. Fall River Motor Sales, Inc., 409 Mass. 302, 307 (1991). A party relying on this rule must show that the discovery planned will address the issue raised in the summary judgment motion. "One common reason for the denial of a continuance in this context is the irrelevance of further discovery to the issue being adjudicated in summary judgment." Id. at 308. See generally, Herbert A. Sullivan, Inc. v. Utica Mut. Ins. Co. 439 Mass. 387, 400-401 (2003) (failure to file Rule 56(f) affidavit in response to summary judgment motion waives right to conduct further discovery prior to ruling on motion).

The ground of Geller's motion, in substance, is that the undisputed facts fail to establish any of the elements of a claim of fraud. More specifically, Geller points out that plaintiffs have failed to identify any false statement of fact made by Geller on which they relied to their detriment. See Zimmerman v. Kent, 31 Mass. App. Ct. 72, 77 (1991). The Court agrees.

The plaintiffs' initial response to the motion is to seek postponement of its consideration pending further discovery. In support of this effort, they offer the affidavit of their counsel, pursuant to M.R. Civ. P. 56(f), identifying anticipated discovery. The affidavit recites that plaintiffs "intend to depose each of the principals of the Defendants, as well as each of the individuals named in the e-mails and memoranda provided thus far," and that each "will be asked to explain the meaning of their written words." Counsel offers no suggestion as to what testimony he expects to elicit through such depositions, or how such testimony might assist in proving the elements of the claim pled in the complaint. In addition, counsel recites that plaintiffs "are going to provide expert witnesses as to public bidding and construction," and that such witnesses will testify to their opinions "that it is contrary to industry practice" for architects to engage in the various nefarious practices of which the plaintiffs accuse Geller, as well as "explain the intricacies of municipal law with relation to compliance with public bidding law and the open meeting law."

Counsel's affidavit falls well short of the requirement of Rule 56(f). A mere intention to take depositions, without anything to indicate that such depositions are likely to elicit evidence pertinent to the issues raised, is insufficient. Nor does an intention to hire expert witnesses have any bearing on the issues presented. The hiring of expert witnesses is not discovery, but is a matter entirely within a party's own control. If the plaintiffs believed that expert opinions would assist them in responding to the summary judgment motion, their proper course would have been to engage experts and submit affidavits. Nor do any of the expert opinions counsel expresses the intention to obtain have any bearing on the issues raised here; the claim pled against Geller is fraud, not departure from "industry practice."

Expert testimony to "explain the intricacies of municipal law with relation to compliance with public bidding law and the open meeting law" would be inadmissable, even if the complaint alleged a violation of such laws. Issues of law are for the Court, not for expert witnesses.

Plaintiffs' substantive response to the summary judgment motion consists largely of rhetoric and hyperbole. Plaintiffs accuse the defendants of engaging in "a fraudulent bidding process," "conspiring" . . . "to obstruct the Attorney General's review by falsifying documents for politically motivated reasons," "collusion," and "fabricating the start date of the contract work." Efforts to strip away the rhetoric, so as to identify the underlying claim, prove fruitless. The essence of the plaintiffs' fraud theory seems to be that the bid documents contained an implicit statement of intention to conduct a fair and open bid process, in compliance with applicable law, and that Geller did not have such intent. See generally, Celluci v. Sun Oil Co., 2 Mass. App. Ct. 722, 730 (1974) (regarding fraud based on false statement of present intention). The problem with this theory is that the record offers no evidence whatever to support it. To the contrary, the undisputed facts establish that Geller applied the specifications exactly as written, and that it disqualified the plaintiffs' bid because that bid did not meet the specifications.

The plaintiffs' memorandum emphasizes Street's extensive experience in turf installation. Street, however, was not the installation subcontractor listed in the bid. Evergrass was, and it indisputably did not have the qualifications required by the specifications. Even Street, as far as the record discloses, had not performed ten outdoor installations within the previous three years.

The plaintiffs repeatedly assert that Geller violated the public bidding laws, but they identify no provision of law that they claim was violated, and no violation appears in the record. The plaintiffs assert that Geller intended all along to select an installer of Field Turf, but they offer no evidence for that assertion. They also suggest that Geller drafted the specifications so as to limit qualified bidders to installers of Field Turf. Here again, evidence is utterly lacking; that Evergrass did not meet the qualifications gives no indication of how many others did, or whether distributors of Field Turf were somehow disproportionately represented among those who did.

See note 3, supra. The Court does not assume that it would have been unlawful for Geller to have specified a particular brand of turf; that question is not presented.

The plaintiffs rely on Nota Construction Corporation v. Keyes Associates, Inc., 45 Mass. App. Ct. 15 (1998). There, as here, the plaintiff subcontractor claimed misrepresentation by the defendant architect in bid specifications. The similarity ends there. In Nota, the alleged misrepresentation was the statement that "the contractor should anticipate some 12,000 cubic yards of ledge when [the architect] had information in its possession which demonstrated the presence of at least 24,000 cubic yards of ledge." Id. at 16. This allegation, the Court held, sufficed to state a claim of deceit. The contrast between that allegation and the claim asserted here could hardly be more stark; the plaintiff there identified with precision a statement of fact, on a matter clearly material to the bids, while the plaintiffs here rely on an amorphous theory, unrelated to any specific statement of fact, for which they offer no evidence. Nota does not assist this claim, but merely illustrates the type of specific allegations these plaintiffs have failed to make.

