Appeal from Supreme Court, Kings County (Feinberg, J.),


Ordered that the orders are affirmed, with one bill of costs.

On January 2, 1991, the plaintiff Shaban Canka was seriously injured when he fell from a wooden plank laying across an opening between the second and third floor levels of a stairwell shaft. At the time of the accident, the injured plaintiff was employed by the third-party defendant 786 Iron Works Corp. (hereinafter the appellant), a subcontractor engaged in the installation of new stairs in a five-story building owned by the defendant Coalition for the Homeless, Inc. (hereinafter Coalition). Although the defendant B J General Contractors, Inc. (hereinafter B J was the general contractor for the renovation project, B J subcontracted performance of the construction work to the defendant Cosa Development Corp. (hereinafter Cosa Development).

Contrary to the appellant's contention, the Supreme Court properly granted the plaintiffs' motion for summary judgment on the issue of liability against the owner of the premises, Coalition, the general contractor, B J, and the subcontractor, Cosa Development. Here, the plaintiffs submitted evidence establishing that the injured plaintiff fell three stories through an open stairwell which was not protected by "sound planking * * * laid across the opening at levels not more than two stories above and not more than one story below" as required by Labor Law § 241-a ( see, Fuller v. Catalfamo, 223 A.D.2d 850; Santos v. Sure Iron Works, 166 A.D.2d 571). In addition, the plaintiffs demonstrated their entitlement to summary judgment pursuant to Labor Law § 240 (1) through uncontroverted evidence that the injured plaintiff was provided with no safety devices to prevent or break his fall ( see, Schneider v. Hanover E. Estates, 237 A.D.2d 274; Dawson v. Pauarini Constr. Co., 228 A.D.2d 466; Whalen v. Sciame Constr. Co., 198 A.D.2d 501).

Furthermore, the Supreme Court properly awarded summary judgment to Coalition and B J on their indemnification claims asserted against the appellant. It is well settled that an owner or general contractor held vicariously liable under the Labor Law is entitled to full common-law indemnification from an actively negligent subcontractor provided that the owner or general contractor did not direct, control, or supervise the subcontractor's work ( see, Kelly v. Diesel Constr. Div., 35 N.Y.2d 1, 6-7; Dawson v. Pavarini Constr. Co., supra; Lopez v. 36-2nd J Corp., 211 A.D.2d 667). Since Coalition has been found liable to the plaintiffs based solely upon its ownership of the premises, and there has been no showing that it supervised or controlled the renovation work being performed by the subcontractors and the injured plaintiff, it is entitled to common-law indemnification from the appellant ( see, Eccleston v. Berakha, 233 A.D.2d 417; Dawson v. Pavarini Constr. Co., supra). Similarly, the record does not support the appellant's claim that B J, which subcontracted performance of the construction work to Costa, directed or controlled the work performed by its subcontractors and the injured plaintiff at the renovation site. Accordingly, B J is also entitled to commonlaw indemnification from the appellant ( see, Lopez v. 36-2nd J Corp., supra; Richardson v. Matarese, 206 A.D.2d 354).

Although not raised as an issue on this appeal, to the extent that the recent amendment to the Workers' Compensation Law, limiting the right of third parties to sue an employer for contribution or indemnification based upon liability for injuries sustained by the employee within the scope of his or her employment, might otherwise be applicable to the facts of this case, we note that the amendment is not to be applied retroactively to third-party actions pending on the effective date of the amendment ( see, Workers' Compensation Law § 11, as amended by L 1996, ch 635, § 2; Morales v. Gross, 230 A.D.2d 7).

Finally, we reject the appellant's claim that the Supreme Court improvidently exercised its discretion in permitting the plaintiffs to file a note of issue and denying its belated request to conduct a second deposition of a representative of Cosa Development on matters related to its defense of the second third-party action ( see, Defina v. Brooklyn Union Gas Co., 217 A.D.2d 681; Colicchio v. City of New York, 181 A.D.2d 528).

Bracken, J.P., O'Brien, Krausman and Goldstein, JJ., concur.


Summaries of

Canka v. Coalition for the Homeless, Inc.

Appellate Division of the Supreme Court of New York, Second Department
Jun 2, 1997
240 A.D.2d 355 (N.Y. App. Div. 1997)
Case details for

Canka v. Coalition for the Homeless, Inc.

Case Details

Full title:SHABAN CANKA et al., Respondents, v. COALITION FOR THE HOMELESS, INC.…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Jun 2, 1997

Citations

240 A.D.2d 355 (N.Y. App. Div. 1997)
657 N.Y.S.2d 779

Citing Cases

Martinez v. Colasanto Constr., Inc.

Finally, pursuant to Article 14 of the contract, Spencer agreed that its Project Super, Mr. Wild, would be…

ZHONG v. FATE REALTY

In opposition, New Trend failed to raise any triable issues of fact concerning the movant's negligence, the…