Judgment, Supreme Court, New York County (Suzanne Adams, J.), entered June 27, 2022, in favor of plaintiff and against defendants in the amount of $641,033.40, and bringing up for review an order, same court and Justice, entered on or about June 17, 2022, which granted plaintiff's oral application for summary judgment on his claims for fraud, conversion and constructive trust, unanimously reversed, on the law, without costs, the judgment vacated, and the matter remanded for further proceedings in accordance with this Court's decision in Adago v. Sy, 205 A.D.3d 602, 169 N.Y.S.3d 610 [1st Dept. 2022]. Appeal from the order entered on or about June 17, 2022, unanimously dismissed, without costs, as subsumed in the appeal from the judgment.
During a hearing following remand to determine whether a memorandum of understanding was "permeated with fraud" so that its arbitration clause was void ( Adago, 205 A.D.3d 602, 169 N.Y.S.3d 610 ), plaintiff requested summary judgment on his claims against defendants and argued that defendants were in default.
The court erred in granting plaintiff summary judgment absent any motion made on notice pursuant to CPLR 3212, and before issue had been joined by service of an answer (see CPLR 3212[a] ; City of Rochester v. Chiarella, 65 N.Y.2d 92, 101, 490 N.Y.S.2d 174, 479 N.E.2d 810 [1985] ; SHG Resources, LLC v. SYTR Real Estate Holdings LLC, 201 A.D.3d 610, 611, 162 N.Y.S.3d 325 [1st Dept. 2022] ). "[T]his is not a case where both sides deliberately lay bare their proof and make clear that they were charting a summary judgment course" pursuant to CPLR 3211(c) ( American Infertility of N.Y., P.C. v. Kushnir, 187 A.D.3d 629, 630, 131 N.Y.S.3d 153 [1st Dept. 2020] [internal quotation marks omitted]). Even if, as plaintiff urges, the order actually granted him a default judgment against defendants since they had failed to answer at the time of the hearing, which was 22 days after this Court issued its order, which resulted in ending the stay of the action pending arbitration ( Adago, 205 A.D.3d at 602, 169 N.Y.S.3d 610 ), plaintiff failed to make a motion for a default judgment on notice to defendants, in compliance with CPLR 3215(c) and (g), and the order appealed from does not state that such relief was granted.
The matter is remanded for fact finding, based on the evidence proffered at the June 16, 2022 hearing, concerning the issue of whether the memorandum of understanding was permeated with fraud, so that arbitration of the claims against the corporate defendant may not be compelled, to the extent that issue has not become academic.