The plaintiffs also cite TLT Construction Corp. v. Anthony Tappe Associates, 48 Mass. App. Ct. 1 (1999). The Court fails to see any relevance of that decision to this case.

The plaintiffs devote substantial emphasis to Geller's role in what they term the "political" dispute within the Town. There may be room for argument about the propriety of Geller's advocacy, particularly the tone of some of its e-mail comments. But Geller's conduct in advocating for synthetic turf, against those who opposed it, had no adverse effect on these plaintiffs, who sought a contract to install synthetic turf. Had the opponents of the project prevailed, no contract would have been available for any synthetic turf installer.

The plaintiffs also emphasize the defendants' conduct in awarding the contract, and proceeding with the work immediately, despite the pending bid protest. This too is beside the point. The Town clearly was in a rush to proceed before further opposition could mount. The rush might be viewed as unseemly, but it was not fraudulent or unlawful, and it had no effect on these plaintiffs. The plaintiffs' bid indisputably did not conform; no amount of time spent in bid protest proceedings could have changed that fact, or affected the outcome. See Cataldo Ambulance Serv. v. City of Chelsea, 426 Mass. 383, 388-389 (1998). The plaintiffs have failed to identify any evidence of fraud, or of any other conduct in violation of G.L.c. 93A. Accordingly, defendant Geller is entitled to judgment as a matter of law.

2. The Motions to Strike and for Sanctions.

Both sides have filed motions to strike and for sanctions. The plaintiffs have moved to strike portions of Geller's Rule 9A(b)(5) statement, and for sanctions and costs. Geller's Rule 9A(b)(5) statement complies with that rule; it presents assertions of fact, supported by accurate references to admissible evidence. No ground exists to strike it, or for sanctions against Geller. Geller moves to strike portions of the plaintiffs' Rule 9A(b)(5) statement, as well as its two affidavits. As noted supra, the plaintiffs' Rule 9A(b)(5) statement departs from the requirement of the rule in significant respects. The remedy is not to strike the statement, but to deem admitted those facts not properly contested, and to disregard factual assertions not properly presented with supporting record references. That is what the Court has done. See note 1, supra.

Geller moves to strike the affidavit of plaintiffs' counsel pursuant to M.R. Civ. P. 56(f). The affidavit is proper in form, but its content is insufficient to make the showing required by that rule. The Court has considered the affidavit, and will not strike it, but rejects the request to defer consideration of the summary judgment motion. Geller also moves to strike paragraphs 6, 7, and 8 of the affidavit of Michael Volcano as not based on personal knowledge. The point is well taken; these paragraphs contain the affiant's subjective impressions of the demeanor of others, and his theories as to their thinking and motivation. This is not competent evidence, and must be stricken.

Geller also moves for sanctions, pursuant to M.R. Civ. P. 11, on that ground that the plaintiffs' submissions "blatantly misrepresent the record." Have carefully reviewed all of the material submitted, the Court is of the view that the record presents serious ground to question the good faith of the plaintiffs and their counsel. Particularly disturbing is the plaintiffs' misuse of various comments plucked out of context from e-mail communications, in a manner that distorts the meaning that clearly emerges when those messages are read in their entirety. The Court is mindful, however, of the subjective standard for Rule 11 sanctions established in Van Christo Advertising, Inc. v. M/A-COM/LCS, 426 Mass. 410, 422 (1998). In light of that standard, and in the exercise of discretion, the Court declines to impose sanctions at this time.

CONCLUSION AND ORDER

For the reasons stated, the Motion of Defendant, Geller Sport, Inc., for Summary Judgment is ALLOWED. The Plaintiffs' Cross Motion to Strike Improper Portions of the Rule 9A(b)(5) Statement and Cross Motion for Sanctions and Costs are DENIED. Geller Sport, Inc.'s Motion to Strike Portions of Affidavits of Michael Volcano and Robert Meltzer and Portions of Plaintiffs' Response to Rule 9A(b)(5) Statement of Material Facts is ALLOWED with respect to the Volcano affidavit, and otherwise DENIED. Plaintiffs' Cross-Motion to Strike Geller Sport, Inc.'s Motion to Strike Portions of Affidavits of Michael Volcano and Robert Meltzer and Portions of Plaintiffs' Response to Rule 9A(b)(5) statement of material facts, and Plaintiffs' Request for Sanctions and Costs Pursuant to Mass. R. Civ. P. 11 are DENIED.


Summaries of

Evergrass, Inc. v. Lexington, No

Commonwealth of Massachusetts Superior Court. MIDDLESEX, SS
Jan 16, 2004
No. 03-1027 (Mass. Cmmw. Jan. 16, 2004)
Case details for

Evergrass, Inc. v. Lexington, No

Case Details

Full title:Evergrass, Inc. and Emanouil Brothers, Inc. v. Town of Lexington and…

Court:Commonwealth of Massachusetts Superior Court. MIDDLESEX, SS

Date published: Jan 16, 2004

Citations

No. 03-1027 (Mass. Cmmw. Jan. 16, 2004)