From Casetext: Smarter Legal Research

Chapman-Stein Co. v. Lippincott Glass Co.

Court of Appeals of Indiana
Apr 27, 1928
161 N.E. 645 (Ind. Ct. App. 1928)

Opinion

No. 12,980.

Filed April 27, 1928.

MECHANICS' LIENS — Right to Lien — Completion of Work. — A contractor for the construction and installation of four tanks in a plant for the manufacture of glass, could not, after the apparent completion of said tanks and their acceptance and use by the owner and the rendition of a bill by the contractor for the amount due for the completed job, and after the time for filing a mechanic's lien had expired, by placing a few bricks in the portholes of the last two of such tanks constructed, without the knowledge or consent of the owner or his representative, create a right to a lien for the amount due under the contract.

From Madison Superior Court; Lawrence V. Mays, Judge.

The Chapman-Stein Company filed an intervening petition in the receivership of the Lippincott Glass Company, asserting a claim against the latter company and its receivers for work of constructing four large tanks as a part of the company's glass plant and asking the foreclosure of a lien therefor. From an allowance of the claim as a general claim only and refusing claimant's right to a lien, it appeals. Affirmed. By the court in banc.

Henry C. Devin, Dee R. Jones and Diven, Diven Campbell, for appellant.

Bagot, Free Pence, for appellees.


Appeal from a judgment rendered by the superior court of Madison county, December 31, 1926, upon the intervening petition of appellant filed in the receivership proceedings of appellee, Lippincott Glass Company, in which appellant asserted a claim against said appellee and its receivers for $8,865, and that it had a valid mechanic's lien upon the real estate belonging to the company which it was entitled to have foreclosed. The court found that appellant was entitled to the allowance of its claim as a general claim only, and found against appellant in so far as the mechanic's lien was concerned, and rendered judgment accordingly.

The error assigned is the court's action in overruling appellant's motion for a new trial, under which appellant presents only the insufficiency of the evidence to sustain the decision of the court.

Appellee's summary of the evidence is unchallenged by appellant. It is substantially as follows: Appellant constructed, installed and fully completed in the factory of appellee company at Alexandria, Indiana, four recuperative day tanks pursuant to a contract therefor between said parties of February 12, 1926, the first of said tanks being completed on April 2, the next one very shortly thereafter, and the last two on June 25, 1926. Each and all of said tanks were fully completed. delivered and accepted by the company as fully completed, and the company was instructed by appellant to fire said furnaces and tanks, which it did and used two of them in the manufacture of glass until receivers were appointed for it on July 21, 1927.

Invoices were rendered by appellant for said tanks, and $735 had been paid thereon when the receivers were appointed. Appellant rendered invoices to the receivers therefor, and on September 12, 1927, filed with said receivers a sworn statement of its account, with invoices attached thereto, showing the last and final payment of $3,200 on said furnaces to be due and payable August 4, 1926.

In no statement, verbal or written, did appellant even suggest that any more material was required or work done to complete said furnaces, until in the early part of October, 1926, and long after its right to acquire a lien by notice of its intention so to do had expired, when appellant shipped to itself, by express, to Alexandria, sixteen fused alumina bricks or blocks. The receivers refused to accept the same, and in a few days thereafter, when the receivers and their manager in charge of the factory were absent, one of appellant's employees procured said sixteen bricks or blocks to be brought to the factory. After cutting down the size of such brick until two of them would fit therein, said employee loosely laid two of said bricks in the bottom of the two portholes of each of the last two of said tanks constructed, leaving the remaining eight of said bricks at the factory, and then left. Following this, on October 20, 1926, appellant recorded a notice of its intention to hold a mechanic's lien upon the factory and property of the glass company for such tanks, and the labor and material furnished in the construction thereof.

Appellee contends that the transaction of appellant with said sixteen bricks, under the evidence, was no part of the work of completing such tanks, that such tanks had been completed months before, and that the same was solely for the purpose of colorably giving appellant the right to assert a mechanic's lien long after the time its right to assert or give notice of its intention to hold such lien had expired. The court by its general findings has sustained appellee's contention. Under such circumstances, appellant did not acquire a lien. § 9833 Burns 1926; Sulzer-Vogt Machine Co. v. Rushville Water Co. (1902), 160 Ind. 202, 65 N.E. 583.

Affirmed.


Summaries of

Chapman-Stein Co. v. Lippincott Glass Co.

Court of Appeals of Indiana
Apr 27, 1928
161 N.E. 645 (Ind. Ct. App. 1928)
Case details for

Chapman-Stein Co. v. Lippincott Glass Co.

Case Details

Full title:CHAPMAN-STEIN COMPANY v. LIPPINCOTT GLASS COMPANY ET AL

Court:Court of Appeals of Indiana

Date published: Apr 27, 1928

Citations

161 N.E. 645 (Ind. Ct. App. 1928)
161 N.E. 645

Citing Cases

Lost Acres LLC v. Bank of Wolcott (In re Lost Acres LLC)

I.C. 32-28-3-3. That time period cannot be extended by performing repairs or work incidental to the contract.…

Riggins v. Sadowsky

However, depending upon the particular circumstances of various cases, the Court of Appeals has permitted the…