Elliott v. Garringer

Court of Appeals of Ohio
Oct 28, 1927
161 N.E. 287 (Ohio Ct. App. 1927)

Opinion

Decided October 28, 1927.

Contracts — Breach for failure to build house for agreed price — Delivery not refused, where delivery of deed offered when grantee named — Grantor entitled to judgment on note for equity in property.

1. Where defendants agreed to build house for $7,300, but failed to build house for price agreed on, and total charges against property as result were about $10,000, defendants breached contract.

2. Where vendor had advised one of purchasers that deed for which note sued on was given would be delivered as soon as she was advised as to whom transfer should be made, vendor did not refuse to deliver deed.

3. Where defendants breached contract with plaintiff to build house for $7,300, and as result charges against property amounted to about $10,000, and defendant gave plaintiff note for $900 for her equity in property, and plaintiff was willing to deliver deed as soon as she was advised as to whom transfer should be made, plaintiff was entitled to judgment on note.

ERROR: Court of Appeals for Cuyahoga county.

Mr. H.E. Elliott, for plaintiffs in error.

Messrs. Mooney, Hahn, Loeser Keough, for defendant in error.


Frieda H. Garringer brought an action against Elliott and McCleod on a cognovit note for $900, with interest at 7 per cent. from December 22, 1924. The defendants, by answer, admitted the signing of the note, and pleaded that they did not deliver or receive any consideration for it. The answer further states that prior to the date of said note the defendants offered plaintiff said note for a certain piece of real estate owned by her, located on Melgrave avenue in the city of Cleveland; that said note was given to her for the purpose of inspection and submission of same to her husband for approval, and with the intent that if he approved the same she should keep it and deliver a deed they had prepared for said property; that she held said note and deed for about three weeks, without either delivering or offering to deliver the deed; and that then the defendants notified her of their withdrawal of said offer and demanded the return of the note.

The allegations of the answer were denied by the reply.

At the trial a verdict was returned for plaintiff for the full amount. Judgment was entered on that verdict, and this action is prosecuted to reverse that judgment.

Plaintiff, Frieda Garringer, owned an unimproved lot on Melgrave avenue. January 14, 1924, the Home Estate Construction Company entered into a written contract with Roy and Frieda Garringer to build a house on said lot for them for the sum of $7,300, and to complete it within three months; allowance to be made for weather conditions.

Plaintiff borrowed money to pay for the work as it progressed. She gave two mortgages on the property, one for $5,700, and the other for $2,000. Subsequently, material liens were filed against the property in the sum of $2,000. Other claims were presented. The total charges against the property, by reason of the failure of the Home Estate Construction Company to build the house for the price agreed upon, were about or a little more than $10,000.

The deed referred to in the answer of the defendants was either blank, or partially blank. No grantee was named, nor was the name of any grantee furnished to plaintiff.

It is not important to recite the details of the negotiations that were had by the parties. The Home Estate Construction Company at the time of entering into this contract was not a corporation, but was owned and managed by the defendants and other persons, and in so far as it failed to construct the house for the price agreed upon it breached its contract. The plaintiff, by the negotiations carried on between her and the defendants, sought to save her equity in the property. As a result of the negotiations, on December 22, 1924, the defendants signed said note and the plaintiff has had it in her possession from and since that date.

The defendants' claim that the deed was not delivered, or that no offer was made to deliver the same, is not tenable.

January 27, 1925, plaintiff advised Elliott, who was one of the parties, that the deed would be delivered as soon as she was advised as to whom the transfer should be made. The plaintiff did not therefore refuse to deliver the deed.

The defendants, through the said construction company, breached the contract to construct the house for $7,300. The result of the negotiations between the parties was the giving of the note in question.

Our conclusion is that the judgment of the court of common pleas should be, and it hereby is, affirmed.

Judgment affirmed.

HAMILTON, P.J., and MILLS, J., concur.

Judges of the First Appellate District, sitting in place of Judges SULLIVAN, VICKERY and LEVINE, of the Eighth Appellate District.


Summaries of

Elliott v. Garringer

Court of Appeals of Ohio
Oct 28, 1927
161 N.E. 287 (Ohio Ct. App. 1927)
Case details for

Elliott v. Garringer

Case Details

Full title:ELLIOTT ET AL. v. GARRINGER

Court:Court of Appeals of Ohio

Date published: Oct 28, 1927

Citations

161 N.E. 287 (Ohio Ct. App. 1927)
161 N.E. 287

Citing Cases

Corp. of Pres. of L.D.S. v. Hartford Acc. Ind. Co.

But the Surety, by denying liability and walking off, not because it then claimed that there was no default…