The plaintiffs sought, by way of summary process, to regain possession of certain premises from the defendant. The trial court rendered judgment for the plaintiffs, from which the defendant appealed to this court. Thereafter, the trial court granted the plaintiffs' motion for an order of use and occupancy payments and ordered the defendant to pay monthly use and occupancy in the amount of $1000 beginning November 1, 2010, and the defendant filed an amended appeal with this court. Subsequently the plaintiffs filed motions to dismiss the appeal and the amended appeal. With respect to the amended appeal, because the sole remedy for seeking review of an order of use and occupancy is through a motion for review under the applicable rule of practice (§ 66-6), the defendant's amended appeal was dismissed. With respect to the original appeal filed by the defendant, the failure of an occupant of a dwelling unit in a summary process action to provide a bond for use and occupancy during the pendency of the appeal as required by statute (§ 47a-35a [a]) makes the appeal voidable upon attack and furnishes a sufficient ground for dismissal of the appeal, and the defendant's failure to comply with the use and occupancy payments in January, 2011, was a failure to comply with the bond requirement of § 47a-35a (a), thereby warranting a dismissal of his appeal.

Argued January 31, 2011

Officially released April 12, 2011

Procedural History

Summary process action, brought to the Superior Court in the judicial district of Fairfield, Housing Session, and tried to the court, Moore, J.; judgment for the plaintiffs, from which the defendant appealed to this court; thereafter, the court, Moore, J., granted the plaintiffs' motion for an order of use and occupancy payments, and the defendant filed an amended appeal to this court; subsequently, this court granted the plaintiffs' motions to dismiss the appeals. Appeals dismissed.

Richard Fenyes, pro se, the appellant (defendant).

Douglas R. Brown, pro se, the appellee (named plaintiff). Joseph W. Auger, for the appellee (plaintiff James Sheridan, trustee).


Opinion


The defendant, Richard Fenyes, appeals from the judgment of possession rendered in this summary process action in favor of the plaintiffs, Douglas R. Brown, administrator of the estate of Edmond Fenyes, and James Sheridan, trustee of the Mary Fenyes living trust. After reviewing the briefs, underlying record and pending motions, the court concludes that it lacks jurisdiction to consider this appeal and accordingly dismisses it.

"Summary process is a special statutory procedure designed to provide an expeditious remedy. . . . Summary process statutes secure a prompt hearing and final determination. . . . Therefore, the statutes relating to summary process must be narrowly construed and strictly followed." (Internal quotation marks omitted.) St. Paul's Flax Hill Co-operative v. Johnson, 124 Conn. App. 728, 733, 6 A.3d 1168 (2010), cert. denied, 300 Conn. 906, A.3d (2011).

The plaintiffs brought this action against the defendant, alleging that he no longer had any right or privilege to occupy the premises at 607 Booth Hill Road, Trumbull. After trial, the court rendered judgment of possession in favor of the plaintiffs. The defendant filed a timely appeal. During the pendency of the appeal, the plaintiffs filed a motion under General Statutes § 47a-35a seeking an order of use and occupancy payments. On October 26, 2010, after a hearing, the court ordered the defendant to pay monthly use and occupancy in the amount $1000 beginning November 1, 2010. Thereafter, the defendant filed an amended appeal from the use and occupancy order and made the ordered payments in November and December. At the time of oral argument before this court, the defendant had not paid use and occupancy for the month of January, 2011. Prior to oral argument, the plaintiffs filed motions to dismiss the appeal and the amended appeal, and the defendant timely objected.

General Statutes § 47a-35a (a) provides in relevant part: "When any appeal is taken by the defendant occupying a dwelling unit as defined in section 47a-1 in an action of summary process, he shall, within the period allowed for taking such appeal, give a bond with surety to the adverse party to guarantee payment for all rents that may accrue during the pendency of such appeal, or, where no lease had existed, for the reasonable value for such use and occupancy that may so accrue; provided the court shall upon motion by the defendant and after hearing thereon order the defendant to deposit with the court payments for the reasonable fair rental value of the use and occupancy of the premises during the pendency of such appeal accruing from the date of such order. . . ."

As to the motion to dismiss the defendant's amended appeal, the court turns to its decision in Scagnelli v. Donovan, 88 Conn. App. 840, 871 A.2d 1084 (2005), for guidance. In that case, this court stated that the sole remedy for seeking review of an order of use and occupancy is through a motion for review under Practice Book § 66-6. Id., 841-42. On the basis of this precedent, we dismiss the defendant's amended appeal.

The defendant did file a motion for review of the court's order for use and occupancy payments. A panel of this court granted the motion for review but denied the relief requested. The defendant then filed a motion for reargument to the panel and the court, en banc; this motion was denied.

We now turn to the original appeal filed by the defendant. Section 47a-35a (a) requires a defendant occupying a dwelling unit in a summary process action to give a bond for use and occupancy during the pendency of the appeal. In Young v. Young, 249 Conn. 482, 497, 733 A.2d 835 (1999), the Supreme Court stated that "[f]ailure to comply with the bond requirement makes the appeal voidable upon attack. . . . Therefore, the failure to provide such a bond furnishes a sufficient ground for dismissal of the appeal." (Citation omitted; internal quotation marks omitted.) The defendant's failure to comply with the use and occupancy payments in January, 2011, is a failure to comply with the bond requirement of § 47a-35a (a).

The plaintiffs' motions to dismiss are granted.


Summaries of

Brown v. Fenyes

Appellate Court of Connecticut
Apr 12, 2011
15 A.3d 1160 (Conn. App. Ct. 2011)
Case details for

Brown v. Fenyes

Case Details

Full title:DOUGLAS R. BROWN, ADMINISTRATOR (ESTATE OF EDMOND FENYES), ET AL. v…

Court:Appellate Court of Connecticut

Date published: Apr 12, 2011

Citations

15 A.3d 1160 (Conn. App. Ct. 2011)
15 A.3d 1160

Citing Cases

City of Norwich v. Shelby–Posello

(Emphasis added.) Scagnelli v. Donovan, 88 Conn.App. 840, 843–44, 871 A.2d 1084 (2005). If a defendant in a…

Brown v. Fenyes

Decided July 13, 2011 The defendant's petition for certification for appeal from the Appellate Court, 127…