From Casetext: Smarter Legal Research

Arnell Constr. Corp. v. N.Y.C. Sch. Constr. Auth.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Aug 12, 2020
186 A.D.3d 540 (N.Y. App. Div. 2020)

Opinion

2018–11934 Index No. 717514/17

08-12-2020

ARNELL CONSTRUCTION CORPORATION, respondent, v. NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, appellant.

James E. Johnson, Corporation Counsel, New York, N.Y. (Scott Shorr and Janet L. Zaleon of counsel), for appellant. Forchelli Deegan Terrana LLP, Uniondale, N.Y. (David A. Loglisci and Joseph P. Asselta of counsel), for respondent.


James E. Johnson, Corporation Counsel, New York, N.Y. (Scott Shorr and Janet L. Zaleon of counsel), for appellant.

Forchelli Deegan Terrana LLP, Uniondale, N.Y. (David A. Loglisci and Joseph P. Asselta of counsel), for respondent.

JOHN M. LEVENTHAL, J.P., SHERI S. ROMAN, JEFFREY A. COHEN, ROBERT J. MILLER, JJ.

DECISION & ORDER

In an action to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Queens County (Kevin J. Kerrigan, J.), entered August 14, 2018. The order denied the defendant's motion pursuant to CPLR 3211(a) to dismiss the second cause of action and portions of the first cause of action.

ORDERED that the order is modified, on the law, by deleting the provision thereof denying that branch of the defendant's motion which was to dismiss so much of the first cause of action as was predicated on extra work claims totaling $129,338.27, and substituting therefor a provision granting that branch of the motion; as so modified, the order is affirmed, without costs or disbursements.

The plaintiff was the successful bidder on a project to perform renovation work for the defendant in an existing building and to construct a new building at a school site. The plaintiff commenced this action to recover damages for breach of contract. The first cause of action sought payment for, inter alia, extra work that the plaintiff allegedly performed, and the second cause of action sought delay damages. The defendant moved pursuant to CPLR 3211(a) to dismiss portions of the first cause of action and the entire second cause of action. In an order entered August 14, 2018, the Supreme Court denied the motion. The defendant appeals.

A party is entitled to dismissal pursuant to CPLR 3211(a)(1) on the ground that a defense is founded on documentary evidence "only where the documentary evidence utterly refutes [the] plaintiff's factual allegations, conclusively establishing a defense as a matter of law" ( Goshen v. Mutual Life Ins. Co. of N.Y., 98 N.Y.2d 314, 326, 746 N.Y.S.2d 858, 774 N.E.2d 1190 ; see S & J Serv. Ctr., Inc. v. Commerce Commercial Group, Inc., 178 A.D.3d 977, 112 N.Y.S.3d 584 ; Rodolico v. Rubin & Licatesi, P.C., 114 A.D.3d 923, 924–925, 981 N.Y.S.2d 144 ). "A motion pursuant to CPLR 3211(a)(5) to dismiss a complaint on the ground of payment may be granted where the documentary evidence establishes the defense of payment as a matter of law" ( Parkoff v. Stavsky, 109 A.D.3d 646, 647, 970 N.Y.S.2d 817 ).

We agree with the Supreme Court's determination denying that branch of the defendant's motion which was to dismiss so much of the first cause of action as was predicated on extra work claims totaling $521,480.16 on the ground that those claims were paid. The evidence submitted by the defendant in support of this branch of its motion did not conclusively prove that it paid the plaintiff (see id. at 647, 970 N.Y.S.2d 817 ). Additionally, the defendant was not entitled to dismissal of these claims based on a release found in the change orders associated with these claims. The language of the release affects the plaintiff's right to litigate the amount of money or extension of time associated with a change order, not the plaintiff's right to enforce the defendant's obligation to pay the amount of money or grant the extension of time found in each change order.

