From Casetext: Smarter Legal Research

Barleo Homes, Inc. v. Tudomawr Corporation

Appellate Division of the Supreme Court of New York, Second Department
Apr 24, 1995
214 A.D.2d 694 (N.Y. App. Div. 1995)

Opinion

April 24, 1995

Appeal from the Supreme Court, Orange County (Fitzer, J.H.O.).


Ordered that the order is affirmed, with costs.

The plaintiff, a developer, contracted with the defendant for the paving of a road. The contract provided that the defendant was to use approximately 36,000 square feet of "Blacktop Cold Mix 3 1/2 [inches]". The contract further provided that the work was to be acceptable to the Town Inspector or the Superintendent of Highways of the Town of Woodbury (hereinafter the Town). The defendant installed the blacktop, which was inspected three times by the Superintendent of Highways and the Town Engineer, and it was acceptable to the Superintendent of Highways upon its completion. More than two years later, however, when the plaintiff sought to have the road dedicated, it was rejected for dedication by the Town, in part, because it did not meet the Town's specification that it be 3 1/2 inches thick after it was compacted. The plaintiff hired another paving company to complete the work on the road and now seeks to recover the cost incurred for that work from the defendant. The plaintiff contends, inter alia, that the contract should be interpreted to require that the road's thickness was to be measured after the road had been compacted and that the determination of the Superintendent of Highways was not binding on the parties. We reject these contentions.

"A court may not rewrite into a contract conditions the parties did not insert, or under the guise of construction, add or excise terms" (Marine Assocs. v New Suffolk Dev. Corp., 125 A.D.2d 649, 652). The plaintiff was not new to the business of paving roads and understood what was involved therein. Had the plaintiff wished to require that the thickness of the blacktop be measured after it had been compacted, it could have included such a term in the contract. However, it did not. We may not now rewrite the contract by adding such a term under the guise of contractual construction. Moreover, the testimony at trial was insufficient to establish that the parties had not intended to be bound by the approval of the road by the Superintendent of Highways. In any event, we note that the plaintiff failed to offer any admissible proof of its damages.

The plaintiff's remaining contentions are not preserved for appellate review, or they are without merit. Bracken, J.P., O'Brien, Santucci and Florio, JJ., concur.


Summaries of

Barleo Homes, Inc. v. Tudomawr Corporation

Appellate Division of the Supreme Court of New York, Second Department
Apr 24, 1995
214 A.D.2d 694 (N.Y. App. Div. 1995)
Case details for

Barleo Homes, Inc. v. Tudomawr Corporation

Case Details

Full title:BARLEO HOMES, INC., Appellant, v. TUDOMAWR CORPORATION, Respondent

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Apr 24, 1995

Citations

214 A.D.2d 694 (N.Y. App. Div. 1995)
625 N.Y.S.2d 599

Citing Cases

Sussman Sales Co. v. VWR Int'l, LLC

The Court cannot rewrite the Agreement where Plaintiff failed to negotiate for the requirements that it now…

Sephardic Senior Citizens Lodge v. Serure

Thus, since the condition of the lease was waived by SSCL, section 14 of the agreement could not revive this…