From Casetext: Smarter Legal Research

Davidge v. Velie

County Court, Ulster County
May 1, 1916
95 Misc. 511 (N.Y. Cnty. Ct. 1916)

Opinion

May, 1916.

Alexander Johnston (V.B. Van Wagonen, of counsel), for appellant.

A.D. A.W. Lent, for respondent.


On October 6, 1914, a paper, of which the following is a copy, was signed by one of the defendants and delivered to the plaintiff:

"Hudson Carbon Co.,

"Order ______, Date ____________, 191_

Oct. 6, 1914,

"Ship to Velie Bros. "At P.O. Marlboro, N.Y. "How ship, Cedarcliff, N.Y. When, Mch. 1st. "Terms, Net cash fob, Cedarcliff, N.Y. "Salesman _________________ Buyer _________________ If needed earlier will advise.

"20 bags, 1 ton

Davidge's Special Phosphorus, $40.00

"Velie Bros. "Less freight."

On February 12, 1915, the plaintiff delivered this fertilizer to the Delaware and Hudson Railroad Company at Ballston Spa, for shipment, and in due course it arrived at Cedarcliff, before February twenty-second, when the defendants wrote the plaintiff that they had just received word of the shipment of February twelfth, of one ton Davidge's Special Phosphorus and that they had on February eighteenth written asking them to cancel the order for March first. That they gave this order with the understanding that they could so do, and that they would not take it from the freight house.

The plaintiff sued to recover the purchase price. The defendants claimed nonperformance by delivery before the time fixed in the order; and that the writing above set forth did not contain the entire agreement. Upon the trial the defendants' offer of proof that it was agreed that the order for March delivery could be cancelled by defendants any time before March 1st was rejected upon the ground that the writing contained a complete contract and parol evidence was not admissible to modify its terms. I think this was error. The contract was not complete on its face. There was no acceptance of the order in the writing, nothing to bind the plaintiff so as to make a complete executory contract. It was an offer, and, to make a complete contract, an acceptance by act or promise by the plaintiff was necessary. The writing might have been shown to be part only of an entire verbal contract. If this instrument can be said to contain a contract, this case falls in the second class of exceptions set forth in the opinion in Thomas v. Scutt, 127 N.Y. 133, to the rule that a complete written contract cannot be modified or contradicted by parol evidence. Judge Vann says: "The second class embraces those cases which recognize the written instrument as existing and valid, but regard it as incomplete either obviously, or at least possibly, and admit parol evidence, not to contradict or vary, but to complete the entire agreement of which the writing was only a part. * * * Two things, however, are essential to bring a case within this class: I. The writing must not appear upon inspection to be a complete contract, embracing all the particulars necessary to make a perfect agreement and designed to express the whole arrangement between the parties, for in such a case it is conclusively presumed to embrace the entire contract.

"2. The parol contract must be consistent with and not contradictory to the written instrument."

The written instrument here is nothing more than an offer by the defendants to purchase fertilizer, fixing price, quality, quantity, time and place of delivery. No acceptance binding the plaintiff can be found within the four corners of the paper. It may be that soliciting the order and manual acceptance of the paper would warrant the inference of its acceptance, but that must be shown by evidence outside the paper. I think the defendants should have been allowed their proof showing an entire executory contract of an order for goods to be delivered March first, with a right to cancel before the date of delivery.

Regarding the instrument as an offer, where is the acceptance necessary to make a complete contract? Was the shipment of February twelfth such an acceptance? I think not, because the act did not square with the offer. The offer was for a shipment on March first, and that is not complied with by a shipment February twelfth. Corrigan v. Sheffield, 10 Hun, 227.

Again, if the instrument was only an offer, the defendants had a right to withdraw it before acceptance by the plaintiff. This they did by notifying the plaintiff a reasonable time before March first.

For these reasons the judgment is reversed, with costs.

Judgment reversed, with costs.


Summaries of

Davidge v. Velie

County Court, Ulster County
May 1, 1916
95 Misc. 511 (N.Y. Cnty. Ct. 1916)
Case details for

Davidge v. Velie

Case Details

Full title:WILLIAM M. DAVIDGE, Doing Business as HUDSON CARBON COMPANY, Respondent, v…

Court:County Court, Ulster County

Date published: May 1, 1916

Citations

95 Misc. 511 (N.Y. Cnty. Ct. 1916)
160 N.Y.S. 820

Citing Cases

Quinn v. Quinn

A writing which does not vest, pass, nor extinguish any right, either by contract, operation of law, or…