We also agree with the Supreme Court's determination denying that branch of the defendant's motion which was pursuant to CPLR 3211(a)(1) to dismiss the second cause of action on the ground that the plaintiff failed to provide timely notice of the condition causing a delay as is required in the contract between the parties, because "[t]he plain terms of the subject clause of the parties' contract provide that the consequence of such a failure is denial of a request for a schedule change" ( Arnell Constr. Corp. v. New York City Sch. Constr. Auth., 177 A.D.3d 595, 597, 112 N.Y.S.3d 169 ). Furthermore, the affidavit submitted by the defendant in support of that branch of its motion is not documentary evidence within the meaning of CPLR 3211(a)(1) (see Granada Condominium III Assn. v. Palomino, 78 A.D.3d 996, 997, 913 N.Y.S.2d 668 ).

We disagree, however, with the Supreme Court's denial of that branch of the defendant's motion which was to dismiss so much of the first cause of action as was predicated on extra work claims totaling $129,338.27 on the ground that the plaintiff failed to file timely notices of claim. Public Authorities Law § 1744(2) requires the plaintiff to serve a notice of claim upon the defendant within three months after the accrual of such claim. Under the version of this statute that was in effect over the course of this contract, a claim accrued when it was ascertainable (see C.S.A. Contr. Corp. v. New York City School Constr. Auth., 5 N.Y.3d 189, 800 N.Y.S.2d 123, 833 N.E.2d 266 ; AMCC Corp. v. New York City Sch. Contr. Auth., 154 A.D.3d 673, 675, 62 N.Y.S.3d 430 ; Kafka Constr., Inc. v. New York City Sch. Constr. Auth., 125 A.D.3d 933, 5 N.Y.S.3d 167 ). "Although the determination of the date on which damages are ascertainable may vary based on the facts and circumstances of each particular case, ‘it generally has been recognized that damages are ascertainable once the work is substantially completed or a detailed invoice of the work performed is submitted’ " ( C.S.A. Contr. Corp. v. New York City School Constr. Auth., 5 N.Y.3d at 192, 800 N.Y.S.2d 123, 833 N.E.2d 266, quoting New York City School Constr. Auth. v. Kallen & Lemelson, 290 A.D.2d 497, 497, 736 N.Y.S.2d 259 ).

Here, the defendant submitted evidence, in the form of detailed invoices from the plaintiff, that damages were ascertainable for change orders 28, 35, and 61 on March 8, 2016, February 2, 2016, and February 2, 2016, respectively. The plaintiff's March 2017 notice of claim was, accordingly, untimely under Public Authorities Law § 1744(2) with respect to these claims (see AMCC Corp. v. New York City Sch. Contr. Auth., 154 A.D.3d at 675, 62 N.Y.S.3d 430 ; Kafka Constr., Inc. v. New York City Sch. Constr. Auth., 125 A.D.3d 933, 5 N.Y.S.3d 167 ).

We agree with the Supreme Court's determination denying that branch of the defendant's motion which was to dismiss so much of the second cause of action as was predicated on delay damages totaling $3,371,955.85 on the ground that the plaintiff failed to file a timely notice of claim. The evidence relied on by the defendant in support of this branch of its motion did not conclusively prove that the plaintiff's claims for delay damages accrued more than three months prior to the plaintiff filing a notice of claim (see CPLR 3211[a][1] ; Public Authorities Law § 1744[2] ).

The defendant's remaining contention, raised for the first time on appeal, is not properly before us (see Hudson City Sav. Bank, FSB v. Schoenfeld, 172 A.D.3d 692, 99 N.Y.S.3d 389 ).

LEVENTHAL, J.P., ROMAN, COHEN and MILLER, JJ., concur.


Summaries of

Arnell Constr. Corp. v. N.Y.C. Sch. Constr. Auth.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Aug 12, 2020
186 A.D.3d 540 (N.Y. App. Div. 2020)
Case details for

Arnell Constr. Corp. v. N.Y.C. Sch. Constr. Auth.

Case Details

Full title:Arnell Construction Corporation, respondent, v. New York City School…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department

Date published: Aug 12, 2020

Citations

186 A.D.3d 540 (N.Y. App. Div. 2020)
186 A.D.3d 540
2020 N.Y. Slip Op. 4445

Citing Cases

U.S. Bank v. Zaccagnino

"The proponent of a summary judgment motion must make a prima facie showing of entitlement to judgment as a…

Siemens Indus. v. Skanska Walsh Design-Build Joint Venture

"A party is entitled to dismissal pursuant to CPLR 3211(a)(1) on the ground that a defense is founded on…