Chung-Li Chou v. Main Street Associates

Appellate Division of the Supreme Court of New York, Second Department
Oct 17, 1994
208 A.D.2d 670 (N.Y. App. Div. 1994)

Opinion

October 17, 1994

Appeal from the Supreme Court, Queens County (Leviss, J.).


Ordered that the order is affirmed, with costs.

The plaintiffs entered into a contract pursuant to which the defendants agreed to construct a five family dwelling with a medical office. The contract provided that the deed would be delivered on or about September 30, 1988. The defendants did not obtain a certificate of occupancy until February 1992. During the period between September 1988 and February 1992, while the defendants were attempting to secure the certificate of occupancy, the plaintiffs reaffirmed their interest in completing performance, albeit with a price adjustment. The defendants insisted upon performance at the contract price and scheduled a closing for July 16, 1992, declaring that "time is of the essence". Thereafter, the plaintiffs commenced this action alleging that the defendants breached the contract of sale by failing to complete the building and deliver the deed within a reasonable time after September 30, 1988, and by making substantial alterations in the building plans without the consent of the plaintiffs. The plaintiffs demanded a judgment rescinding the contract and recovering the payments that they had already made. The defendants moved to dismiss upon the ground that the complaint did not state a cause of action under CPLR 3211 (a) (7). The Supreme Court granted the motion and we affirm.

It is well settled that a party's failure to perform by the closing date specified in the contract does not constitute a material breach unless the other party has effectively declared time to be of the essence (see, Wilkinson v. Hoelscher, 163 A.D.2d 819; Jones Realty Corp. v. Frick, 144 A.D.2d 451). In this case, the plaintiffs never declared time to be of the essence (see, Tucek v. Hoffman, 161 A.D.2d 588; Stargiotti v. Nigrello, 114 A.D.2d 498). Moreover, notwithstanding the delay, the plaintiffs twice, in the intervening period, indicated that they still sought performance. Therefore, they cannot now repudiate the contract by citing the defendants' alleged breach (see, Jones Realty Corp. v Frick, supra). Furthermore, since the contract provided that the defendants reserved the right to determine the design of the building, the plaintiffs do not have a claim for breach of contract based on the ground that defendants made unauthorized alterations in the building.

We have reviewed the plaintiffs' remaining contentions and find them to be without merit. Miller, J.P., Joy, Altman and Goldstein, JJ., concur.


Summaries of

Chung-Li Chou v. Main Street Associates

Appellate Division of the Supreme Court of New York, Second Department
Oct 17, 1994
208 A.D.2d 670 (N.Y. App. Div. 1994)
Case details for

Chung-Li Chou v. Main Street Associates

Case Details

Full title:CHUNG-LI CHOU et al., Appellants, v. MAIN STREET ASSOCIATES et al.…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 17, 1994

Citations

208 A.D.2d 670 (N.Y. App. Div. 1994)
617 N.Y.S.2d 313

Citing Cases

Luo v. Main Street Associates

Ordered that the order is reversed insofar as appealed from, on the law, with costs, the defendants' motion…

Singh v. Carrington

The plaintiff admits that she caused the funds that were being held in escrow to be released to her. "Delay…