416 W 25TH STREET LENDER LLC, et al., Plaintiff–Appellant, v. 416 W. 25TH STREET ASSOCIATES, LLC, et al., Defendants–Respondents, New York City Environmental Control Board, et al., Defendants.

Katsky Korins LLP, New York (Robert A. Abrams and Steven H. Newman of counsel), for appellant. Oved & Oved LLP, New York (Aaron J. Solomon of counsel), for respondents.


Katsky Korins LLP, New York (Robert A. Abrams and Steven H. Newman of counsel), for appellant.

Oved & Oved LLP, New York (Aaron J. Solomon of counsel), for respondents.

Renwick, J.P., Richter, Mazzarelli, Singh, JJ.

Order, Supreme Court, New York County (Arlene P. Bluth, J.), entered on or about May 14, 2019, which, inter alia, granted the motion by defendants 416 W. 25th Street Associates, LLC and Andreas Steiner (collectively, defendants) to dismiss the complaint, unanimously affirmed, without costs.

Plaintiff's notice to cure was deficient, as it failed to inform the borrower of the 30–day period to cure, which was a critical portion of section 21 of the Consolidation, Extension and Modification Agreement (CEMA) (see Filmtrucks, Inc. v. Express Indus. & Term. Corp. , 127 A.D.2d 509, 510, 511 N.Y.S.2d 862 [1st Dept. 1987] ; PNC Capital Recovery v. Mechanical Parking Sys. , 283 A.D.2d 268, 271, 726 N.Y.S.2d 394 [1st Dept. 2001], appeal dismissed 98 N.Y.2d 763, 751 N.Y.S.2d 846, 781 N.E.2d 911 [2002] ).

Plaintiff contends that even if paragraph 21 of the CEMA required written notice that defendant borrower had 30–days to cure its non-monetary default, such written notice was provided to borrower by virtue of its June 28, 2018 email sent in response to the default letter, which stated: "Our position is that the lien needs to be removed within 30 days of the letter we sent you." Plaintiff additionally asserts that borrower was provided with more than 30 days to cure its default. The CEMA, however, requires written notice to be sent by hand; via certified mail, return receipt requested; or by overnight courier with evidence of receipt. The email did not meet this requirement, or the specificity required of a notice to cure (see Filmtrucks, Inc. at 510–511, 511 N.Y.S.2d 862 ).

The motion court should not have reached the merits of the foreclosure claim, raised for the first time on reply, and we decline to address the arguments regarding that claim.


Summaries of

416 W 25TH St. Lender LLC v. 416 W. 25TH St. Assocs.

Appellate Division of the Supreme Court of the State of New York
Apr 2, 2020
182 A.D.3d 432 (N.Y. App. Div. 2020)
Case details for

416 W 25TH St. Lender LLC v. 416 W. 25TH St. Assocs.

Case Details

Full title:416 W 25th Street Lender LLC, Plaintiff-Appellant, v. 416 W. 25th Street…

Court:Appellate Division of the Supreme Court of the State of New York

Date published: Apr 2, 2020

Citations

182 A.D.3d 432 (N.Y. App. Div. 2020)
2020 N.Y. Slip Op. 2183
119 N.Y.S.3d 862

Citing Cases

Fusion Auto Fin. v. Long Island Raceway, LLC

We agree with the District Court that the notice to cure was defective, albeit on a different ground. As…

Corbett & Dullea Realty, LLC v Muss Dev., LLC

Therefore, VCPRE has waived this argument because it raised it for the first time on reply, and this court…